22627 W SYLVAN ST 91367
Certificate Information: 22627 W SYLVAN ST 91367
- Application / Permit
- 16014-20000-02803
- Plan Check / Job No.
- B16VN07977
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT. GARAGE & BREEZEWAY TO RECREATION ROOM AND ADD NEW ATTACHED 2-CAR CARPORT. NEW 3'4"X6'2" LAUNDRY ROOM.
- Permit Issued
- Issued on 10/7/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2016 | RODNEY SAMIIAN |
| Corrections Issued | 6/22/2016 | RODNEY SAMIIAN |
| Quality Review Completed | 6/24/2016 | STEVEN KIM |
| Building Plans Picked Up | 6/28/2016 | APPLICANT |
| Green Plans Picked Up | 8/1/2016 | APPLICANT |
| Applicant returned to address corrections | 8/16/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 9/28/2016 | RODNEY SAMIIAN |
| Plan Check Approved | 10/4/2016 | RODNEY SAMIIAN |
| Issued | 10/7/2016 | LADBS |
| CofO in Progress | 6/13/2023 | TROY SANDERS |
| No Progress | 1/8/2025 | HENRY KIM |
| CofO in Progress | 1/8/2025 | HENRY KIM |
| Permit Finaled | 7/31/2025 | DANIEL ORRANTE |
| CofO Issued | 7/31/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2016 | ERIK MUNOZ |
| Roof/Waste drainage to street | Cleared | 7/27/2016 | ERIK MUNOZ |
| Green Code | Cleared | 8/16/2016 | ROLLIN GETTLE III |
| Private sewage disp. approval | Cleared | 9/21/2016 | BARTON HOLMES |
Contact Information
| Architect | Diradourian, Richard C; Lic. No.: C10336 | 2618 HERMOSA AVENUE MONTROSE, CA 91020 |
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2016 | No Access for Inspection | FRED HANNUM |
| ELECTRICAL-Rough | 12/20/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 2/24/2022 | Approved | TROY SANDERS |
| Green Building Rough | 2/24/2022 | Approved | TROY SANDERS |
| Final | 6/2/2023 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 6/2/2023 | Approved | TROY SANDERS |
| Green Building Final | 6/2/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 6/2/2023 | Approved | TROY SANDERS |
| Final | 6/13/2023 | OK to Issue CofO | TROY SANDERS |