16560 W CHATTANOOGA PL 90272
Certificate Information: 16560 W CHATTANOOGA PL 90272
- Application / Permit
- 16014-20000-01425
- Plan Check / Job No.
- B16VN04241
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & MAJOR REMODEL TO (E) DWELLING. 25'4" X 43'2" IRR. SHAPE ADDITION TO FIRST FLOOR TO ADD DINING AND LIVING ROOM AND 15'6" X 43'2" IRR. SHAPE DECK AT REAR. 60' X 39' IRR. SHAPE ADDITION OF 2ND FLOOR TO ADD 3 BEDROOMS, 3 BATHROOMS, AND DECK. ENTIRE DWELLING SHALL BE FULLY SPRINKLERED. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/5/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2016 | JEFFREY TANGONAN |
| Green Plans Picked Up | 4/18/2016 | APPLICANT |
| Corrections Issued | 4/20/2016 | JEFFREY TANGONAN |
| Quality Review Completed | 4/20/2016 | STEVEN KIM |
| Building Plans Picked Up | 4/22/2016 | APPLICANT |
| Applicant returned to address corrections | 7/29/2016 | JEFFREY TANGONAN |
| Plan Check Approved | 5/24/2018 | JEFFREY TANGONAN |
| Issued | 6/5/2018 | LADBS |
| CofO in Progress | 12/12/2023 | EVAN COOPER |
| Permit Finaled | 12/28/2023 | DANIEL ORRANTE |
| CofO Issued | 12/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/28/2016 | ADRIAN SANCHEZ |
| Distance to fire station | Cleared | 5/4/2016 | JOHN DALLAS |
| Hydrant and Access approval | Cleared | 5/4/2016 | JOHN DALLAS |
| Green Code | Cleared | 6/21/2016 | RICHARD DOCKUS |
| ZA Case | Cleared | 7/29/2016 | RICK TORRES |
| Low Impact Development | Cleared | 8/23/2016 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 8/24/2016 | HUGO RICO |
| GPI Written Notices | Cleared | 11/18/2016 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 11/18/2016 | JEFFREY TANGONAN |
| Coastal Zone | Cleared | 5/24/2018 | DAISY BENICIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| BOBBY KEY, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/4/2018 | Partial Inspection | MICHAEL PELHAM |
| Pre-Inspection | 12/3/2018 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 1/18/2019 | Not Ready for Inspection | ANDREW NAVE |
| Piling/Pier/Caisson | 3/11/2019 | Partial Inspection | ANDREW NAVE |
| PLUMBING-Rough | 3/22/2019 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 4/12/2019 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 5/28/2019 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/12/2019 | Corrections Issued | ANDREW NAVE |
| Reinforced Concrete Frame | 6/18/2019 | Corrections Issued | ANDREW NAVE |
| Reinforced Concrete Frame | 6/24/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 7/15/2019 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 7/17/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 9/6/2019 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 9/9/2019 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 9/10/2019 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 9/16/2019 | No Access for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 9/16/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/3/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/21/2019 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 11/27/2019 | No Access for Inspection | ROBERT SHELLY |
| Wood Frame | 1/8/2020 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 1/10/2020 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 4/14/2021 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Corrections Issued | ANDREW NAVE |
| Gas Test | 4/14/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 4/14/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 4/14/2021 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 4/16/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 4/16/2021 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 6/3/2021 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 6/15/2021 | Corrections Issued | ANDREW NAVE |
| Wood Frame | 6/15/2021 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/28/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 6/28/2021 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 6/28/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 7/22/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 7/22/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 7/22/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | ANDREW NAVE |
| Insulation | 8/9/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/20/2021 | No Access for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 8/24/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 12/3/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Shower Pan | 12/3/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/13/2021 | Corrections Issued | BRENDAN LOONEY |
| Shower Pan | 12/13/2021 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/28/2022 | Approved | ANDREW NAVE |
| Shower Pan | 2/28/2022 | Approved | ANDREW NAVE |
| Pre-Inspection | 5/3/2022 | Approved | ANDREW NAVE |
| Gas Test | 9/12/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 9/12/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 9/12/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/29/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 11/29/2022 | Partial Approval | BRENDAN LOONEY |
| Green Building Final | 12/12/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 12/12/2022 | Corrections Issued | BRENDAN LOONEY |
| Smoke Detectors | 12/12/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/24/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 1/24/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 1/24/2023 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 1/24/2023 | Approved | BRENDAN LOONEY |
| Final | 11/29/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 11/29/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | EVAN COOPER |
| Final | 12/7/2023 | No Access for Inspection | EVAN COOPER |
| Final | 12/12/2023 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 12/12/2023 | Approved | EVAN COOPER |