3359 S COLBERT AVE 90066
Certificate Information: 3359 S COLBERT AVE 90066
- Application / Permit
- 16014-20000-00889
- Plan Check / Job No.
- B16VN02686
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 6'0" x 33'6", addition of 16'0" x 15'7", irregular addition of 8'0' x 22'6", and enclose 3'6" x 9'0" covered patio to the SFD. Exterior remodel, interior remodel, relocate bedroom, raise floor in the family room, and install (3) skylights.
- Permit Issued
- Issued on 3/18/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2016 | JOSE RODRIGUEZ |
| Corrections Issued | 3/1/2016 | JOSE RODRIGUEZ |
| Plan Check Approved | 3/17/2016 | GUANG MIN TUNG |
| Issued | 3/18/2016 | LADBS |
| CofO in Progress | 10/23/2025 | KIRK SANDERS |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
| CofO Issued | 10/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2016 | SEVAK ISAKHAYAN |
| Low Impact Development | Cleared | 3/9/2016 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 3/9/2016 | SEVAK ISAKHAYAN |
| Grading Pre-Inspection | Cleared | 3/17/2016 | JOSE RODRIGUEZ |
| Miscellaneous | Cleared | 3/17/2016 | TAO YANG |
Contact Information
| Contractor | Yd Construction & Development Inc; Lic. No.: 839200-B | 14923 OXNARD ST VAN NUYS, CA 91411 |
| Engineer | Almalla, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/21/2016 | Conditional Approval | MARVIN GODFREY |
| Excavation/Setback/Form/Re-Bar | 5/6/2016 | Approved | MARVIN GODFREY |
| Wood Frame | 5/18/2016 | Approved | MARVIN GODFREY |
| PLUMBING-Rough | 10/4/2016 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/27/2016 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 10/27/2016 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2016 | Partial Approval | MICHAEL PELHAM |
| Green Building Rough | 10/27/2016 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 10/27/2016 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 10/27/2016 | Approved | MICHAEL PELHAM |
| Rough-Elec/Plmb/HVAC | 10/27/2016 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 10/27/2016 | Partial Approval | MICHAEL PELHAM |
| Wood Frame | 10/27/2016 | Conditional Approval | MICHAEL PELHAM |
| Insulation | 12/19/2016 | Approved | MICHAEL PELHAM |
| Shower Pan | 12/19/2016 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 12/28/2016 | Approved | MICHAEL PELHAM |
| Green Building Rough | 12/28/2016 | Approved | MICHAEL PELHAM |
| Shower Pan | 12/28/2016 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 1/25/2017 | Partial Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/31/2017 | Approved | MICHAEL PELHAM |
| Final | 5/31/2017 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/31/2017 | Approved | MICHAEL PELHAM |
| Green Building Final | 5/31/2017 | Corrections Issued | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 5/31/2017 | SGSOV Not Ready | MICHAEL PELHAM |
| Smoke Detectors | 5/31/2017 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 6/6/2025 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Final | 10/1/2025 | Corrections Issued | KIRK SANDERS |
| Final | 10/1/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 10/1/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 10/1/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 10/1/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/22/2025 | Approved | KIRK SANDERS |
| Final | 10/22/2025 | OK to Issue CofO | KIRK SANDERS |