612 W 43RD PL 90037
Certificate Information: 612 W 43RD PL 90037
- Application / Permit
- 16014-20000-00032
- Plan Check / Job No.
- B16VN00123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- Irregular addition of 9'8" x 23'2" and conversion the existing detached storage building to an accessory living quaters . Remove an irregular 24'0" x 14'0" portion of the existing building. Fully sprinklered per NFPA 13D. "Air filtration system with filters capable of achieving a MERV of at least 11 or better shall be installed." (See comments).
- Permit Issued
- Issued on 3/1/2016
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2016 | JOSE RODRIGUEZ |
| Corrections Issued | 1/6/2016 | JOSE RODRIGUEZ |
| Plan Check Approved | 1/27/2016 | JOSE RODRIGUEZ |
| Issued | 3/1/2016 | LADBS |
| CofO in Progress | 2/10/2026 | SABAS ALONSO |
| No Progress | 2/10/2026 | MICHAEL LEWIS |
| CofO in Progress | 2/10/2026 | MICHAEL LEWIS |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
| CofO Issued | 2/10/2026 | DEROLD HAUFF |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2016 | RICHARD SOUTHERLAND |
| Hydrant and Access approval | Cleared | 1/27/2016 | DOMINIQUE MEDINA |
| Miscellaneous | Cleared | 1/27/2016 | ANNA VIDAL |
| Roof/Waste drainage to street | Cleared | 1/27/2016 | RICHARD SOUTHERLAND |
| Sewer availability | Cleared | 1/27/2016 | RICHARD SOUTHERLAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2016 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/16/2016 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/17/2016 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/7/2016 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/7/2016 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/7/2016 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/7/2016 | Approved | ENRIQUE MIRELES |
| Insulation | 7/12/2016 | Corrections Issued | RICHARD VENTURA |
| Drywall Nailing | 7/14/2016 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/14/2016 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/18/2016 | Approved | ENRIQUE MIRELES |
| Final | 8/24/2016 | Conditional Approval | ENRIQUE MIRELES |
| Green Building Final | 8/24/2016 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/24/2016 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/24/2016 | Approved | ENRIQUE MIRELES |
| Final | 8/26/2016 | Conditional Approval | ENRIQUE MIRELES |
| Final | 8/26/2024 | Corrections Issued | SABAS ALONSO |
| Pre-Inspection | 11/19/2024 | Corrections Issued | SABAS ALONSO |
| Final | 12/4/2025 | Corrections Issued | SABAS ALONSO |
| Final | 2/9/2026 | OK to Issue CofO | SABAS ALONSO |