382 WORLD WAY 90045

Certificate Information: 382 WORLD WAY 90045

Application / Permit
16014-10022-06005
Plan Check / Job No.
B19LA07953
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
SUPPLEMENTAL PERMIT TO 16014-10000-06005 FOR DEFERRED DESIGN ITEM - INSTALLATION OF THE STEEL FRAMING PLATFORMS FOR THE SUPPORT OF THE BAGGAGE HANDLING CONVEYOR SYSTEM.
Permit Issued
Issued on 10/18/2019
Issuing Office
Metro
Current Status
Permit Finaled on 3/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2019 APPLICANT
Assigned to Plan Check Engineer 4/24/2019 EDUARDO RODRIGUEZ
Corrections Issued 5/1/2019 EDUARDO RODRIGUEZ
Quality Review Completed 5/15/2019 MINYE PAK
Applicant returned to address corrections 6/18/2019 EDUARDO RODRIGUEZ
Plan Check Approved 10/8/2019 EDUARDO RODRIGUEZ
Issued 10/18/2019 LADBS
Permit Finaled 3/11/2021 JONATHAN ALLEN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Vanderlande Industries Inc; Lic. No.: 843620-A 1975 WEST OAK PARKWAY      MARRIETTA, GA 30062
Engineer Scott,, Andrew Nicholas; Lic. No.: S4809 375 BEALE STREETE STE 500      SAN FRANCISCO, CA 94105

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2019 Partial Approval ALBERT COMISARI
Deputy Reinf. Concrete 12/3/2019 Partial Approval ALBERT COMISARI
Pre-Inspection 12/5/2019 Partial Approval ALBERT COMISARI
Deputy Reinf. Concrete 12/20/2019 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/6/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/6/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/7/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/7/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/14/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/14/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/15/2020 Conditional Approval ALBERT COMISARI
Deputy Reinf. Concrete 1/15/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/15/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/16/2020 Conditional Approval ALBERT COMISARI
Deputy Reinf. Concrete 1/16/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/16/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/17/2020 Conditional Approval ALBERT COMISARI
Deputy Reinf. Concrete 1/17/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/17/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/21/2020 Conditional Approval ALBERT COMISARI
Deputy Reinf. Concrete 1/21/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 1/21/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/22/2020 Conditional Approval ALBERT COMISARI
Deputy Reinf. Concrete 1/22/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 1/31/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 2/3/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 2/4/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 2/5/2020 Conditional Approval ALBERT COMISARI
Deputy Drilled-In Anchors 2/6/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 6/19/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 6/22/2020 Partial Approval ALBERT COMISARI
Deputy Drilled-In Anchors 6/26/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 6/26/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 6/29/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 6/30/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 7/1/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 7/2/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 7/6/2020 Approved JONATHAN ALLEN
Deputy Steel/Welding 7/7/2020 Conditional Approval ALBERT COMISARI
Deputy Steel/Welding 7/8/2020 Conditional Approval JONATHAN ALLEN
Deputy Steel/Welding 7/9/2020 Conditional Approval ALBERT COMISARI
Final 7/29/2020 Not Ready for Inspection ALBERT COMISARI