1501 S PACIFIC AVE 90291
Certificate Information: 1501 S PACIFIC AVE 90291
- Application / Permit
- 16014-10002-05179
- Plan Check / Job No.
- B20LA06991
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- SUPPLEMENTAL PERMIT TO 16014-10000-05179: CONVERT RETAIL PORTION TO RESTAURANT PER DIR 2018-4410-CDP-SPP/ZA 2018-3595-CU-CUB-ZV.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/17/2020 | LAWRENCE QUIRANTE |
| Quality Review Completed | 6/22/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 6/29/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2021 | LAWRENCE QUIRANTE |
| Disabled Access Plans Picked Up | 8/24/2021 | APPLICANT |
| Applicant returned to address corrections | 10/19/2021 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 2/17/2022 | APPLICANT |
| Applicant returned to address corrections | 3/31/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/4/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/5/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/11/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 5/18/2022 | LAWRENCE QUIRANTE |
| Issued | 6/17/2022 | APPLICANT |
| Permit Finaled | 7/30/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 7/23/2020 | DINAH GARIN |
| Sewer availability | Cleared | 8/27/2020 | DINAH GARIN |
| Green Code | Cleared | 9/16/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 10/15/2020 | LAWRENCE QUIRANTE |
| Coastal Zone | Cleared | 5/26/2021 | LAUREN PADICK |
| Comm Cor/Mini-Mall | Cleared | 5/26/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 5/26/2021 | LAUREN PADICK |
| Specific Plan | Cleared | 5/26/2021 | LAUREN PADICK |
| ZA Case | Cleared | 5/26/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | SAUL GARCIA |
| Address approval | Cleared | 6/3/2021 | DINAH GARIN |
| Food Service Establishment | Cleared | 6/10/2021 | PAWAN VERMA |
| Specific Plan | Cleared | 6/22/2021 | KEVIN ARUCAN |
| Specific Plan | Cleared | 6/22/2021 | KEVIN ARUCAN |
| Food establishment approval | Cleared | 7/2/2021 | LACDHS APPROVED |
| Food establishment approval | Cleared | 7/2/2021 | LACDHS APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 8/11/2021 | ANDREW KO |
Contact Information
| Architect | Thibodeau, Robert E; Lic. No.: C25585 | 529 CALIFORNIA AVENUE VENICE, CA 90291 |
| Contractor | Build Group Construction Company Inc; Lic. No.: 1015855-B | 1212 ABBOT KINNEY BLVD #A LOS ANGELES, CA 90291 |
| Engineer | Howe, Carl William; Lic. No.: C44773 | 3347 MOTOR AVE STE 200 C W HOWE PARTNERS INC. LOS ANGELES, CA 90034 |
| Engineer | Larocca, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 7/5/2022 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 7/13/2022 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 7/19/2022 | Not Ready for Inspection | GRANT WOODS |
| Deputy Wood Construction | 7/20/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 7/21/2022 | Partial Inspection | SORIN CIRSTOIU |
| Masonry Wall/Backfill | 7/22/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 8/1/2022 | Partial Approval | SORIN CIRSTOIU |
| Pre-Inspection | 2/27/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| METHANE-Final | 4/29/2024 | Approved | FARHAD DADBIN |
| METHANE-Rough | 4/29/2024 | Approved | FARHAD DADBIN |
| Reinforced Masonry Frame | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Masonry Frame | 2/27/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 2/27/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 4/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Masonry Frame | 4/11/2025 | Approved | FARHAD DADBIN |
| Smoke Detectors | 4/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 7/30/2025 | Permit Finaled | FARHAD DADBIN |
| Smoke Detectors | 7/30/2025 | Approved | FARHAD DADBIN |