78 E MARKET ST 90291
Certificate Information: 78 E MARKET ST 90291
- Application / Permit
- 16014-10001-05179
- Plan Check / Job No.
- B18LA18256
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- SUPPLEMENTAL TO PERMIT # 16014-10000-05179: TO REVISE ROOF, FLOOR LAYOUT AND STRUCTURAL. <PERMIT FEES PAID UNDER 16014-10000-05179><NO CHANGE IN VALUATION>
- Permit Issued
- Issued on 1/2/2019
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2018 | APPLICANT |
| Green Plans Picked Up | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/24/2018 | LAWRENCE QUIRANTE |
| Disabled Access Plans Picked Up | 9/26/2018 | APPLICANT |
| Quality Review Completed | 9/28/2018 | GARO TELMI |
| Building Plans Picked Up | 10/18/2018 | APPLICANT |
| Applicant returned to address corrections | 11/15/2018 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/30/2018 | LAWRENCE QUIRANTE |
| Plan Check Approved | 12/18/2018 | LAWRENCE QUIRANTE |
| Issued | 1/2/2019 | LADBS |
| Permit Finaled | 7/30/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Coastal Zone | Cleared | 11/27/2018 | MOTOUMI SASAKI |
| Specific Plan | Cleared | 11/27/2018 | MOTOUMI SASAKI |
| ZA Case | Cleared | 11/27/2018 | MOTOUMI SASAKI |
| Green Code | Cleared | 11/29/2018 | KHEDER ALRAZAA |
| DAS Clearance | Cleared | 11/30/2018 | LAWRENCE QUIRANTE |
Contact Information
| Architect | Thibodeau, Robert E; Lic. No.: C25585 | 529 CALIFORNIA AVENUE VENICE, CA 90291 |
| Contractor | Lyons Glenn Construction Inc; Lic. No.: 640172-B | 1335 APPLETON WAY VENICE, CA 90291 |
| Engineer | Howe, Carl William; Lic. No.: C44773 | 3347 MOTOR AVE STE 200 C W HOWE PARTNERS INC. LOS ANGELES, CA 90034 |
| Engineer | Larocca, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/15/2020 | Approved | JASON BORUTA |
| Deputy Reinf. Concrete | 1/7/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 1/14/2022 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 1/20/2022 | Conditional Approval | JOHN DODGE |
| Deputy Drilled-In Anchors | 1/28/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/28/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/7/2022 | No Access for Inspection | JOHN DODGE |
| Deputy Steel/Welding | 3/1/2022 | Conditional Approval | JOHN DODGE |
| Deputy Drilled-In Anchors | 3/3/2022 | Conditional Approval | JOHN DODGE |
| Deputy Steel/Welding | 3/3/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Masonry | 3/7/2022 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 3/9/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 3/15/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 3/16/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 3/17/2022 | Conditional Approval | JOHN DODGE |
| Deputy Steel/Welding | 3/17/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 3/24/2022 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 3/30/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 4/5/2022 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 4/11/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 4/27/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/5/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/10/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/12/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/23/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/27/2022 | Conditional Approval | DAVID TSAU |
| Final | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 2/28/2025 | Approved | FARHAD DADBIN |
| Final | 4/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 7/30/2025 | Permit Finaled | FARHAD DADBIN |