13823 W DESMOND ST 91331

Certificate Information: 13823 W DESMOND ST 91331

Application / Permit
16014-10001-04503
Plan Check / Job No.
B19LA15863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental permit to 16014-20000-04503 to change scope of work - 2- story addition to garage/ recreation room and convert whole building into accessory dwelling unit per LAMC 12.22A.33(c)-(d) (remove exterior stair and add new interior stair and change interior floor plan layout). Provide 2 open parking stalls. All work per engineer design.
Permit Issued
Issued on 12/22/2020
Issuing Office
Valley
Current Status
Permit Finaled on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 SAM CHANG
Corrections Issued 8/27/2019 SAM CHANG
Quality Review Completed 8/31/2019 STANLEY RAAP
Building Plans Picked Up 9/11/2019 APPLICANT
Green Plans Picked Up 9/11/2019 APPLICANT
Applicant returned to address corrections 9/16/2020 SAM CHANG
Plan Check Approved 11/23/2020 SAM CHANG
Issued 12/22/2020 APPLICANT
Permit Finaled 12/23/2021 MICHEL ABAJAN

Permit Application Clearance Information

Address approval Cleared 11/26/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/26/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/26/2019 GUILLERMO PETRA
Sewer availability Cleared 11/26/2019 GUILLERMO PETRA
Construction near power lines Cleared 12/26/2019 RIDWAN HARDY
Green Code Cleared 6/12/2020 SARAH ABOULHOSN
Clean Up Green Up Cleared 7/14/2020 LAUREN PADICK
Hydrant and Access approval Cleared 8/5/2020 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/13/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/20/2021 Approved MICHEL ABAJAN
METHANE-Barrier 1/20/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 1/20/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/7/2021 Approved MICHEL ABAJAN
Underground Mechanical 5/7/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/20/2021 Approved MICHEL ABAJAN
Final 10/20/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 10/20/2021 Approved MICHEL ABAJAN
Green Building Rough 10/20/2021 Approved MICHEL ABAJAN
METHANE-Final 10/20/2021 Approved MICHEL ABAJAN
METHANE-Rough 10/20/2021 Approved MICHEL ABAJAN
Smoke Detectors 10/20/2021 Approved MICHEL ABAJAN