2224 N WINONA BLVD 90027
Certificate Information: 2224 N WINONA BLVD 90027
- Application / Permit
- 16014-10000-06125
- Plan Check / Job No.
- B16LA20410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAJOR REMODELING TO EXISTING 2 STORY HOUSE. FIRE SPRINKLER IS REQUIRED FOR ENTIRE BUILDING.
- Permit Issued
- Issued on 4/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2017 | YOUNG KIM |
| Corrections Issued | 2/23/2017 | YOUNG KIM |
| Quality Review Completed | 3/6/2017 | BILL STUTSMAN |
| Green Plans Picked Up | 3/10/2017 | APPLICANT |
| Applicant returned to address corrections | 6/13/2017 | YOUNG KIM |
| Applicant returned to address corrections | 7/12/2017 | YOUNG KIM |
| Plan Check Approved | 8/3/2017 | YOUNG KIM |
| Issued | 4/23/2021 | APPLICANT |
| Building Plans Picked Up | 4/29/2021 | APPLICANT |
| CofO in Progress | 9/15/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/13/2017 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 6/13/2017 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 6/13/2017 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2017 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 6/13/2017 | ROBERT DUFF |
| Sewer availability | Cleared | 6/13/2017 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 7/3/2017 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 7/3/2017 | CELINA MORENO |
| Green Code | Cleared | 7/5/2017 | MICKEY YAMASHITA |
| Distance to fire station | Cleared | 1/10/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/17/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/21/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/2/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Approved | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 6/7/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 8/3/2021 | Conditional Approval | BRIAN SULLIVAN |
| Gas Test | 8/25/2021 | Partial Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 8/25/2021 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/1/2021 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 9/1/2021 | Not Ready for Inspection | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 9/1/2021 | Corrections Issued | ALAN MORELOS |
| Verify Sprinkler Sign Off | 9/1/2021 | Not Ready for Inspection | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 9/2/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 9/7/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 9/7/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 9/13/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 9/13/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/13/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 9/13/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/15/2021 | Approved | RAUL BARAJAS |
| Service/Power Release | 10/22/2021 | Approved | SCOTT FINNILA |
| Sewer | 11/17/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 9/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 9/14/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |