17261 W SUNBURST ST 91325
Certificate Information: 17261 W SUNBURST ST 91325
- Application / Permit
- 16014-10000-05460
- Plan Check / Job No.
- B16LA18012
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO BEDROOM WITH 3/ 4 BATHROOM AND CLOSET. ADD NEW ATTACHED CARPORT ( 23' X 31').
- Permit Issued
- Issued on 4/27/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2016 | CRISTINA SALAZAR |
| Corrections Issued | 11/16/2016 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/16/2016 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 12/21/2016 | CRISTINA SALAZAR |
| Issued | 4/27/2017 | LADBS |
| CofO in Progress | 9/13/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 11/18/2024 | DANIEL ORRANTE |
| CofO Issued | 11/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/14/2016 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2016 | RAVIL MANAPOV |
| Permit | Cleared | 12/16/2016 | RAVIL MANAPOV |
| Roof/Waste drainage to street | Cleared | 12/16/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 12/16/2016 | RAVIL MANAPOV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2017 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 1/11/2018 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 3/30/2018 | Partial Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/15/2020 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 6/15/2020 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 6/15/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/15/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/17/2020 | Approved | MARK JOHNSON |
| Insulation | 6/17/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 6/17/2020 | Approved | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 6/17/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 6/19/2020 | Approved | MARK JOHNSON |
| Shower Pan | 2/23/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Structural Steel Frame | 2/8/2023 | Approved | JAVIER RAMOS JR |
| Deputy Reinf. Concrete | 2/10/2023 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Final | 8/6/2024 | Approved | JAVIER RAMOS JR |
| Final | 8/6/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 8/6/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 8/6/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/6/2024 | Approved | JAVIER RAMOS JR |
| Final | 9/6/2024 | OK to Issue CofO | SALVADOR MARTINEZ |