2325 S DUXBURY CIR 90034
Certificate Information: 2325 S DUXBURY CIR 90034
- Application / Permit
- 16014-10000-05449
- Plan Check / Job No.
- B16LA17986
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF ENTRY PORCH AND VESTIBULE ON FIRST FLOOR. ADDITION OF BEDROOMS, CLOSETS, AND BATHROOMS ON SECOND FLOOR.
- Permit Issued
- Issued on 11/2/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2016 | MOHAMMAD FIROUZBAKHT |
| Corrections Issued | 12/20/2016 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 1/3/2017 | WING SUEN |
| Building Plans Picked Up | 1/10/2017 | APPLICANT |
| Green Plans Picked Up | 5/3/2018 | APPLICANT |
| Plan Check Approved | 10/10/2018 | MOHAMMAD FIROUZBAKHT |
| Issued | 11/2/2018 | LADBS |
| CofO in Progress | 10/18/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 10/22/2024 | RICHARD STEINBACH |
| CofO Issued | 10/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2018 | MICHAEL CASTILLO |
| Low Impact Development | Cleared | 6/13/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 6/13/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 8/24/2018 | NEGAR NEJAD |
| Sewer availability | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| ZI | Cleared | 8/31/2018 | SOPHIE GABEL-SCHEINBAU |
| GPI Written Notices | Cleared | 9/17/2018 | MOHAMMAD FIROUZBAKHT |
| Grading Pre-Inspection | Cleared | 9/17/2018 | MOHAMMAD FIROUZBAKHT |
Contact Information
| Architect | , ; Lic. No.: C15059 | 326 PASEO DE LA PLAYA B REDONDO BEACH, CA 90277 |
| Contractor | Owner-Builder | , |
| Geologist | , ; Lic. No.: EG1300 | 7650 HASKELL AVE D LOS ANGELES, CA 91406 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2019 | Partial Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 7/19/2019 | Partial Approval | RONALD WEBER |
| Deputy Drilled-In Anchors | 10/1/2019 | Conditional Approval | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2019 | Corrections Issued | RONALD WEBER |
| HVAC-Rough | 12/11/2019 | Not Ready for Inspection | RONALD WEBER |
| PLUMBING-Rough | 12/11/2019 | Partial Approval | RONALD WEBER |
| Deputy Wood Construction | 2/12/2020 | Conditional Approval | RONALD WEBER |
| Deputy Steel/Welding | 4/15/2020 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 6/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 6/30/2022 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 7/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/12/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/4/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/4/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/4/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/11/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2022 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 8/11/2022 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 10/14/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 11/3/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/14/2022 | Approved | JEREMY TODD |
| Drywall Nailing | 1/13/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/20/2023 | Approved | ASHLEY THOMPSON |
| Shower Pan | 3/14/2023 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 3/24/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/17/2024 | Approved | ASHLEY THOMPSON |
| Green Building Final | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 9/17/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 10/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 10/15/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 10/15/2024 | Approved | MEL KHACHATOURIAN |
| Final | 10/17/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| PLUMBING-Final | 10/17/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | MEL KHACHATOURIAN |