78 E MARKET ST 90291
Certificate Information: 78 E MARKET ST 90291
- Application / Permit
- 16014-10000-05179
- Plan Check / Job No.
- B16LA16988
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ADDITION AND REMODEL OF AN (E) MEDICAL OFFICES BUILDING AND CHANGE OF USE FROM MEDICAL OFFICES TO RETAIL WITH OFFICE SPACE PER ZA 2014-4913(CDP)(SPP). 5 ONSITE PARKING AND 4 BIKECYCLE PARKING PER ZA.
- Permit Issued
- Issued on 1/10/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Corrected on 10/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2016 | JAYDON NGUYEN |
| Green Plans Picked Up | 12/13/2016 | APPLICANT |
| Corrections Issued | 1/3/2017 | JAYDON NGUYEN |
| Quality Review Completed | 1/10/2017 | JOHN VASQUEZ |
| Building Plans Picked Up | 1/18/2017 | APPLICANT |
| Applicant returned to address corrections | 8/17/2017 | JAYDON NGUYEN |
| Applicant returned to address corrections | 9/13/2017 | JAYDON NGUYEN |
| Applicant returned to address corrections | 12/14/2017 | JAYDON NGUYEN |
| Applicant returned to address corrections | 12/20/2017 | JAYDON NGUYEN |
| Plan Check Approved | 1/2/2018 | JAYDON NGUYEN |
| Issued | 1/10/2018 | LADBS |
| CofO in Progress | 8/13/2025 | FARHAD DADBIN |
| Re-Activate Permit | 9/17/2025 | DAVID TSAU |
| CofO Issued-Status Void | 9/17/2025 | DAVID TSAU |
| Permit Finaled-Status Void | 9/17/2025 | DAVID TSAU |
| CofO Corrected-Status Void | 9/17/2025 | DAVID TSAU |
| Permit Finaled-Status Void | 9/17/2025 | DAVID TSAU |
| Re-Activate Permit | 9/24/2025 | DAVID TSAU |
| CofO Corrected-Status Void | 9/24/2025 | DAVID TSAU |
| Permit Finaled-Status Void | 9/24/2025 | DAVID TSAU |
| Re-Activate Permit | 9/30/2025 | DAVID TSAU |
| Permit Finaled | 10/8/2025 | DAVID TSAU |
| CofO Corrected | 10/8/2025 | DAVID TSAU |
| Permit Finaled | 10/8/2025 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/2/2017 | CHOI YAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2017 | ROCHELLE DUNGCA |
| Sewer availability | Cleared | 3/15/2017 | ROCHELLE DUNGCA |
| Miscellaneous | Cleared | 3/22/2017 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 9/29/2017 | ARIEL MORENO |
| Miscellaneous | Cleared | 9/29/2017 | ARIEL MORENO |
| Specific Plan | Cleared | 9/29/2017 | ARIEL MORENO |
| ZA Case | Cleared | 9/29/2017 | ARIEL MORENO |
| Green Code | Cleared | 11/9/2017 | JOHN KLARIN |
| Low Impact Development | Cleared | 12/19/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/19/2017 | EDUARDO PEDROZA |
Contact Information
| Architect | Thibodeau, Robert E; Lic. No.: C25585 | 529 CALIFORNIA AVENUE VENICE, CA 90291 |
| Contractor | Lyons Glenn Construction Inc; Lic. No.: 640172-B | 1335 APPLETON WAY VENICE, CA 90291 |
| Engineer | Howe, Carl William; Lic. No.: C44773 | 3347 MOTOR AVE STE 200 C W HOWE PARTNERS INC. LOS ANGELES, CA 90034 |
| Engineer | Larocca, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2018 | Approved | JASON BORUTA |
| Pre-Inspection | 12/6/2018 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 1/14/2020 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 10/12/2021 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 10/20/2021 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 12/14/2021 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 12/17/2021 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Partial Approval | DERRICK SPENCER |
| METHANE-Barrier | 12/21/2021 | Not Ready for Inspection | NICK LAROCCA |
| METHANE-Subgrade | 12/21/2021 | Not Ready for Inspection | NICK LAROCCA |
| Deputy Reinf. Concrete | 12/28/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 1/14/2022 | Corrections Issued | JOEY BUCHANAN |
| METHANE-Barrier | 1/14/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Subgrade | 1/14/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/19/2022 | Partial Approval | JOHN DODGE |
| METHANE-Barrier | 1/19/2022 | Approved | JOHN DODGE |
| METHANE-Subgrade | 1/19/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 1/28/2022 | Partial Approval | DERRICK SPENCER |
| METHANE-Subgrade | 1/28/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 2/9/2022 | Conditional Approval | JOHN DODGE |
| Deputy Drilled-In Anchors | 2/14/2022 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 2/22/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 3/15/2022 | Not Ready for Inspection | JOHN DODGE |
| Green Building Rough | 3/15/2022 | Approved | JOHN DODGE |
| METHANE-Rough | 3/15/2022 | Approved | JOHN DODGE |
| METHANE-Subgrade | 3/15/2022 | Approved | JOHN DODGE |
| Structural Steel Frame | 3/15/2022 | Not Ready for Inspection | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Partial Approval | JOHN DODGE |
| Reinforced Concrete Frame | 3/23/2022 | Partial Approval | JOHN DODGE |
| Light Gage Steel Frame | 4/4/2022 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 4/4/2022 | Approved | JOHN DODGE |
| Structural Steel Frame | 4/11/2022 | Corrections Issued | JEFF BYTHEWAY |
| Deputy Fireproofing | 4/19/2022 | Conditional Approval | JOHN DODGE |
| Deputy Fireproofing | 4/20/2022 | Conditional Approval | JOHN DODGE |
| Deputy Fireproofing | 4/21/2022 | Conditional Approval | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Not Ready for Inspection | JOHN DODGE |
| Deputy Wood Construction | 5/2/2022 | Conditional Approval | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 5/6/2022 | Approved | JOHN DODGE |
| Light Gage Steel Frame | 5/12/2022 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 5/18/2022 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 5/26/2022 | Partial Approval | JOHN DODGE |
| Light Gage Steel Frame | 5/26/2022 | Partial Approval | JOHN DODGE |
| Light Gage Steel Frame | 6/14/2022 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 6/21/2022 | Partial Approval | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Wood Construction | 6/24/2022 | Approved | SORIN CIRSTOIU |
| Drywall Nailing | 6/24/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 1/20/2023 | Approved | FARHAD DADBIN |
| Deputy Grading | 3/17/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 6/5/2023 | Partial Inspection | AMANUEL BERHE |
| Masonry Wall/Backfill | 6/21/2023 | Corrections Issued | FARHAD DADBIN |
| Drywall Nailing | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 4/29/2024 | Corrections Issued | FARHAD DADBIN |
| Footing/Foundation/Slab | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 4/29/2024 | Approved | FARHAD DADBIN |
| Reinforced Masonry Frame | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 4/29/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 8/7/2024 | Corrections Issued | FARHAD DADBIN |
| Pre-Inspection | 9/30/2024 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Masonry Frame | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 2/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Drywall Nailing | 4/11/2025 | Approved | FARHAD DADBIN |
| Final | 4/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 4/11/2025 | Approved | FARHAD DADBIN |
| Reinforced Masonry Frame | 4/11/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/11/2025 | Approved | FARHAD DADBIN |
| Structural Steel Frame | 4/11/2025 | Approved | FARHAD DADBIN |
| Final | 7/30/2025 | OK to Issue CofO | FARHAD DADBIN |
| Special/Order Compliance | 7/30/2025 | Approved | FARHAD DADBIN |