2329 N JUPITER DR 90046
Certificate Information: 2329 N JUPITER DR 90046
- Application / Permit
- 16014-10000-04591
- Plan Check / Job No.
- B16LA14889
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 1ST AND 2ND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/1/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2016 | HERNAN ARREOLA |
| Corrections Issued | 10/19/2016 | HERNAN ARREOLA |
| Quality Review Completed | 10/19/2016 | CHAD DOI |
| Building Plans Picked Up | 10/25/2016 | APPLICANT |
| Green Plans Picked Up | 7/14/2017 | APPLICANT |
| Plan Check Approved | 8/30/2017 | HERNAN ARREOLA |
| Issued | 9/1/2017 | LADBS |
| CofO in Progress | 1/9/2026 | BRIAN SULLIVAN |
| Permit Finaled | 1/10/2026 | DEROLD HAUFF |
| CofO Issued | 1/10/2026 | DEROLD HAUFF |
| Permit Finaled | 1/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/13/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 7/13/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 7/13/2017 | ROCHELLE DUNGCA |
| Distance to fire station | Cleared | 7/13/2017 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2017 | ROCHELLE DUNGCA |
| Hydrant and Access approval | Cleared | 7/13/2017 | ROBERT DUFF |
| Green Code | Cleared | 7/28/2017 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 8/22/2017 | IDA MEISAMI-FARD |
| Grading Pre-Inspection | Cleared | 8/30/2017 | HERNAN ARREOLA |
| Roof/Waste drainage to street | Cleared | 8/30/2017 | HISASHI KOBAYAKAWA |
Contact Information
| Engineer | Johnson, Charles Arthur Jr; Lic. No.: S2537 | 6212 SHAWNEE RD WESTMINSTER, CA 92683 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/30/2018 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 1/30/2018 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/6/2018 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/20/2018 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/6/2018 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/16/2018 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/23/2018 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/30/2018 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 7/24/2019 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/26/2019 | No Result Entered | BRAD BESCOS |
| Footing/Foundation/Slab | 12/2/2019 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/25/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 9/25/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 10/2/2020 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/8/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/8/2021 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/8/2021 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 1/11/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 1/19/2021 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/8/2021 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/8/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Approved | RAUL BARAJAS |
| HVAC-Rough | 3/8/2021 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 3/8/2021 | Conditional Approval | RAUL BARAJAS |
| Gas Test | 1/20/2023 | Corrections Issued | RAUL BARAJAS |
| Gas Test | 1/25/2023 | Corrections Issued | STUART CHAPMAN |
| Special/Order Compliance | 1/25/2023 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 12/5/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/11/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 4/11/2024 | Corrections Issued | RAUL BARAJAS |
| Final | 4/11/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 4/11/2024 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 4/11/2024 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 4/11/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 4/11/2024 | Approved | RAUL BARAJAS |
| Final | 7/17/2024 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 7/17/2024 | Approved | RAUL BARAJAS |
| Smoke Detectors | 7/18/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 2/21/2025 | Corrections Issued | ROY SPAULDING |
| Final | 10/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Final | 10/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 10/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Final | 10/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 10/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 10/23/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 11/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 12/9/2025 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 12/9/2025 | Approved | ROY SPAULDING |
| Final | 12/17/2025 | Conditional Approval | ROY SPAULDING |
| Final | 1/8/2026 | OK to Issue CofO | BRIAN SULLIVAN |