3201 N LACY ST 90031

Certificate Information: 3201 N LACY ST 90031

Application / Permit
16014-10000-04382
Plan Check / Job No.
B16LA14060
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(23) Animal Keeping - domestic
Work Description
ADDITION, RENOVATION & REMODEL OF (E) ANIMAL CARE FACILITY. NEW PARKING DESIGN.
Permit Issued
Issued on 9/7/2017
Issuing Office
Metro
Current Status
CofO Issued on 12/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2016 APPLICANT
Assigned to Plan Check Engineer 10/20/2016 EUGENE BARBEAU
Corrections Issued 10/26/2016 EUGENE BARBEAU
Disabled Access Plans Picked Up 10/28/2016 APPLICANT
Green Plans Picked Up 10/28/2016 APPLICANT
Quality Review Completed 11/9/2016 BILL STUTSMAN
Building Plans Picked Up 11/10/2016 APPLICANT
Applicant returned to address corrections 12/12/2016 EUGENE BARBEAU
Applicant returned to address corrections 12/21/2016 EUGENE BARBEAU
Applicant returned to address corrections 2/23/2017 EUGENE BARBEAU
Plan Check Approved 3/16/2017 EUGENE BARBEAU
Issued 9/7/2017 LADBS
CofO in Progress 12/1/2020 ERNESTO CORRAL
Permit Finaled 12/2/2020 ERNESTO CORRAL
CofO Issued 12/2/2020 ERNESTO CORRAL
Permit Finaled 12/2/2020 ERNESTO CORRAL

Permit Application Clearance Information

City owned building/parcel Cleared 2/13/2017 HAROOT AVANESIAN
Eng Process Fee Ord 176,300 Cleared 2/13/2017 CARLA VALLADARES
Fire Marshall Fire Life Safety Cleared 2/13/2017 PEJMAN NOORI
Highway dedication Cleared 2/13/2017 CARLA VALLADARES
Prkng lot landscape/Water mgmt Cleared 2/13/2017 FIPE LEILUA
Sewer availability Cleared 2/13/2017 CARLA VALLADARES
Miscellaneous Cleared 2/15/2017 MICHAEL SIN
Specific Plan Cleared 2/15/2017 MICHAEL SIN
DAS Clearance Cleared 2/28/2017 SHINE LIN
Green Code Cleared 3/2/2017 JOHN KLARIN
Low Impact Development Cleared 3/2/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/2/2017 LINDA MARGARET

Contact Information

Architect Cordova, Pedro; Lic. No.: C30384 4511 W 171ST STREET      LAWNDALE, CA 90260
Contractor Ford E C Inc; Lic. No.: 396212-B 10850 WILSHIRE BLVD #380      LOS ANGELES, CA 90024
Engineer Ashba, Barbara Jean; Lic. No.: C31417 PO BOX 90833      LONG BEACH, CA 90809
Engineer Tso, Leslie; Lic. No.: S3073 511 MISSION ST      SOUTH PASADENA, CA 910303035

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 1/9/2018 Not Ready for Inspection JAMES POWERS
Final 1/9/2018 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 1/9/2018 Not Ready for Inspection JAMES POWERS
Green Building Final 1/9/2018 Not Ready for Inspection JAMES POWERS
Green Building Rough 1/9/2018 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 1/9/2018 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 1/9/2018 SGSOV Not Ready JAMES POWERS
Smoke Detectors 1/9/2018 Not Ready for Inspection JAMES POWERS
Structural Steel Frame 1/9/2018 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/8/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/9/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/12/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/13/2018 Partial Approval FELIX CEBALLOS
Piling/Pier/Caisson 3/13/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/14/2018 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/16/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/19/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/20/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/21/2018 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 3/23/2018 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 5/16/2018 Partial Inspection ERNESTO CORRAL
Piling/Pier/Caisson 5/16/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/21/2018 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 5/31/2018 Partial Inspection ERNESTO CORRAL
Deputy Steel/Welding 6/19/2018 Partial Approval FELIX CEBALLOS
Footing/Foundation/Slab 6/20/2018 Partial Approval FELIX CEBALLOS
Piling/Pier/Caisson 6/20/2018 Partial Approval FELIX CEBALLOS
Deputy Methane Barrier 6/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/2/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/2/2018 Partial Inspection ERNESTO CORRAL
Green Building Rough 7/2/2018 Not Ready for Inspection ERNESTO CORRAL
Piling/Pier/Caisson 7/2/2018 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 7/2/2018 Not Ready for Inspection ERNESTO CORRAL
Structural Steel Frame 7/2/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/3/2018 Conditional Approval ERNESTO CORRAL
Wood Frame 7/26/2018 Partial Inspection ERNESTO CORRAL
Wood Frame 9/6/2018 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 9/11/2018 Conditional Approval JEFFREY FULTON
Wood Frame 9/18/2018 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 9/19/2018 Conditional Approval JEFFREY FULTON
Wood Frame 9/27/2018 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/12/2018 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 10/26/2018 Conditional Approval JEFFREY FULTON
Wood Frame 11/2/2018 Conditional Approval FRED WOHLFARTH
Light Gage Steel Frame 1/17/2019 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 1/30/2019 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 2/15/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 3/1/2019 Partial Inspection ERNESTO CORRAL
Green Building Rough 3/1/2019 Not Ready for Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/1/2019 Partial Inspection ERNESTO CORRAL
Insulation 3/28/2019 Partial Inspection JEFFREY FULTON
Wood Frame 3/28/2019 Partial Inspection JEFFREY FULTON
Wood Frame 4/4/2019 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 4/18/2019 Conditional Approval JEFFREY FULTON
Insulation 4/25/2019 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/2/2019 Approved FELIX CEBALLOS
Insulation 5/14/2019 Partial Inspection JEFFREY FULTON
Green Building Rough 5/20/2019 Approved JEFFREY FULTON
Light Gage Steel Frame 5/20/2019 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 5/20/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/28/2019 Partial Inspection JEFFREY FULTON
Insulation 5/28/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/5/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/20/2019 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 7/17/2019 Approved JEFFREY FULTON
Grading Pre-Inspection 8/9/2019 Partial Inspection JEFFREY FULTON
Grading Pre-Inspection 8/20/2019 Partial Inspection JEFFREY FULTON
Grading Pre-Inspection 9/19/2019 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 9/19/2019 Partial Inspection JEFFREY FULTON
Grading Pre-Inspection 10/22/2019 Partial Inspection JEFFREY FULTON
Grading Pre-Inspection 10/30/2019 Partial Approval RONALD PACHECO
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/8/2019 No Access for Inspection JEFFREY FULTON
Insulation 12/6/2019 Approved JEFFREY FULTON
Light Gage Steel Frame 12/6/2019 Approved JEFFREY FULTON
T-Bar Ceiling 12/6/2019 Approved JEFFREY FULTON
Pre-Inspection 12/16/2019 Partial Inspection JEFFREY FULTON
Pre-Inspection 3/6/2020 Approved RONALD PACHECO
Pre-Inspection 7/7/2020 Partial Inspection LANNY MERRICK
Green Building Final 8/17/2020 Conditional Approval LANNY MERRICK
Pre-Inspection 8/17/2020 Conditional Approval LANNY MERRICK
Drywall Nailing 8/27/2020 Not Ready for Inspection LANNY MERRICK
Final 8/27/2020 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 8/27/2020 Not Ready for Inspection LANNY MERRICK
Green Building Final 8/27/2020 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 8/27/2020 Approved LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 8/27/2020 SGSOV Approved LANNY MERRICK
Smoke Detectors 8/27/2020 Not Ready for Inspection LANNY MERRICK
Structural Steel Frame 8/27/2020 Not Ready for Inspection LANNY MERRICK
Green Building Final 8/31/2020 Conditional Approval RONALD PACHECO
Drywall Nailing 9/30/2020 Not Ready for Inspection RONALD PACHECO
Final 9/30/2020 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 9/30/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 9/30/2020 Conditional Approval RONALD PACHECO
Smoke Detectors 9/30/2020 Not Ready for Inspection RONALD PACHECO
Structural Steel Frame 9/30/2020 Not Ready for Inspection RONALD PACHECO
Pre-Inspection 10/17/2020 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 10/23/2020 Approved RUSSELL BONVOULOIR
Final 10/23/2020 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 10/23/2020 Approved RUSSELL BONVOULOIR
Green Building Final 10/23/2020 Conditional Approval RUSSELL BONVOULOIR
Smoke Detectors 10/23/2020 Approved RUSSELL BONVOULOIR
Structural Steel Frame 10/23/2020 Approved RUSSELL BONVOULOIR