Work Description
ADD STORY TO EXISTING 2-STORY DWELLING BY CONVERTING EXISTING CRAWL SPACE TO HABITABLE ROOMS. CONSTRUCT NEW FOUNDATION FOR BUILDING SUPPORT.
Permit Issued
Issued on 2/16/2018
Issuing Office
Metro
Current Status
Issued on 2/16/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/17/2016 APPLICANT
Green Plans Picked Up 9/26/2016 APPLICANT
Assigned to Plan Check Engineer 9/29/2016 EUGENE BARBEAU
Corrections Issued 10/5/2016 EUGENE BARBEAU
Quality Review Completed 10/19/2016 BILL STUTSMAN
Applicant returned to address corrections 1/30/2018 EUGENE BARBEAU
Applicant returned to address corrections 2/12/2018 EUGENE BARBEAU
Plan Check Approved 2/16/2018 EUGENE BARBEAU
Issued 2/16/2018 LADBS

Permit Application Clearance Information

ZA Case Cleared 1/26/2018 DAISY BENICIA
BHO/Hillside ordinance Cleared 1/30/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/30/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/30/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 1/30/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 1/30/2018 ADRIAN SANCHEZ
Sewer availability Cleared 1/30/2018 ADRIAN SANCHEZ
Green Code Cleared 2/2/2018 ROLLIN GETTLE III
Grading Pre-Inspection Cleared 2/12/2018 EUGENE BARBEAU
Excavation more than 5-ft deep Cleared 2/15/2018 CALOSHA APPROVED
Private sewage disp. approval Cleared 2/15/2018 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708
Geologist Schick, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/27/2018 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 1/28/2019 Corrections Issued DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 1/30/2019 Corrections Issued DANNY TOLENTINO
Deputy Drilled-In Anchors 1/31/2019 No Access for Inspection DANNY TOLENTINO
Deputy Drilled-In Anchors 2/6/2019 No Access for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 2/7/2019 Partial Approval DANNY TOLENTINO
Deputy Shotcrete 2/12/2019 No Access for Inspection DANNY TOLENTINO
Deputy Drilled-In Anchors 3/7/2019 No Access for Inspection DANNY TOLENTINO
Piling/Pier/Caisson 3/13/2019 Corrections Issued DANNY TOLENTINO
Deputy Drilled-In Anchors 3/14/2019 No Access for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 3/19/2019 Partial Approval DANNY TOLENTINO
Deputy Drilled-In Anchors 3/27/2019 Conditional Approval DANNY TOLENTINO
Deputy Reinf. Concrete 3/29/2019 Conditional Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 4/19/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/24/2019 Conditional Approval DANNY TOLENTINO
Deputy Reinf. Concrete 4/25/2019 Conditional Approval DANNY TOLENTINO
Deputy Drilled-In Anchors 5/8/2019 Conditional Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/24/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 4/19/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 4/19/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/17/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 5/19/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/1/2021 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/1/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval RAUL BARAJAS
Green Building Rough 10/13/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/4/2021 Partial Approval RAUL BARAJAS
Green Building Rough 11/4/2021 Approved RAUL BARAJAS
HVAC-Rough 11/4/2021 Partial Inspection RAUL BARAJAS
Drywall Nailing 3/15/2022 Approved RAUL BARAJAS
Shower Pan 4/11/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 8/1/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 7/13/2023 Approved RAUL BARAJAS
Final 7/13/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 7/13/2023 Approved RAUL BARAJAS
Green Building Final 7/13/2023 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 7/13/2023 Approved RAUL BARAJAS