- 1. ADD 1800 SF 1-STORY EXTENSION + SECOND FLOOR ADDITION TO EXISTING 1-STORY SFD. 2. INTERIOR REMODEL
- Permit Issued
- Issued on 8/11/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/16/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/1/2016 | APPLICANT |
Assigned to Plan Check Engineer | 4/21/2016 | CHRISTOPHER KOMANCHECK |
Corrections Issued | 4/23/2016 | CHRISTOPHER KOMANCHECK |
Quality Review Completed | 5/10/2016 | BILL STUTSMAN |
Building Plans Picked Up | 5/12/2016 | APPLICANT |
Green Plans Picked Up | 5/12/2016 | APPLICANT |
Applicant returned to address corrections | 7/28/2016 | CHRISTOPHER KOMANCHECK |
Plan Check Approved | 8/11/2016 | CHRISTOPHER KOMANCHECK |
Issued | 8/11/2016 | LADBS |
CofO in Progress | 6/9/2018 | RICHARD STEINBACH |
Permit Finaled | 6/16/2018 | DANIEL ORRANTE |
CofO Issued | 6/16/2018 | DANIEL ORRANTE |
Permit Finaled | 6/16/2018 | DANIEL ORRANTE |
Permit Application Clearance Information
BHO/Hillside ordinance | Cleared | 5/18/2016 | AVALYN KAMACHI |
BHO/Hillside ordinance | Cleared | 5/18/2016 | AVALYN KAMACHI |
BHO/Hillside ordinance | Cleared | 5/18/2016 | AVALYN KAMACHI |
BHO/Hillside ordinance | Cleared | 5/18/2016 | AVALYN KAMACHI |
BHO/Hillside ordinance | Cleared | 5/18/2016 | AVALYN KAMACHI |
Eng Process Fee Ord 176,300 | Cleared | 5/18/2016 | AVALYN KAMACHI |
Grading Pre-Inspection | Cleared | 5/18/2016 | PATRICK MISCHLICH |
Sewer availability | Cleared | 5/18/2016 | AVALYN KAMACHI |
Green Code | Cleared | 8/8/2016 | MICKEY YAMASHITA |
Low Impact Development | Cleared | 8/11/2016 | RYAN HUDSON |
Roof/Waste drainage to street | Cleared | 8/11/2016 | RAVIL MANAPOV |
Contact Information
Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 19625 VENTURA BLVD STE 200 TARZANA, CA 91356 |
Engineer | Carrizosa, Richard Garcia; Lic. No.: C25828 | 1505 LYNDHURST AVE HACIENDA HEIGHTS, CA 917452932 |
Inspector Information
STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 9/12/2016 | Partial Approval | KENNETH NAGLE |
Footing/Foundation/Slab | 10/18/2016 | Partial Approval | KENNETH NAGLE |
BUILDING-Rough-Frame | 10/27/2016 | Partial Approval | KENNETH NAGLE |
Green Building Rough | 10/27/2016 | Not Ready for Inspection | KENNETH NAGLE |
PLUMBING-Rough | 10/27/2016 | Not Ready for Inspection | KENNETH NAGLE |
Verify Sprinkler Sign Off | 10/27/2016 | Not Ready for Inspection | KENNETH NAGLE |
ELECTRICAL-Rough | 11/1/2016 | Not Ready for Inspection | KENNETH NAGLE |
PLUMBING-Rough | 11/1/2016 | Not Ready for Inspection | KENNETH NAGLE |
PLUMBING-Rough | 11/2/2016 | Corrections Issued | DAVID KOSKI |
BUILDING-Rough-Frame | 11/3/2016 | Partial Approval | KENNETH NAGLE |
Green Building Rough | 11/3/2016 | Not Ready for Inspection | KENNETH NAGLE |
PLUMBING-Rough | 11/3/2016 | Partial Approval | KENNETH NAGLE |
Verify Sprinkler Sign Off | 11/3/2016 | Not Ready for Inspection | KENNETH NAGLE |
Floor/Roof Diaphrgm/Shear Wall | 11/9/2016 | Partial Approval | KENNETH NAGLE |
Floor/Roof Diaphrgm/Shear Wall | 11/17/2016 | Partial Approval | KENNETH NAGLE |
Floor/Roof Diaphrgm/Shear Wall | 12/8/2016 | Partial Approval | KENNETH NAGLE |
Floor/Roof Diaphrgm/Shear Wall | 2/13/2017 | Partial Approval | JOHN LUMB |
BUILDING-Rough-Frame | 2/22/2017 | Not Ready for Inspection | KENNETH NAGLE |
Green Building Rough | 2/22/2017 | Not Ready for Inspection | KENNETH NAGLE |
Interior/Exterior Lathing | 2/22/2017 | Not Ready for Inspection | KENNETH NAGLE |
Rough-Elec/Plmb/HVAC | 2/22/2017 | Corrections Issued | KENNETH NAGLE |
Verify Sprinkler Sign Off | 2/22/2017 | Not Ready for Inspection | KENNETH NAGLE |
ELECTRICAL-Rough | 3/2/2017 | Corrections Issued | KENNETH NAGLE |
Interior/Exterior Lathing | 3/2/2017 | Partial Approval | KENNETH NAGLE |
ELECTRICAL-Rough | 3/10/2017 | Approved | KENNETH NAGLE |
HVAC-Rough | 3/10/2017 | Not Ready for Inspection | KENNETH NAGLE |
BUILDING-Rough-Frame | 4/20/2017 | Corrections Issued | KENNETH NAGLE |
Green Building Rough | 4/20/2017 | Approved | KENNETH NAGLE |
HVAC-Rough | 4/20/2017 | Approved | KENNETH NAGLE |
Verify Sprinkler Sign Off | 4/20/2017 | Not Ready for Inspection | KENNETH NAGLE |
BUILDING-Rough-Frame | 4/27/2017 | Approved | KENNETH NAGLE |
Verify Sprinkler Sign Off | 4/27/2017 | Approved | KENNETH NAGLE |
Insulation | 5/5/2017 | Approved | KENNETH NAGLE |
Interior/Exterior Lathing | 5/5/2017 | Approved | KENNETH NAGLE |
Drywall Nailing | 5/10/2017 | Approved | KENNETH NAGLE |
Insulation | 5/10/2017 | Approved | KENNETH NAGLE |
Gas Test | 6/29/2017 | Approved | KENNETH NAGLE |
PLUMBING-Rough | 6/29/2017 | Partial Approval | KENNETH NAGLE |
Service/Power Release | 8/23/2017 | Approved | KENNETH NAGLE |
Final | 11/13/2017 | Not Ready for Inspection | KENNETH NAGLE |
Footing/Foundation/Slab | 11/13/2017 | Approved | KENNETH NAGLE |
Green Building Final | 11/13/2017 | Not Ready for Inspection | KENNETH NAGLE |
SGSOV-Seismic Gas S/O Valve | 11/13/2017 | SGSOV Not Ready | KENNETH NAGLE |
Smoke Detectors | 11/13/2017 | Approved | KENNETH NAGLE |
Final | 11/29/2017 | Not Ready for Inspection | KENNETH NAGLE |
Green Building Final | 11/29/2017 | Not Ready for Inspection | KENNETH NAGLE |
SGSOV-Seismic Gas S/O Valve | 11/29/2017 | SGSOV Not Ready | KENNETH NAGLE |
Final | 2/9/2018 | Corrections Issued | KENNETH NAGLE |
Green Building Final | 2/9/2018 | Approved | KENNETH NAGLE |
SGSOV-Seismic Gas S/O Valve | 2/9/2018 | SGSOV Approved | KENNETH NAGLE |
ELECTRICAL-Final | 5/2/2018 | Approved | RICHARD STEINBACH |
Final | 5/2/2018 | Not Ready for Inspection | RICHARD STEINBACH |
HVAC-Final | 5/2/2018 | Corrections Issued | RICHARD STEINBACH |
PLUMBING-Final | 5/2/2018 | Approved | RICHARD STEINBACH |
Final | 6/8/2018 | OK to Issue CofO | RICHARD STEINBACH |
HVAC-Final | 6/8/2018 | Approved | RICHARD STEINBACH |