15210 W ANTELO PL 90077

Certificate Information: 15210 W ANTELO PL 90077

Application / Permit
16014-10000-01431
Plan Check / Job No.
B16LA04587
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL OF (E) 3-STORY SINGLE FAMILY DWELLING WITH 1 LEVEL BASEMENT PER DIR-2015-4662-DRB-SPP-MSP
Permit Issued
Issued on 7/21/2017
Issuing Office
Metro
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2016 APPLICANT
Assigned to Plan Check Engineer 4/21/2016 RICARDO SUPAN
Corrections Issued 4/26/2016 RICARDO SUPAN
Quality Review Completed 5/2/2016 HOK CHI CHIU
Building Plans Picked Up 5/3/2016 APPLICANT
Green Plans Picked Up 5/10/2016 APPLICANT
Applicant returned to address corrections 8/22/2016 RICARDO SUPAN
Applicant returned to address corrections 9/9/2016 RICARDO SUPAN
Plan Check Approved 7/12/2017 RICARDO SUPAN
Issued 7/21/2017 LADBS
CofO in Progress 10/21/2020 CHRISTOPHER WILSON
Permit Finaled 11/24/2021 DANIEL ORRANTE
CofO Issued 11/24/2021 DANIEL ORRANTE
Permit Finaled 11/24/2021 DANIEL ORRANTE

Permit Application Clearance Information

Private street Cleared 5/31/2016 CASSANDRA ZWEEP
Prkng lot landscape/Water mgmt Cleared 5/31/2016 CASSANDRA ZWEEP
ZA Case Cleared 5/31/2016 CASSANDRA ZWEEP
Eng Process Fee Ord 176,300 Cleared 6/8/2016 SHANNON CAMPBELL
Landscape for retaining wall Cleared 7/29/2016 VINCENT QUITORIANO
Miscellaneous Cleared 7/29/2016 VINCENT QUITORIANO
Specific Plan Cleared 7/29/2016 VINCENT QUITORIANO
Specific Plan Cleared 7/29/2016 VINCENT QUITORIANO
Hydrant and Access approval Cleared 6/6/2017 ROBERT DUFF
Low Impact Development Cleared 6/6/2017 RYAN HUDSON
Green Code Cleared 6/26/2017 KATHRYN BUTTERWORTH
BHO/Hillside ordinance Cleared 6/29/2017 LUZ RABELO
Roof/Waste drainage to street Cleared 6/29/2017 CHEN ZHANG
Excavation more than 5-ft deep Cleared 7/12/2017 CALOSHA APPROVED
GPI Written Notices Cleared 7/12/2017 RICARDO SUPAN
Grading Pre-Inspection Cleared 7/12/2017 RICARDO SUPAN
Hold Cleared 8/15/2017 TERESA MUI

Contact Information

Architect Whitby, Michael B; Lic. No.: C26182 12114 N. BRIGHTON CT.      HAYDEN, ID 83835
Contractor Rjc Builders Inc; Lic. No.: 740011-B 3509 W 6TH STREET      LOS ANGELES, CA 90020
Engineer Peck, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023
Engineer Perlof, Stephen Lee; Lic. No.: S1641 3207 VIOLA PL      MARINA DEL REY, CA 90292
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Gladson, Richard; Lic. No.: EG1758 1545 VICTORY BL      GLENDALE, CA 91201

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/18/2017 Partial Approval ANTHONY ANDERSON
Gas Test 10/10/2017 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/10/2017 Approved CHRISTOPHER WILSON
PLUMBING-Rough 3/21/2018 Partial Approval MATT KELLERMAN
Special/Order Compliance 6/23/2018 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/13/2018 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/13/2018 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 8/13/2018 Partial Inspection CHRISTOPHER WILSON
Insulation 8/13/2018 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/20/2018 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/27/2018 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/27/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 8/27/2018 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/28/2018 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 8/28/2018 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/5/2018 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 9/5/2018 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/5/2018 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 9/5/2018 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/5/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 9/7/2018 Partial Approval MATT KELLERMAN
Shower Pan 9/12/2018 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 9/19/2018 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/21/2018 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/21/2018 Approved CHRISTOPHER WILSON
Green Building Rough 9/21/2018 Approved CHRISTOPHER WILSON
HVAC-Rough 9/21/2018 Approved CHRISTOPHER WILSON
PLUMBING-Rough 9/21/2018 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/21/2018 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 9/26/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/28/2018 Corrections Issued CHRISTOPHER WILSON
Insulation 9/28/2018 Approved CHRISTOPHER WILSON
Drywall Nailing 10/4/2018 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2018 Not Ready for Inspection MATT KELLERMAN
Insulation 10/4/2018 Not Ready for Inspection MATT KELLERMAN
Drywall Nailing 10/9/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2018 Approved CHRISTOPHER WILSON
Drywall Nailing 10/17/2018 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 12/27/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 12/27/2018 Approved CHRISTOPHER WILSON
Special/Order Compliance 1/12/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 3/30/2019 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 4/4/2019 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 8/16/2019 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 9/30/2019 Partial Approval MATT KELLERMAN
PLUMBING-Rough 10/17/2019 No Access for Inspection MATT KELLERMAN
Gas Test 10/22/2019 Approved MATT KELLERMAN
Light Gage Steel Frame 11/1/2019 Partial Approval MATT KELLERMAN
Special/Order Compliance 11/1/2019 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/4/2020 Approved CHRISTOPHER WILSON
Drywall Nailing 5/4/2020 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 5/4/2020 Corrections Issued CHRISTOPHER WILSON
Final 5/4/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/4/2020 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/4/2020 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 5/4/2020 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 5/8/2020 Corrections Issued CHRISTOPHER WILSON
Green Building Final 5/8/2020 Partial Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 5/8/2020 Approved CHRISTOPHER WILSON
Final 5/13/2020 Not Ready for Inspection MATT KELLERMAN
Green Building Final 5/13/2020 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 5/13/2020 SGSOV Approved MATT KELLERMAN
Final 5/20/2020 Partial Inspection CHRISTOPHER WILSON
Green Building Final 5/20/2020 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 5/29/2020 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Final 5/29/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 6/2/2020 Approved CHRISTOPHER WILSON
HVAC-Final 6/3/2020 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Final 6/4/2020 Approved CHRISTOPHER WILSON
HVAC-Final 6/26/2020 Approved CHRISTOPHER WILSON
Final 9/10/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 9/10/2020 Not Ready for Inspection CHRISTOPHER WILSON
Final 9/21/2020 Corrections Issued CHRISTOPHER WILSON
Green Building Final 9/21/2020 Approved CHRISTOPHER WILSON
Final 9/28/2020 Corrections Issued CHRISTOPHER WILSON
Final 10/5/2020 Corrections Issued CHRISTOPHER WILSON
Final 10/13/2020 Conditional Approval CHRISTOPHER WILSON