7759 W SKYHILL DR 90068
Certificate Information: 7759 W SKYHILL DR 90068
- Application / Permit
- 16014-10000-00908
- Plan Check / Job No.
- B16LA02840
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Enclose 9'0" x 41'0" patio cover on 1st floor (below 2nd floor deck/balcony); Remove portion of (e) raised floor and replace with slab on grade; Remodel (e) kitchen and living room.
- Permit Issued
- Issued on 3/15/2016
- Issuing Office
- Valley
- Current Status
- Issued on 3/15/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/2/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2016 | KRIKOR MANOUKIAN |
| Corrections Issued | 3/2/2016 | KRIKOR MANOUKIAN |
| Plan Check Approved | 3/8/2016 | CATHERINE CHEN |
| Issued | 3/15/2016 | LADBS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/3/2016 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 3/3/2016 | HERMINIGILDO AGUSTIN |
| Metro Rail approval | Cleared | 3/7/2016 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/17/2016 | Order to Comply Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 3/17/2016 | Order to Comply Issued | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 3/17/2016 | Order to Comply Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 4/13/2016 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 5/2/2016 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 5/11/2016 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 5/11/2016 | Not Ready for Inspection | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 5/11/2016 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 5/11/2016 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 6/15/2016 | No Access for Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2016 | No Access for Inspection | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 6/15/2016 | No Access for Inspection | RUBEN SALAS |
| Wood Frame | 6/15/2016 | No Access for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/20/2016 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 6/20/2016 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 6/20/2016 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 6/20/2016 | Not Ready for Inspection | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 6/20/2016 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 7/5/2016 | No Access for Inspection | MICHAEL TUCK |
| Reinforced Concrete Frame | 7/5/2016 | No Access for Inspection | MICHAEL TUCK |
| Wood Frame | 7/5/2016 | No Access for Inspection | MICHAEL TUCK |
| Rough-Elec/Plmb/HVAC | 7/11/2016 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 7/11/2016 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 8/16/2016 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 8/16/2016 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 8/16/2016 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 8/16/2016 | Partial Approval | RUBEN SALAS |
| Interior/Exterior Lathing | 8/22/2016 | Not Ready for Inspection | JOEL WILLIAMS |
| PLUMBING-Rough | 8/22/2016 | Not Ready for Inspection | JOEL WILLIAMS |
| Insulation | 8/26/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/26/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/26/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/2/2016 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 9/2/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/2/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/12/2016 | No Access for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 10/12/2016 | No Access for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/12/2016 | No Access for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/13/2016 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/13/2016 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 10/24/2016 | No Access for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 10/24/2016 | No Access for Inspection | BRIAN SULLIVAN |
| Final | 11/21/2018 | Corrections Issued | ELMER BLAND |
| Pre-Inspection | 6/25/2025 | Corrections Issued | BRIAN SULLIVAN |