616 E 77TH ST 90001
Certificate Information: 616 E 77TH ST 90001
- Application / Permit
- 16014-10000-00215
- Plan Check / Job No.
- B16LA00722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONSTRUCT NEW ADDITION TO (E) 1-STORY SFD (13' x 32.33'). ALL WORK PER WFPP
- Permit Issued
- Issued on 3/4/2016
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 3/4/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/20/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2016 | RICARDO SUPAN |
| Corrections Issued | 1/20/2016 | RICARDO SUPAN |
| Plan Check Approved | 3/1/2016 | ERIC CABRERA |
| Issued | 3/4/2016 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2016 | ARNULFO NUNO |
| Roof/Waste drainage to street | Cleared | 2/12/2016 | ARNULFO NUNO |
| Sewer availability | Cleared | 2/12/2016 | ARNULFO NUNO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2016 | Corrections Issued | RICHARD VENTURA |
| Excavation/Setback/Form/Re-Bar | 4/12/2016 | Approved | RICHARD VENTURA |
| BUILDING-Rough-Frame | 4/20/2016 | Partial Approval | JAVIER ALIPIO |
| Green Building Rough | 4/20/2016 | Not Ready for Inspection | JAVIER ALIPIO |
| Underground Mechanical | 4/20/2016 | Approved | JAVIER ALIPIO |
| BUILDING-Rough-Frame | 5/3/2016 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/3/2016 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 5/3/2016 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/5/2016 | Approved | ENRIQUE MIRELES |
| Insulation | 5/5/2016 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/5/2016 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 5/10/2016 | Approved | JAVIER ALIPIO |
| Interior/Exterior Lathing | 5/10/2016 | Approved | JAVIER ALIPIO |
| Final | 6/6/2016 | Conditional Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/6/2016 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/6/2016 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2016 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/6/2016 | Approved | ENRIQUE MIRELES |
| Final | 7/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 8/22/2025 | Corrections Issued | JOSH MEISTER |
| Final | 9/22/2025 | Corrections Issued | SALVADOR MARTINEZ |