948 N ORLANDO AVE 90069

Certificate Information: 948 N ORLANDO AVE 90069

Application / Permit
16010-70000-02801
Plan Check / Job No.
B16SL00830
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
New recreation room at rear of the lot per wood frame prescriptive provisions. Voluntary Fire Sprinkler NFPA 13D
Permit Issued
Issued on 8/19/2016
Issuing Office
Valley
Current Status
CofO Issued on 7/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2016 APPLICANT
Assigned to Plan Check Engineer 6/28/2016 ALBERT SERVIN
Corrections Issued 6/28/2016 ALBERT SERVIN
Plan Check Approved 8/16/2016 JOSHUA DIAZ
Issued 8/19/2016 LADBS
CofO in Progress 10/15/2021 ROBERT MINASSIANS
Permit Finaled 7/25/2022 DANIEL SANCHEZ
CofO Issued 7/25/2022 DANIEL SANCHEZ
Permit Finaled 7/25/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/18/2016 RAVIL MANAPOV
Sewer availability Cleared 7/18/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 7/19/2016 ROBERT DUFF
Construction near power lines Cleared 8/5/2016 LUCIO FERRER
Low Impact Development Cleared 8/11/2016 SAM NAVID
Roof/Waste drainage to street Cleared 8/12/2016 RAVIL MANAPOV

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/6/2016 Approved JOHN MATTILLO
Footing/Foundation/Slab 9/6/2016 Corrections Issued JOHN MATTILLO
Footing/Foundation/Slab 9/20/2016 Approved JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 10/11/2016 Partial Approval JOHN MATTILLO
Green Building Rough 10/11/2016 Partial Inspection JOHN MATTILLO
Verify Sprinkler Sign Off 10/11/2016 Not Ready for Inspection JOHN MATTILLO
BUILDING-Rough-Frame 12/14/2016 Approved JOHN MATTILLO
ELECTRICAL-Rough 12/14/2016 Approved JOHN MATTILLO
Green Building Rough 12/14/2016 Approved JOHN MATTILLO
HVAC-Rough 12/14/2016 Approved JOHN MATTILLO
PLUMBING-Rough 12/14/2016 Approved JOHN MATTILLO
Rough-Elec/Plmb/HVAC 12/14/2016 Approved JOHN MATTILLO
Verify Sprinkler Sign Off 12/14/2016 Approved JOHN MATTILLO
Drywall Nailing 3/1/2017 Approved JOHN MATTILLO
Interior/Exterior Lathing 3/1/2017 Approved JOHN MATTILLO
Gas Test 9/7/2017 Approved JOHN MATTILLO
Final 12/6/2017 Not Ready for Inspection JOHN MATTILLO
Green Building Final 12/6/2017 Not Ready for Inspection JOHN MATTILLO
SGSOV-Seismic Gas S/O Valve 12/6/2017 SGSOV Not Ready JOHN MATTILLO
Service/Power Release 12/6/2017 Not Ready for Inspection JOHN MATTILLO
Smoke Detectors 12/6/2017 Not Ready for Inspection JOHN MATTILLO
Gas Test 12/7/2017 Approved JOHN MATTILLO
Final 3/19/2021 Corrections Issued PATRICK QUALEY
Green Building Final 3/19/2021 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved PATRICK QUALEY
Smoke Detectors 3/19/2021 Corrections Issued PATRICK QUALEY
Final 7/29/2021 OK to Issue CofO PATRICK QUALEY
Green Building Final 7/29/2021 Approved PATRICK QUALEY
Smoke Detectors 7/29/2021 Approved PATRICK QUALEY