115-117 W 74TH ST 90003

Certificate Information: 115-117 W 74TH ST 90003

Application / Permit
16010-70000-00319
Plan Check / Job No.
B16SL00113
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT THE FRONT DUPLEX TO SFD AND ADD A NEW SFD WITH AN ATTACHED CARPORT AT THE REAR.
Permit Issued
Issued on 9/21/2016
Issuing Office
Valley
Current Status
Issued on 9/21/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/1/2016 APPLICANT
Assigned to Plan Check Engineer 2/11/2016 QUAN NGHIEM
Corrections Issued 2/18/2016 QUAN NGHIEM
Plans on Hold 2/23/2016 BILL STUTSMAN
Hold Released 4/12/2016 QUAN NGHIEM
Quality Review Completed 4/26/2016 BILL STUTSMAN
Building Plans Picked Up 4/29/2016 APPLICANT
Plan Check Approved 9/20/2016 QUAN NGHIEM
Issued 9/21/2016 LADBS

Permit Application Clearance Information

Hold Cleared 4/7/2016 CANDICE JUSAY
Eng Process Fee Ord 176,300 Cleared 5/24/2016 JOHN LIN
Sewer availability Cleared 5/24/2016 JOHN LIN
Address approval Cleared 7/1/2016 ROBERT SAMONTE
Project located in CRA area Cleared 8/10/2016 JIM URQUHART
Low Impact Development Cleared 8/23/2016 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/23/2016 IRENE CHIA
Green Code Cleared 9/15/2016 JOHN KLARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2017 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 4/11/2017 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 4/13/2017 Approved JAVIER ALIPIO
Floor/Roof Diaphrgm/Shear Wall 6/19/2017 Partial Approval ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 9/8/2017 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 12/19/2017 No Access for Inspection FRANCISCO MORADO
Interior/Exterior Lathing 12/26/2017 No Access for Inspection ANDEY CHAPARRO
Interior/Exterior Lathing 1/2/2018 Corrections Issued ANDEY CHAPARRO
Interior/Exterior Lathing 2/5/2018 Approved ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 2/5/2018 Not Ready for Inspection ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 3/6/2018 Approved ANDEY CHAPARRO
PLUMBING-Final 3/6/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 3/6/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 3/16/2018 No Access for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 3/22/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 3/27/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 4/3/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 4/10/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 4/16/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 4/20/2018 Not Ready for Inspection ANDEY CHAPARRO
Green Building Final 4/25/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 4/25/2018 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 5/2/2018 Approved ANDEY CHAPARRO
Green Building Rough 5/2/2018 Approved ANDEY CHAPARRO
HVAC-Rough 5/2/2018 Approved ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 5/2/2018 Not Ready for Inspection ANDEY CHAPARRO
Insulation 5/4/2018 Approved ANDEY CHAPARRO
Drywall Nailing 6/5/2018 Conditional Approval ANDEY CHAPARRO
BUILDING-Rough-Frame 6/7/2018 Approved ANDEY CHAPARRO
Green Building Final 6/7/2018 Not Ready for Inspection ANDEY CHAPARRO
Interior/Exterior Lathing 6/7/2018 Approved ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 6/7/2018 SGSOV Not Ready ANDEY CHAPARRO
Smoke Detectors 6/7/2018 Not Ready for Inspection ANDEY CHAPARRO
Special/Order Compliance 6/7/2018 Not Ready for Inspection ANDEY CHAPARRO
Special/Order Compliance 7/3/2018 Not Ready for Inspection WILLIAM ROSE
Pre-Inspection 9/25/2020 Corrections Issued DAVID FEILER
Drywall Nailing 11/17/2020 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/17/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/17/2020 Approved ALEJANDRO DE ARTOLA
Final 11/22/2021 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 11/22/2021 Approved HORACE FULTZ
Green Building Final 11/22/2021 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Not Ready HORACE FULTZ
Smoke Detectors 11/22/2021 Approved HORACE FULTZ
Final 12/7/2021 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Not Ready SABAS ALONSO
Final 12/14/2021 Not Ready for Inspection ADAM ESCOTO
Pre-Inspection 12/14/2021 Approved ADAM ESCOTO
Final 12/21/2021 Partial Inspection HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved HORACE FULTZ
Final 1/27/2022 No Access for Inspection LILIANA PORTILLO
Final 2/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 8/23/2022 Corrections Issued LILIANA PORTILLO
Service/Power Release 8/23/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 12/9/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 4/29/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 4/29/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Final 4/29/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 4/29/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 6/2/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 6/2/2025 Corrections Issued JOHN QUINTANILLA
Gas Test 6/2/2025 Not Ready for Inspection JOHN QUINTANILLA
Service/Power Release 6/2/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 6/12/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 6/13/2025 Approved JOHN QUINTANILLA
Gas Test 6/13/2025 Approved JOHN QUINTANILLA
Service/Power Release 6/13/2025 Approved JOHN QUINTANILLA