Pre-Inspection
|
5/22/2020
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Shotcrete
|
10/18/2023
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
10/18/2023
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
10/24/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Shotcrete
|
11/2/2023
|
Conditional Approval
|
AMANUEL BERHE
|
|
Deputy Shotcrete
|
11/13/2023
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
11/14/2023
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
11/15/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
11/15/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
11/16/2023
|
Approved
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
11/29/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Masonry
|
11/30/2023
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Shotcrete
|
12/5/2023
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
12/5/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Shotcrete
|
12/7/2023
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
1/9/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Steel/Welding
|
1/10/2024
|
Approved
|
JOEY BUCHANAN
|
|
Green Building Rough
|
1/17/2024
|
Approved
|
JOEY BUCHANAN
|
|
Masonry Wall/Backfill
|
1/17/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Structural Steel Frame
|
1/17/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Verify Sprinkler Sign Off
|
1/17/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Masonry
|
1/19/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
2/12/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
2/16/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
3/5/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
3/5/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Reinforced Masonry Frame
|
3/5/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
3/7/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
3/13/2024
|
Approved
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
3/14/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
3/15/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Masonry
|
3/22/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
4/17/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
4/19/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
5/6/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
5/7/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
5/7/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
5/8/2024
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Reinf. Masonry
|
5/20/2024
|
Approved
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
5/20/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
5/23/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
5/31/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
6/26/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
7/1/2024
|
Partial Approval
|
DAVID TSAU
|
|
Deputy Reinf. Concrete
|
7/10/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
7/29/2024
|
Partial Inspection
|
AMANUEL BERHE
|
|
Deputy Reinf. Concrete
|
7/31/2024
|
Conditional Approval
|
AMANUEL BERHE
|
|
Reinforced Concrete Frame
|
9/12/2024
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Wall Anchors
|
9/12/2024
|
Approved
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
9/16/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
9/20/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
10/22/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
10/23/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
11/8/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
1/29/2025
|
Approved
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
2/4/2025
|
Approved
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/19/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Reinforced Concrete Frame
|
2/19/2025
|
Approved
|
JOEY BUCHANAN
|
|
Wood Frame
|
2/19/2025
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/14/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/16/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Deputy Wood Construction
|
9/3/2025
|
Approved
|
NICK LAROCCA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2026
|
Partial Approval
|
DAVID TSAU
|