13755 W ROSCOE BLVD 91402

Certificate Information: 13755 W ROSCOE BLVD 91402

Application / Permit
16010-30005-03198
Plan Check / Job No.
B20WL00503
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Supplememtal ref to pcis # 16010-30000-03198, for structural revisions
Permit Issued
Issued on 4/8/2020
Issuing Office
Current Status
Permit Finaled on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 2/26/2020 SERGIO SILVA
Corrections Issued 3/3/2020 MARJAN SHENASI
Quality Review Completed 3/12/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/2/2020 SERGIO SILVA
Building Plans Picked Up 4/3/2020 APPLICANT
Issued 4/8/2020 APPLICANT
Permit Finaled 8/14/2024 DANNY RODRIGUEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Khorramian, Abdy; Lic. No.: C13138 4741 LAUREL CANYON BLVD      VALLEY VILLAGE, CA 91607
Contractor Owner-Builder       ,
Engineer Almalla, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Smith, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 4/13/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/24/2020 Partial Approval JONATHAN QUACH
Reinforced Masonry Frame 5/21/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 5/22/2020 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 5/22/2020 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 6/19/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 7/1/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 7/1/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 7/6/2020 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 7/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/13/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 7/22/2020 Partial Approval DANNY RODRIGUEZ