10649 W CAPELLO WAY 90077
Certificate Information: 10649 W CAPELLO WAY 90077
- Application / Permit
- 16010-30004-00034
- Plan Check / Job No.
- B21WL05024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- supplemental ref to pcis # 16010-30003-00034, for structural change & interior, EXTERIOR AND ROOF layout changes
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | TARIK SAOUD |
| Corrections Issued | 11/30/2021 | TARIK SAOUD |
| Quality Review Completed | 12/6/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 3/24/2022 | TARIK SAOUD |
| Issued | 4/25/2022 | APPLICANT |
| Permit Finaled | 6/4/2025 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2021 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 3/24/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | JENSON LEE |
Contact Information
| Architect | Maly, Farzin; Lic. No.: C33731 | PO BOX 57002 SHERMAN OAKS, CA 91413 |
| Contractor | Owner-Builder | , |
| Engineer | Melkonians, Armen; Lic. No.: C55884 | 435 N BEVERLY DR #208 BEVERLY HILLS, CA 90210 |
| Engineer | Minas, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Pirbadian, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 212 ENCINO, CA 91436 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/27/2022 | Partial Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 9/27/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 10/3/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 11/16/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | CARLOS MATAMOROS |
| Wood Frame | 11/21/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 12/6/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/3/2024 | Partial Approval | CARLOS MATAMOROS |