13755 W ROSCOE BLVD 91402
Certificate Information: 13755 W ROSCOE BLVD 91402
- Application / Permit
- 16010-30002-03198
- Plan Check / Job No.
- B19WL03292
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Supplemental to permit # 16010-30000-03198, for revisions at both 1st and 2nd level to remove interior walls and replace with moment frame, remove ground floor access driveway and convert the covered area to retail, remove driveway on Woodman Ave and parking lot revisions, update structural inventory.
- Permit Issued
- Issued on 11/19/2019
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2019 | APPLICANT |
| Building Plans Picked Up | 6/25/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 6/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | MARJAN SHENASI |
| Green Plans Picked Up | 7/3/2019 | APPLICANT |
| Corrections Issued | 7/8/2019 | MARJAN SHENASI |
| Quality Review Completed | 7/19/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/30/2019 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/6/2019 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/14/2019 | MARJAN SHENASI |
| Plan Check Approved | 11/19/2019 | MARJAN SHENASI |
| Issued | 11/19/2019 | LADBS |
| Permit Finaled | 8/14/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/27/2019 | WAI LAU |
| "Q" conditions | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Drive-through fast food | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Frnt yard landscape/Water mgmt | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Prkng lot landscape/Water mgmt | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/18/2019 | STEVEN WECHSLER |
| Green Code | Cleared | 10/24/2019 | RICHARD GARCIA |
| Fire Marshall Fire Life Safety | Cleared | 11/12/2019 | DOMINIQUE MEDINA |
| Low Impact Development | Cleared | 11/14/2019 | MARTIN FRAGOSO |
Contact Information
| Architect | Khorramian, Abdy; Lic. No.: C13138 | 4741 LAUREL CANYON BLVD VALLEY VILLAGE, CA 91607 |
| Contractor | Owner-Builder | , |
| Engineer | Almalla, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2019 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 12/2/2019 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 12/11/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 12/12/2019 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/12/2019 | Partial Approval | DANNY RODRIGUEZ |
| Pre-Inspection | 8/26/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 4/25/2023 | Approved | DANNY RODRIGUEZ |
| Final | 4/25/2023 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Final | 4/25/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 4/25/2023 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 4/25/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/25/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Smoke Detectors | 4/25/2023 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 4/25/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 6/9/2023 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Final | 6/9/2023 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 6/9/2023 | Approved | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/9/2023 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 6/9/2023 | Approved | DANNY RODRIGUEZ |