9390 W READCREST DR 90210
Certificate Information: 9390 W READCREST DR 90210
- Application / Permit
- 16010-30001-03854
- Plan Check / Job No.
- B21WL02346
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 16010-30000-03854, for zoning code re-check for 2017 BHO codes (1 of 4)
- Permit Issued
- Issued on 6/28/2022
- Issuing Office
- Current Status
- Issued on 6/28/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/14/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 6/25/2021 | TARIK SAOUD |
| Plan Check Approved | 8/14/2021 | REZA HAGHIGHAT |
| Issued | 6/28/2022 | APPLICANT |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | B D R Inc; Lic. No.: 735996-B | P O BOX 410 AGOURA HILLS, CA 91376 |
| Contractor | Eagle Development & Construction Inc; Lic. No.: 800756-B | 31352 VIA COLINAS STE 101 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Doss, Richard E; Lic. No.: C48987 | 30141 AGOURA RD 200 AGOURA HILLS, CA 91301 |
| Engineer | Garcia, Lionel Jesus; Lic. No.: S4653 | 23890 HAWTHORNE BLVD TORRANCE, CA 90505 |
| Engineer | Hollingsworth, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/1/2022 | Partial Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/28/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 9/28/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 11/1/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 11/21/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/9/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/1/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/11/2023 | Approved | RAUL BARAJAS |
| Pre-Inspection | 9/1/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 9/6/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 9/12/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/10/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/13/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 3/28/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/24/2024 | Conditional Approval | RAUL BARAJAS |
| Pre-Inspection | 5/10/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 5/16/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/16/2024 | Conditional Approval | RAUL BARAJAS |
| Deck | 9/26/2024 | Approved | RAUL BARAJAS |
| Sewer | 9/26/2024 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 4/7/2025 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/8/2025 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 9/17/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Pre-Inspection | 9/17/2025 | Partial Inspection | BRENDAN MORELLI |
| HVAC-Rough | 2/23/2026 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/23/2026 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 4/21/2026 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/6/2026 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/6/2026 | Not Ready for Inspection | CRAIG VAUGHAN |