2078 N STRADELLA ROAD 90077

Certificate Information: 2078 N STRADELLA ROAD 90077

Application / Permit
16010-30000-06432
Plan Check / Job No.
B16WL07003
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story single family residence with attached 3-car garage and basement.
Permit Issued
Issued on 6/25/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2016 APPLICANT
Assigned to Plan Check Engineer 2/16/2017 ERWIN PASCUA
Corrections Issued 2/23/2017 ERWIN PASCUA
Quality Review Completed 2/28/2017 STEVEN KIM
Building Plans Picked Up 3/7/2017 APPLICANT
Applicant returned to address corrections 3/5/2018 ERWIN PASCUA
Applicant returned to address corrections 4/5/2018 ERWIN PASCUA
Green Plans Picked Up 5/23/2018 APPLICANT
Plan Check Approved 6/15/2018 ERWIN PASCUA
Issued 6/25/2018 LADBS
CofO in Progress 9/4/2025 CHRISTOPHER WILSON
Permit Finaled 9/5/2025 RICHARD STEINBACH
CofO Issued 9/5/2025 RICHARD STEINBACH
Permit Finaled 9/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/27/2018 KRISTEN LY
BHO/Hillside ordinance Cleared 3/27/2018 KRISTEN LY
BHO/Hillside ordinance Cleared 3/27/2018 KRISTEN LY
BHO/Hillside ordinance Cleared 3/27/2018 KRISTEN LY
Eng Process Fee Ord 176,300 Cleared 3/27/2018 KRISTEN LY
Permit Cleared 3/27/2018 KRISTEN LY
Sewer availability Cleared 3/27/2018 KRISTEN LY
Hydrant and Access approval Cleared 3/28/2018 JOHN CONNEALLY
Low Impact Development Cleared 5/22/2018 MITESH PATEL
Building over 3-story or 36-ft Cleared 5/24/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/24/2018 CALOSHA APPROVED
GPI Written Notices Cleared 5/24/2018 ERWIN PASCUA
Grading Pre-Inspection Cleared 5/24/2018 ERWIN PASCUA
Roof/Waste drainage to street Cleared 5/24/2018 HISASHI KOBAYAKAWA
Green Code Cleared 6/14/2018 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Geologist , ; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE,

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2018 Approved CARLOS MATAMOROS
Pre-Inspection 5/1/2019 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 8/28/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/31/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 9/24/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 10/3/2019 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 10/10/2019 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/15/2019 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 10/15/2019 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 10/22/2019 Partial Approval ROBERT SHELLY
Footing/Foundation/Slab 10/29/2019 Partial Inspection ANTHONY MCDOWALL
Deputy Grading 11/15/2019 Approved MATT KELLERMAN
Deputy Grading 11/18/2019 Conditional Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/19/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/20/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/25/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Grading 1/6/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 1/6/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 1/28/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/3/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 2/7/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/21/2020 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 2/21/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/24/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/25/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Grading 3/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 3/5/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 3/6/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 3/31/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/2/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/23/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/4/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/6/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/21/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/21/2020 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/22/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/28/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 5/29/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/2/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/9/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/10/2020 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/11/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/16/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/19/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/29/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/29/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Shotcrete 6/30/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 7/6/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/9/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 2/3/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/5/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/9/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/24/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/24/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/8/2021 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 6/8/2021 Not Ready for Inspection MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 6/15/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/18/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/11/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/13/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 8/23/2021 Conditional Approval CHRISTOPHER WILSON
Pre-Inspection 10/8/2021 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 10/8/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/8/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 10/20/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 10/21/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 1/5/2022 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Inspection MICHAEL PELHAM
Pre-Inspection 1/25/2022 Approved BRENDAN LOONEY
Pre-Inspection 1/25/2022 Approved CARLOS MATAMOROS
Pre-Inspection 1/25/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 2/7/2022 Partial Inspection CHRISTOPHER WILSON
Deputy Wood Construction 3/3/2022 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval CARLOS MATAMOROS
Gas Test 4/8/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 8/15/2022 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 8/22/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/25/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/31/2022 Partial Approval CLAYTON GRAHAM
Wood Frame 9/20/2022 Corrections Issued CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 12/1/2022 Corrections Issued CHRISTOPHER WILSON
Shower Pan 12/7/2022 Corrections Issued STEPHANIE SWANSON
Pre-Inspection 12/12/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 12/14/2022 Partial Approval CHRISTOPHER WILSON
Shower Pan 12/23/2022 Not Ready for Inspection CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 1/13/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 1/17/2023 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 1/24/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/25/2023 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 1/26/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/26/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/2/2023 Partial Approval CARLOS MATAMOROS
Wood Frame 2/3/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 2/7/2023 Partial Approval CARLOS MATAMOROS
Insulation 2/10/2023 Partial Approval MICHAEL PELHAM
Interior/Exterior Lathing 2/21/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 4/4/2023 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/7/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 4/11/2023 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 4/11/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 5/9/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/16/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/30/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 7/31/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/11/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 9/14/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 9/26/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/26/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 9/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 9/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/6/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/19/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 11/8/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 11/16/2023 Approved CHRISTOPHER WILSON
Insulation 11/27/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 12/1/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 12/8/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 12/20/2023 Approved CHRISTOPHER WILSON
Sewer 4/23/2024 Approved CHRISTOPHER WILSON
Service/Power Release 5/13/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 5/14/2024 Partial Approval CHRISTOPHER WILSON
Service/Power Release 5/20/2024 Corrections Issued CHRISTOPHER WILSON
Shower Pan 5/30/2024 Corrections Issued STEPHANIE SWANSON
Shower Pan 6/3/2024 Partial Approval CHRISTOPHER WILSON
Gas Test 6/6/2024 Approved CHRISTOPHER WILSON
Shower Pan 6/6/2024 Approved CHRISTOPHER WILSON
Grounding or Bonding 6/7/2024 Partial Approval CHRISTOPHER WILSON
Service/Power Release 6/12/2024 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 7/22/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 11/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 1/3/2025 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 1/3/2025 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 1/9/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 1/14/2025 Partial Approval CARLOS MATAMOROS
Special/Order Compliance 1/31/2025 Corrections Issued MICHAEL PELHAM
Enclosure/Fence 2/26/2025 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 2/26/2025 Partial Inspection CHRISTOPHER WILSON
Gas Test 2/27/2025 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 3/4/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 4/22/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 6/10/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 6/18/2025 Approved CHRISTOPHER WILSON
PLUMBING-Final 6/26/2025 Corrections Issued CHRISTOPHER WILSON
Green Building Final 7/1/2025 Approved CHRISTOPHER WILSON
PLUMBING-Final 7/1/2025 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/30/2025 Approved CHRISTOPHER WILSON
Final 7/30/2025 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 7/30/2025 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 7/30/2025 Approved CHRISTOPHER WILSON
Reinforced Masonry Frame 7/30/2025 Approved CHRISTOPHER WILSON
Smoke Detectors 7/30/2025 Approved CHRISTOPHER WILSON
Structural Steel Frame 7/30/2025 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/30/2025 Approved CHRISTOPHER WILSON
Final 8/25/2025 Not Ready for Inspection CHRISTOPHER WILSON
Final 8/28/2025 OK to Issue CofO CHRISTOPHER WILSON