155 N ANITA AVE 90049

Certificate Information: 155 N ANITA AVE 90049

Application / Permit
16010-30000-06244
Plan Check / Job No.
B16WL06882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 109'5" x 46'0" 2-story SFD with roof deck, basement, and 3-car garage. Fully sprinklered per NFPA 13D.
Permit Issued
Issued on 6/25/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2016 APPLICANT
Assigned to Plan Check Engineer 2/2/2017 JOSE RODRIGUEZ
Corrections Issued 2/16/2017 JOSE RODRIGUEZ
Quality Review Completed 2/21/2017 STEVEN KIM
Applicant returned to address corrections 4/19/2017 JOSE RODRIGUEZ
Applicant returned to address corrections 5/11/2017 JOSE RODRIGUEZ
Green Plans Picked Up 10/11/2017 APPLICANT
Plan Check Approved 6/25/2018 JOSE RODRIGUEZ
Issued 6/25/2018 LADBS
Building Plans Picked Up 4/14/2020 APPLICANT
CofO in Progress 6/27/2024 KEVIN SARGSYAN
Permit Finaled 7/10/2024 DANIEL ORRANTE
CofO Issued 7/10/2024 DANIEL ORRANTE
Permit Finaled 7/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 5/11/2017 JOSE RODRIGUEZ
Grading Pre-Inspection Cleared 5/11/2017 JOSE RODRIGUEZ
Address approval Cleared 7/5/2017 ALFREDO JARA
Hydrant and Access approval Cleared 7/5/2017 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 9/20/2017 CELINA MORENO
Sewer availability Cleared 9/20/2017 CELINA MORENO
BHO/Hillside ordinance Cleared 9/25/2017 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 9/25/2017 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 9/25/2017 DENNIS BRAGIN
Low Impact Development Cleared 11/3/2017 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 11/20/2017 ANDREW SLUSSER
Green Code Cleared 11/29/2017 RICHARD GARCIA
Permit Cleared 6/5/2018 STEVEN JIN

Contact Information

Contractor Owner-Builder       ,
Engineer Barajas, Jorge Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Markov, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201
Engineer Namvar, Mohammad Alipour; Lic. No.: C39797 231 VISTA DEL MAR STE D      REDONDO BEACH, CA 90277

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/24/2020 Not Ready for Inspection TIM CHRISTENSEN
Pre-Inspection 2/24/2020 Not Ready for Inspection TIM CHRISTENSEN
Piling/Pier/Caisson 3/17/2020 Corrections Issued TIM CHRISTENSEN
Deputy Grading 3/18/2020 Partial Approval TIM CHRISTENSEN
Piling/Pier/Caisson 3/18/2020 Partial Approval TIM CHRISTENSEN
Deputy Grading 3/19/2020 Conditional Approval TIM CHRISTENSEN
Deputy Grading 3/20/2020 Conditional Approval TIM CHRISTENSEN
Deputy Grading 4/20/2020 Conditional Approval TIM CHRISTENSEN
Deputy Grading 4/21/2020 Conditional Approval TIM CHRISTENSEN
Deputy Grading 4/22/2020 No Access for Inspection TIM CHRISTENSEN
Deputy Grading 4/29/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 5/29/2020 Conditional Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 6/26/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 7/21/2020 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 7/24/2020 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 7/28/2020 Partial Approval TIM CHRISTENSEN
PLUMBING-Rough 8/21/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 8/28/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 9/21/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 9/24/2020 Partial Approval TIM CHRISTENSEN
Deputy Steel/Welding 10/14/2020 Conditional Approval TIM CHRISTENSEN
Deputy Steel/Welding 10/16/2020 Conditional Approval TIM CHRISTENSEN
Deputy Steel/Welding 10/19/2020 Conditional Approval TIM CHRISTENSEN
Structural Steel Frame 10/21/2020 Corrections Issued TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Partial Approval OGANES TARAKHCHYAN
Structural Steel Frame 12/2/2020 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 6/30/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 7/7/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 7/12/2021 Partial Approval PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/12/2021 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 10/19/2021 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 10/19/2021 Corrections Issued JUAN VALENZUELA
Masonry Wall/Backfill 11/24/2021 Corrections Issued JUAN VALENZUELA
Masonry Wall/Backfill 11/30/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 2/3/2022 Not Ready for Inspection JUAN VALENZUELA
Special/Order Compliance 2/3/2022 Partial Inspection JUAN VALENZUELA
Drywall Nailing 2/10/2022 Partial Approval RYAN SALAZAR
Insulation 2/10/2022 Partial Approval RYAN SALAZAR
HVAC-Rough 2/15/2022 Partial Approval ANDREW NAVE
HVAC-Rough 5/12/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/4/2022 Corrections Issued JUAN VALENZUELA
HVAC-Rough 10/5/2022 Approved JUAN VALENZUELA
Special/Order Compliance 10/5/2022 Partial Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 10/24/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 10/28/2022 Corrections Issued JUAN VALENZUELA
Insulation 11/18/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 11/22/2022 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 11/28/2022 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 11/30/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 11/30/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 12/5/2022 Corrections Issued DAVID FEILER
Green Building Rough 12/5/2022 Corrections Issued DAVID FEILER
Verify Sprinkler Sign Off 12/5/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 12/9/2022 Partial Approval DAVID FEILER
Green Building Rough 12/9/2022 Approved DAVID FEILER
Interior/Exterior Lathing 12/13/2022 Partial Approval ASHLEY THOMPSON
Insulation 12/15/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/19/2022 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 12/22/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 2/7/2023 Approved KEVIN SARGSYAN
Insulation 4/4/2023 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 4/13/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 4/17/2023 Approved KEVIN SARGSYAN
Shower Pan 5/4/2023 Corrections Issued KEVIN SARGSYAN
Shower Pan 5/10/2023 Approved MICHAEL PELHAM
Underground Mechanical 11/9/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 11/16/2023 Partial Approval KEVIN SARGSYAN
Gas Test 3/29/2024 Not Ready for Inspection KEVIN SARGSYAN
Sewer 3/29/2024 Approved KEVIN SARGSYAN
Gas Test 4/2/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved KEVIN SARGSYAN
ELECTRICAL-Rough 4/29/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 4/30/2024 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 5/1/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 5/3/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 5/9/2024 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 5/9/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 5/14/2024 Approved KEVIN SARGSYAN
Service/Power Release 5/14/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 5/22/2024 Approved KEVIN SARGSYAN
Service/Power Release 5/22/2024 Approved KEVIN SARGSYAN
Final 6/7/2024 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 6/7/2024 Approved KEVIN SARGSYAN
Green Building Final 6/7/2024 Approved KEVIN SARGSYAN
Smoke Detectors 6/7/2024 Approved KEVIN SARGSYAN
Final 6/18/2024 Corrections Issued KEVIN SARGSYAN
Final 6/26/2024 OK to Issue CofO KEVIN SARGSYAN