155 N ANITA AVE 90049
Certificate Information: 155 N ANITA AVE 90049
- Application / Permit
- 16010-30000-06244
- Plan Check / Job No.
- B16WL06882
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 109'5" x 46'0" 2-story SFD with roof deck, basement, and 3-car garage. Fully sprinklered per NFPA 13D.
- Permit Issued
- Issued on 6/25/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2017 | JOSE RODRIGUEZ |
| Corrections Issued | 2/16/2017 | JOSE RODRIGUEZ |
| Quality Review Completed | 2/21/2017 | STEVEN KIM |
| Applicant returned to address corrections | 4/19/2017 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 5/11/2017 | JOSE RODRIGUEZ |
| Green Plans Picked Up | 10/11/2017 | APPLICANT |
| Plan Check Approved | 6/25/2018 | JOSE RODRIGUEZ |
| Issued | 6/25/2018 | LADBS |
| Building Plans Picked Up | 4/14/2020 | APPLICANT |
| CofO in Progress | 6/27/2024 | KEVIN SARGSYAN |
| Permit Finaled | 7/10/2024 | DANIEL ORRANTE |
| CofO Issued | 7/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/11/2017 | JOSE RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 5/11/2017 | JOSE RODRIGUEZ |
| Address approval | Cleared | 7/5/2017 | ALFREDO JARA |
| Hydrant and Access approval | Cleared | 7/5/2017 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2017 | CELINA MORENO |
| Sewer availability | Cleared | 9/20/2017 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 9/25/2017 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 9/25/2017 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 9/25/2017 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 11/3/2017 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 11/20/2017 | ANDREW SLUSSER |
| Green Code | Cleared | 11/29/2017 | RICHARD GARCIA |
| Permit | Cleared | 6/5/2018 | STEVEN JIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barajas, Jorge Luis; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Markov, George P; Lic. No.: C55855 | 1623 THOMPSON AVE GLENDALE, CA 91201 |
| Engineer | Namvar, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 2/24/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Pre-Inspection | 2/24/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 3/17/2020 | Corrections Issued | TIM CHRISTENSEN |
| Deputy Grading | 3/18/2020 | Partial Approval | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 3/18/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Grading | 3/19/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Grading | 3/20/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Grading | 4/20/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Grading | 4/21/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Grading | 4/22/2020 | No Access for Inspection | TIM CHRISTENSEN |
| Deputy Grading | 4/29/2020 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 5/29/2020 | Conditional Approval | TIM CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/26/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/21/2020 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/28/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 8/21/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 8/28/2020 | Conditional Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 9/21/2020 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/24/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Steel/Welding | 10/14/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Steel/Welding | 10/16/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Steel/Welding | 10/19/2020 | Conditional Approval | TIM CHRISTENSEN |
| Structural Steel Frame | 10/21/2020 | Corrections Issued | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Structural Steel Frame | 12/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/30/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/7/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 7/12/2021 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/12/2021 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/19/2021 | Corrections Issued | JUAN VALENZUELA |
| Masonry Wall/Backfill | 11/24/2021 | Corrections Issued | JUAN VALENZUELA |
| Masonry Wall/Backfill | 11/30/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 2/3/2022 | Partial Inspection | JUAN VALENZUELA |
| Drywall Nailing | 2/10/2022 | Partial Approval | RYAN SALAZAR |
| Insulation | 2/10/2022 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 2/15/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 5/12/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/4/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 10/5/2022 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 10/5/2022 | Partial Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 10/24/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 10/28/2022 | Corrections Issued | JUAN VALENZUELA |
| Insulation | 11/18/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/22/2022 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/28/2022 | Not Ready for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 11/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 11/30/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/2/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/5/2022 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 12/5/2022 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 12/5/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 12/9/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 12/9/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 12/13/2022 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 12/15/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/19/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/22/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 4/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 4/13/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/17/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 5/4/2023 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 5/10/2023 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 11/9/2023 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 11/16/2023 | Partial Approval | KEVIN SARGSYAN |
| Gas Test | 3/29/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 3/29/2024 | Approved | KEVIN SARGSYAN |
| Gas Test | 4/2/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/29/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 4/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 5/1/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/3/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/9/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 5/9/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 5/14/2024 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 5/22/2024 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 5/22/2024 | Approved | KEVIN SARGSYAN |
| Final | 6/7/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/7/2024 | Approved | KEVIN SARGSYAN |
| Green Building Final | 6/7/2024 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 6/7/2024 | Approved | KEVIN SARGSYAN |
| Final | 6/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| Final | 6/26/2024 | OK to Issue CofO | KEVIN SARGSYAN |