Pre-Inspection
|
10/15/2018
|
Partial Inspection
|
DANIEL GONZALEZ
|
|
Pre-Inspection
|
1/9/2019
|
Approved
|
HAMIK HARTOUNIAN
|
|
Special/Order Compliance
|
1/18/2019
|
Approved
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
3/27/2019
|
Partial Inspection
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
4/12/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
4/17/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Special/Order Compliance
|
5/1/2019
|
Approved
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
5/6/2019
|
Partial Inspection
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
5/17/2019
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
5/17/2019
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
6/4/2019
|
Partial Inspection
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
6/7/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
6/28/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
7/1/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Piling/Pier/Caisson
|
10/17/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2019
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
11/1/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
11/6/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
11/21/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Deputy Grading
|
12/2/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Deputy Grading
|
12/9/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Deputy Grading
|
12/13/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Deputy Grading
|
12/16/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Piling/Pier/Caisson
|
1/6/2020
|
Partial Approval
|
RICHARD STEINBACH
|
|
Piling/Pier/Caisson
|
1/17/2020
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
1/28/2020
|
Partial Approval
|
ROBERT CORNELL
|
|
Deputy Grading
|
1/30/2020
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Piling/Pier/Caisson
|
2/4/2020
|
Partial Approval
|
ROBERT CORNELL
|
|
Excavation/Setback/Form/Re-Bar
|
2/20/2020
|
Partial Approval
|
RICHARD STEINBACH
|
|
Excavation/Setback/Form/Re-Bar
|
3/16/2020
|
Partial Approval
|
RICHARD STEINBACH
|
|
PLUMBING-Rough
|
5/27/2020
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
6/12/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
7/6/2020
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
7/10/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2020
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
8/7/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
8/12/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
8/12/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
8/13/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
8/18/2020
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
8/24/2020
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
8/26/2020
|
Approved
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
8/28/2020
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
9/1/2020
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
9/2/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
9/15/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
9/24/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/2/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/5/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Underground Mechanical
|
10/8/2020
|
Approved
|
COREY HUPP
|
|
Footing/Foundation/Slab
|
10/14/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/23/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/29/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
11/6/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
11/18/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
12/7/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
HVAC-Rough
|
12/7/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
12/16/2020
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Piling/Pier/Caisson
|
12/21/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
12/22/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
Underground Mechanical
|
1/12/2021
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
1/14/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
1/20/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
1/21/2021
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
2/11/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
3/1/2021
|
Partial Inspection
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
3/12/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Light Gage Steel Frame
|
3/12/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
3/15/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Reinforced Masonry Frame
|
3/26/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
3/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/9/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/14/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/20/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
5/11/2021
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
5/12/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
5/20/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
6/7/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
6/8/2021
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
6/8/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
6/21/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
ELECTRICAL-Rough
|
7/12/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
HVAC-Rough
|
7/21/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
PLUMBING-Rough
|
7/27/2021
|
Partial Inspection
|
RICHARD STEINBACH
|
|
ELECTRICAL-Rough
|
8/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
HVAC-Rough
|
8/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
8/30/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
9/13/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
BUILDING-Rough-Frame
|
9/21/2021
|
Corrections Issued
|
RICHARD STEINBACH
|
|
ELECTRICAL-Rough
|
9/21/2021
|
Approved
|
RICHARD STEINBACH
|
|
Green Building Rough
|
9/21/2021
|
Approved
|
RICHARD STEINBACH
|
|
HVAC-Rough
|
9/21/2021
|
Approved
|
RICHARD STEINBACH
|
|
PLUMBING-Rough
|
9/21/2021
|
Approved
|
RICHARD STEINBACH
|
|
Verify Sprinkler Sign Off
|
9/21/2021
|
Partial Approval
|
RICHARD STEINBACH
|
|
Drywall Nailing
|
11/5/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
12/23/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
2/1/2022
|
Partial Inspection
|
RAUL BARAJAS
|
|
Service/Power Release
|
3/1/2022
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
5/3/2022
|
Approved
|
RAUL BARAJAS
|
|
Shower Pan
|
5/31/2022
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
9/1/2022
|
Approved
|
RAUL BARAJAS
|
|
Rough-Elec/Plmb/HVAC
|
9/1/2022
|
Approved
|
RAUL BARAJAS
|
|
Pool Piping
|
2/3/2023
|
No Access for Inspection
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/13/2023
|
Approved
|
RAUL BARAJAS
|
|
Sewer
|
5/5/2023
|
Approved
|
RAUL BARAJAS
|
|
Sewer
|
5/8/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Final
|
5/24/2023
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
7/7/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
7/7/2023
|
Approved
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
7/19/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Reinforced Concrete Frame
|
7/19/2023
|
Approved
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
7/19/2023
|
Approved
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
8/23/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
8/24/2023
|
Approved
|
RAUL BARAJAS
|
|
PLUMBING-Final
|
9/6/2023
|
Approved
|
RAUL BARAJAS
|
|
Pre-Gunite
|
9/6/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
HVAC-Final
|
10/5/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Drywall Nailing
|
11/16/2023
|
Approved
|
RAUL BARAJAS
|
|
Final
|
11/16/2023
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Green Building Final
|
11/16/2023
|
Approved
|
RAUL BARAJAS
|
|
HVAC-Final
|
11/16/2023
|
Approved
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
11/16/2023
|
SGSOV Approved
|
RAUL BARAJAS
|
|
Smoke Detectors
|
11/16/2023
|
Approved
|
RAUL BARAJAS
|
|
Final
|
12/6/2023
|
OK to Issue CofO
|
RAUL BARAJAS
|