318 S MEDIO DR 90049
Certificate Information: 318 S MEDIO DR 90049
- Application / Permit
- 16010-30000-05746
- Plan Check / Job No.
- B16WL06612
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) s.f.d. w/ basement and attached garage
- Permit Issued
- Issued on 12/7/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2016 | TARIK SAOUD |
| Corrections Issued | 1/2/2017 | TARIK SAOUD |
| Quality Review Completed | 1/5/2017 | STEVEN KIM |
| Building Plans Picked Up | 1/9/2017 | APPLICANT |
| Green Plans Picked Up | 1/9/2017 | APPLICANT |
| Plan Check Approved | 12/7/2017 | TARIK SAOUD |
| Issued | 12/7/2017 | LADBS |
| CofO in Progress | 11/13/2021 | JOHN KIDWELL |
| Permit Finaled | 12/3/2021 | DANIEL ORRANTE |
| CofO Issued | 12/3/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/3/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2017 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2017 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 7/11/2017 | NOAH MCCOY |
| Permit | Cleared | 7/11/2017 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/11/2017 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 9/26/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 9/26/2017 | JOHN LIN |
| Hydrant and Access approval | Cleared | 10/4/2017 | ROBERT DUFF |
| Green Code | Cleared | 10/25/2017 | TARIK SAOUD |
| Excavation more than 5-ft deep | Cleared | 12/7/2017 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 12/7/2017 | TARIK SAOUD |
Contact Information
| Contractor | C & C Partners Design/Build Firm Inc; Lic. No.: 654337-B | 1601 PACIFIC COAST HWY STE 160 HERMOSA BEACH, CA 90254 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Tucker, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/29/2018 | Partial Inspection | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 9/13/2018 | Conditional Approval | VINCENT SCIPIONI |
| Deputy Reinf. Concrete | 9/21/2018 | Conditional Approval | VINCENT SCIPIONI |
| Pre-Inspection | 9/21/2018 | Partial Inspection | VINCENT SCIPIONI |
| Reinforced Concrete Frame | 9/24/2018 | Partial Approval | VINCENT SCIPIONI |
| PLUMBING-Rough | 10/17/2018 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 10/19/2018 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 11/5/2018 | Partial Approval | DANIEL ORRANTE |
| Deputy Drilled-In Anchors | 1/23/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/23/2019 | Corrections Issued | KENNETH NAGLE |
| Deputy Reinf. Concrete | 1/28/2019 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 1/28/2019 | Conditional Approval | DANIEL ORRANTE |
| Deputy Steel/Welding | 2/13/2019 | Conditional Approval | DANIEL ORRANTE |
| Deputy Reinf. Concrete | 2/19/2019 | Conditional Approval | RICHARD STEINBACH |
| Wood Frame | 2/20/2019 | Partial Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 2/21/2019 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 2/22/2019 | Conditional Approval | MICHAEL TEMPLE |
| Deputy Reinf. Concrete | 3/12/2019 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 3/14/2019 | Partial Approval | RICHARD STEINBACH |
| Wood Frame | 5/8/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 5/28/2019 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2019 | Conditional Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2019 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 12/19/2019 | Approved | TIM CHRISTENSEN |
| PLUMBING-Rough | 2/10/2020 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 2/24/2020 | Corrections Issued | DANNY TOLENTINO |
| ELECTRICAL-Rough | 3/3/2020 | Approved | ROBERT SHELLY |
| HVAC-Rough | 3/23/2020 | Approved | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2020 | Partial Approval | DANNY TOLENTINO |
| Deputy Wood Construction | 5/8/2020 | No Access for Inspection | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 5/11/2020 | Approved | DANNY TOLENTINO |
| Green Building Rough | 5/11/2020 | Approved | DANNY TOLENTINO |
| Verify Sprinkler Sign Off | 5/11/2020 | Approved | DANNY TOLENTINO |
| Interior/Exterior Lathing | 5/29/2020 | Partial Approval | DANNY TOLENTINO |
| Shower Pan | 5/29/2020 | Approved | DANNY TOLENTINO |
| Insulation | 6/8/2020 | Approved | ROBERT SHELLY |
| Drywall Nailing | 6/22/2020 | Approved | ROBERT SHELLY |
| Interior/Exterior Lathing | 6/25/2020 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 8/31/2020 | Approved | TIM CHRISTENSEN |
| Sewer | 2/24/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 2/26/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/18/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 3/25/2021 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 3/30/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/13/2021 | Approved | ROBERT SHELLY |
| Deputy Reinf. Concrete | 5/11/2021 | Approved | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Partial Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/25/2021 | Partial Approval | JOHN KIDWELL |
| HVAC-Final | 6/15/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 6/17/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 7/1/2021 | Approved | JOHN KIDWELL |
| Pre-Inspection | 10/1/2021 | Partial Inspection | JOHN KIDWELL |
| Final | 11/3/2021 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/3/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 11/3/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 11/3/2021 | Approved | JOHN KIDWELL |
| Smoke Detectors | 11/3/2021 | Approved | JOHN KIDWELL |
| Structural Steel Frame | 11/3/2021 | Approved | JOHN KIDWELL |
| Final | 11/12/2021 | OK to Issue CofO | JOHN KIDWELL |