2605 S SEPULVEDA BLVD 90064

Certificate Information: 2605 S SEPULVEDA BLVD 90064

Application / Permit
16010-30000-05451
Plan Check / Job No.
B16WL06314
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
new 3 units apartment building (4800 s.f.) with ground level parking garage.
Permit Issued
Issued on 11/2/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2016 APPLICANT
Assigned to Plan Check Engineer 12/8/2016 TARIK SAOUD
Corrections Issued 12/10/2016 TARIK SAOUD
Quality Review Completed 12/12/2016 STEVEN KIM
Disabled Access Plans Picked Up 1/5/2017 APPLICANT
Green Plans Picked Up 1/5/2017 APPLICANT
Building Plans Picked Up 1/17/2017 APPLICANT
Plan Check Approved 9/21/2018 TARIK SAOUD
Issued 11/2/2018 LADBS
CofO in Progress 6/11/2024 PAUL DAVIDSON
Permit Finaled 6/28/2024 HENRY BAGHDASSARIAN
CofO Issued 6/28/2024 HENRY BAGHDASSARIAN
Permit Finaled 6/28/2024 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 3/21/2017 AVALYN KAMACHI
Hydrant and Access approval Cleared 3/21/2017 ROBERT DUFF
Project located in CRA area Cleared 3/24/2017 CRAIG BULLOCK
Eng Process Fee Ord 176,300 Cleared 4/19/2017 CARLA VALLADARES
Highway dedication Cleared 4/19/2017 CARLA VALLADARES
Sewer availability Cleared 4/19/2017 CARLA VALLADARES
Permit Cleared 4/20/2017 BRIAN KELLY
Low Impact Development Cleared 5/5/2017 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 5/8/2017 OSCAR GUTIERREZ
DAS Clearance Cleared 5/10/2017 CHOI YAN
Fire Marshall Fire Life Safety Cleared 6/7/2017 DOMINIQUE MEDINA
Green Code Cleared 6/14/2017 BRYAN MEYER
Building over 3-story or 36-ft Cleared 6/27/2017 CALOSHA APPROVED

Contact Information

Architect Avila, Tom A; Lic. No.: C28086 3304 PICO BLVD # G      SANTA MONICA, CA 90405
Contractor Chien Construction; Lic. No.: 886365-B P O BOX 662      WALNUT, CA 91789
Engineer Rybak, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/23/2019 Not Ready for Inspection TONY HARTONO
METHANE-Barrier 5/23/2019 Not Ready for Inspection TONY HARTONO
METHANE-Subgrade 5/23/2019 Not Ready for Inspection TONY HARTONO
Piling/Pier/Caisson 5/23/2019 Not Ready for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 5/24/2019 Partial Inspection TONY HARTONO
Piling/Pier/Caisson 5/24/2019 Partial Inspection TONY HARTONO
Footing/Foundation/Slab 5/29/2019 Not Ready for Inspection TONY HARTONO
METHANE-Barrier 5/29/2019 Not Ready for Inspection TONY HARTONO
METHANE-Subgrade 5/29/2019 Not Ready for Inspection TONY HARTONO
Footing/Foundation/Slab 9/10/2019 Not Ready for Inspection TONY HARTONO
METHANE-Barrier 9/10/2019 Not Ready for Inspection TONY HARTONO
METHANE-Subgrade 9/10/2019 Not Ready for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 9/12/2019 Approved DERRICK SPENCER
Reinforced Concrete Frame 12/12/2019 Partial Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 12/16/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 1/22/2020 Approved TED RIES
Green Building Rough 1/29/2020 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Rough 1/29/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 1/29/2020 Not Ready for Inspection JEFF BYTHEWAY
Verify Sprinkler Sign Off 1/29/2020 Approved JEFF BYTHEWAY
Green Building Rough 2/4/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 2/4/2020 Partial Inspection JEFF BYTHEWAY
Green Building Rough 2/6/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 2/6/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 2/21/2020 Conditional Approval JEFF BYTHEWAY
METHANE-Barrier 2/21/2020 Conditional Approval JEFF BYTHEWAY
METHANE-Subgrade 2/21/2020 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/4/2020 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/5/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 5/6/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 5/8/2020 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/14/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 7/10/2020 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/23/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Not Ready for Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Not Ready for Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Approved JEFF BYTHEWAY
Insulation 2/4/2021 Partial Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Approved JEFF BYTHEWAY
Insulation 2/8/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 3/30/2021 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 6/8/2021 Partial Inspection JEFF BYTHEWAY
Wood Frame 7/22/2021 Partial Inspection JEFF BYTHEWAY
Light Gage Steel Frame 9/2/2021 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 9/13/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 9/13/2021 Approved JEFF BYTHEWAY
Structural Steel Frame 9/13/2021 Approved JEFF BYTHEWAY
Wood Frame 3/9/2022 Partial Approval JEFF BYTHEWAY
Insulation 5/6/2022 Approved JEFF BYTHEWAY
Wood Frame 5/6/2022 Approved JEFF BYTHEWAY
Insulation 6/9/2022 Corrections Issued JEFF BYTHEWAY
Drywall Nailing 7/25/2022 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 8/17/2022 Approved JEFF BYTHEWAY
Light Gage Steel Frame 10/21/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 10/25/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/25/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 10/28/2022 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/28/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 11/7/2022 Approved DERRICK SPENCER
Smoke Detectors 1/18/2023 Approved DERRICK SPENCER
Special/Order Compliance 1/18/2023 Approved DERRICK SPENCER
Special/Order Compliance 11/2/2023 Approved DERRICK SPENCER
Special/Order Compliance 11/8/2023 Approved DERRICK SPENCER
Drywall Nailing 11/20/2023 Approved DERRICK SPENCER
Light Gage Steel Frame 11/20/2023 Approved DERRICK SPENCER
Final 4/26/2024 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 4/26/2024 Approved PAUL DAVIDSON
Green Building Final 4/26/2024 Approved PAUL DAVIDSON
METHANE-Barrier 4/26/2024 Approved PAUL DAVIDSON
METHANE-Subgrade 4/26/2024 Approved PAUL DAVIDSON
Reinforced Concrete Frame 4/26/2024 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved PAUL DAVIDSON
Special/Order Compliance 5/8/2024 Approved NICK LAROCCA
Verify Rec and Parks Fee Memo 5/8/2024 Approved NICK LAROCCA
Posting Pre-Inspection 5/9/2024 Corrections Issued PAUL DAVIDSON
Final 6/10/2024 OK to Issue CofO PAUL DAVIDSON