823 N FULLER AVE 1-6 90046
Certificate Information: 823 N FULLER AVE 1-6 90046
- Application / Permit
- 16010-30000-05380
- Plan Check / Job No.
- B16WL06224
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- new 3-story, 6-unit apartment building with attached parking garage.
- Permit Issued
- Issued on 5/16/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Corrected on 8/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2017 | TARIK SAOUD |
| Disabled Access Plans Picked Up | 1/11/2017 | APPLICANT |
| Green Plans Picked Up | 1/11/2017 | APPLICANT |
| Corrections Issued | 1/13/2017 | TARIK SAOUD |
| Quality Review Completed | 1/19/2017 | STEVEN KIM |
| Building Plans Picked Up | 1/23/2017 | APPLICANT |
| Plan Check Approved | 5/2/2018 | TARIK SAOUD |
| Issued | 5/16/2018 | LADBS |
| CofO in Progress | 7/30/2020 | TERRY HERR |
| CofO Issued-Status Void | 7/30/2020 | TERRY HERR |
| Permit Finaled-Status Void | 7/30/2020 | TERRY HERR |
| Re-Activate Permit | 8/17/2020 | TERRY HERR |
| CofO Corrected | 8/17/2020 | TERRY HERR |
| Permit Finaled | 8/17/2020 | TERRY HERR |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/24/2017 | JESSE RAMOS |
| Address approval | Cleared | 2/24/2017 | RAVIL MANAPOV |
| Permit | Cleared | 2/24/2017 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 3/6/2017 | RAVIL MANAPOV |
| Frnt yard landscape/Water mgmt | Cleared | 3/10/2017 | DANALYNN DOMINGUEZ |
| Construction within easement | Cleared | 4/4/2017 | LUCIO FERRER |
| Hydrant and Access approval | Cleared | 1/24/2018 | ROBERT DUFF |
| DAS Clearance | Cleared | 1/29/2018 | CHOI YAN |
| Fire Marshall Fire Life Safety | Cleared | 2/12/2018 | ANDREW KO |
| Green Code | Cleared | 2/14/2018 | RICHARD GARCIA |
| Low Impact Development | Cleared | 2/22/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/22/2018 | ADRIAN SANCHEZ |
| Opn space landscape/Water mgmt | Cleared | 3/6/2018 | SARAH GOLDMAN |
Contact Information
| Architect | Tomalevski, Vladimir Bogdanov; Lic. No.: C22417 | 2332 COTNER AVENUE SUITE 303 LOS ANGELES, CA 90064 |
| Contractor | Zenko Slavey; Lic. No.: 927036-B | 17426 REVELLO DRIVE PACIFIC PALISADES, CA 90272 |
| Engineer | Azarbin, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Geologist | Miller, Jonathan Steven; Lic. No.: EG2391 | 2800 NEILSON WAY #210 SANTA MONICA, CA 90405 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2018 | Partial Approval | LARRY ARNICK |
| METHANE-Barrier | 6/29/2018 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 6/29/2018 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 8/6/2018 | Approved | LARRY ARNICK |
| METHANE-Barrier | 8/6/2018 | Approved | LARRY ARNICK |
| METHANE-Final | 8/6/2018 | Approved | LARRY ARNICK |
| METHANE-Subgrade | 8/6/2018 | Approved | LARRY ARNICK |
| Green Building Rough | 9/25/2018 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 9/25/2018 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 9/25/2018 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2018 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2018 | Partial Approval | LESLIE TRUJILLO |
| Final | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Final | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 1/11/2019 | SGSOV Not Ready | LARRY ARNICK |
| Smoke Detectors | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Structural Steel Frame | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 1/11/2019 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Wood Construction | 1/23/2019 | Conditional Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2019 | Partial Approval | JEFF BYTHEWAY |
| Deputy Wood Construction | 1/28/2019 | Conditional Approval | LARRY ARNICK |
| Green Building Rough | 3/5/2019 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 3/5/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 3/5/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 5/2/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Insulation | 5/2/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 5/2/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 5/2/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Wood Frame | 5/2/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Insulation | 5/6/2019 | Partial Approval | LARRY ARNICK |
| Green Building Rough | 5/9/2019 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 5/9/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 5/9/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 5/28/2019 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 5/28/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 5/28/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 5/30/2019 | Approved | LARRY ARNICK |
| Verify Sprinkler Sign Off | 5/30/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 5/30/2019 | Not Ready for Inspection | LARRY ARNICK |
| Insulation | 6/10/2019 | Approved | LARRY ARNICK |
| Drywall Nailing | 6/20/2019 | Partial Approval | LARRY ARNICK |
| Interior/Exterior Lathing | 6/20/2019 | Not Ready for Inspection | LARRY ARNICK |
| Drywall Nailing | 6/25/2019 | Approved | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 6/25/2019 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 6/28/2019 | Partial Approval | LARRY ARNICK |
| Interior/Exterior Lathing | 7/31/2019 | Not Ready for Inspection | LARRY ARNICK |
| Interior/Exterior Lathing | 8/2/2019 | Approved | JAMES POWERS |
| Masonry Wall/Backfill | 10/9/2019 | Partial Approval | LARRY ARNICK |
| Masonry Wall/Backfill | 10/22/2019 | Order to Comply Issued | LARRY ARNICK |
| Masonry Wall/Backfill | 10/25/2019 | Not Ready for Inspection | LARRY ARNICK |
| Masonry Wall/Backfill | 10/28/2019 | Approved | LARRY ARNICK |
| Masonry Wall/Backfill | 11/14/2019 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 11/14/2019 | Partial Inspection | LARRY ARNICK |
| Special/Order Compliance | 11/27/2019 | Partial Inspection | LARRY ARNICK |
| Special/Order Compliance | 3/3/2020 | Partial Inspection | LARRY ARNICK |
| Final | 4/15/2020 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Final | 4/15/2020 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 4/15/2020 | SGSOV Not Ready | LARRY ARNICK |
| Smoke Detectors | 4/15/2020 | Not Ready for Inspection | LARRY ARNICK |
| Structural Steel Frame | 4/15/2020 | Approved | LARRY ARNICK |
| Verify Sprinkler Sign Off | 4/15/2020 | Approved | LARRY ARNICK |
| Wood Frame | 4/15/2020 | Approved | LARRY ARNICK |
| Special/Order Compliance | 4/24/2020 | Partial Inspection | LARRY ARNICK |
| Final | 4/30/2020 | Corrections Issued | LARRY ARNICK |
| Green Building Final | 4/30/2020 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 4/30/2020 | SGSOV Approved | LARRY ARNICK |
| Smoke Detectors | 4/30/2020 | Approved | LARRY ARNICK |
| Final | 5/5/2020 | Corrections Issued | LARRY ARNICK |
| Green Building Final | 5/5/2020 | Corrections Issued | LARRY ARNICK |
| Final | 5/22/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Final | 5/22/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 5/27/2020 | Corrections Issued | LARRY ARNICK |
| Green Building Final | 5/27/2020 | Not Ready for Inspection | LARRY ARNICK |
| Final | 6/3/2020 | Corrections Issued | LARRY ARNICK |
| Green Building Final | 6/3/2020 | Conditional Approval | LARRY ARNICK |
| Final | 6/11/2020 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Final | 6/11/2020 | Not Ready for Inspection | LARRY ARNICK |
| Final | 6/22/2020 | Conditional Approval | LARRY ARNICK |
| Green Building Final | 6/22/2020 | Approved | LARRY ARNICK |