823 N FULLER AVE 1-6 90046

Certificate Information: 823 N FULLER AVE 1-6 90046

Application / Permit
16010-30000-05380
Plan Check / Job No.
B16WL06224
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
new 3-story, 6-unit apartment building with attached parking garage.
Permit Issued
Issued on 5/16/2018
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 8/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2016 APPLICANT
Assigned to Plan Check Engineer 1/5/2017 TARIK SAOUD
Disabled Access Plans Picked Up 1/11/2017 APPLICANT
Green Plans Picked Up 1/11/2017 APPLICANT
Corrections Issued 1/13/2017 TARIK SAOUD
Quality Review Completed 1/19/2017 STEVEN KIM
Building Plans Picked Up 1/23/2017 APPLICANT
Plan Check Approved 5/2/2018 TARIK SAOUD
Issued 5/16/2018 LADBS
CofO in Progress 7/30/2020 TERRY HERR
CofO Issued-Status Void 7/30/2020 TERRY HERR
Permit Finaled-Status Void 7/30/2020 TERRY HERR
Re-Activate Permit 8/17/2020 TERRY HERR
CofO Corrected 8/17/2020 TERRY HERR
Permit Finaled 8/17/2020 TERRY HERR

Permit Application Clearance Information

"Q" conditions Cleared 2/24/2017 JESSE RAMOS
Address approval Cleared 2/24/2017 RAVIL MANAPOV
Permit Cleared 2/24/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 3/6/2017 RAVIL MANAPOV
Sewer availability Cleared 3/6/2017 RAVIL MANAPOV
Frnt yard landscape/Water mgmt Cleared 3/10/2017 DANALYNN DOMINGUEZ
Construction within easement Cleared 4/4/2017 LUCIO FERRER
Hydrant and Access approval Cleared 1/24/2018 ROBERT DUFF
DAS Clearance Cleared 1/29/2018 CHOI YAN
Fire Marshall Fire Life Safety Cleared 2/12/2018 ANDREW KO
Green Code Cleared 2/14/2018 RICHARD GARCIA
Low Impact Development Cleared 2/22/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/22/2018 ADRIAN SANCHEZ
Opn space landscape/Water mgmt Cleared 3/6/2018 SARAH GOLDMAN

Contact Information

Architect Tomalevski, Vladimir Bogdanov; Lic. No.: C22417 2332 COTNER AVENUE SUITE 303      LOS ANGELES, CA 90064
Contractor Zenko Slavey; Lic. No.: 927036-B 17426 REVELLO DRIVE      PACIFIC PALISADES, CA 90272
Engineer Azarbin, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307
Geologist Miller, Jonathan Steven; Lic. No.: EG2391 2800 NEILSON WAY #210      SANTA MONICA, CA 90405

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/29/2018 Partial Approval LARRY ARNICK
METHANE-Barrier 6/29/2018 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 6/29/2018 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 8/6/2018 Approved LARRY ARNICK
METHANE-Barrier 8/6/2018 Approved LARRY ARNICK
METHANE-Final 8/6/2018 Approved LARRY ARNICK
METHANE-Subgrade 8/6/2018 Approved LARRY ARNICK
Green Building Rough 9/25/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 9/25/2018 Not Ready for Inspection LARRY ARNICK
Wood Frame 9/25/2018 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/25/2018 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/14/2018 Partial Approval LESLIE TRUJILLO
Final 1/11/2019 Not Ready for Inspection LARRY ARNICK
Green Building Final 1/11/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/11/2019 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 1/11/2019 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 1/11/2019 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 1/11/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/11/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/11/2019 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 1/23/2019 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 1/25/2019 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 1/28/2019 Conditional Approval LARRY ARNICK
Green Building Rough 3/5/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 3/5/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 3/5/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 5/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 5/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Interior/Exterior Lathing 5/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 5/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 5/2/2019 Not Ready for Inspection DANIEL MC AULIFFE
Insulation 5/6/2019 Partial Approval LARRY ARNICK
Green Building Rough 5/9/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/9/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/9/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 5/28/2019 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/28/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/28/2019 Not Ready for Inspection LARRY ARNICK
Green Building Rough 5/30/2019 Approved LARRY ARNICK
Verify Sprinkler Sign Off 5/30/2019 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/30/2019 Not Ready for Inspection LARRY ARNICK
Insulation 6/10/2019 Approved LARRY ARNICK
Drywall Nailing 6/20/2019 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 6/20/2019 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 6/25/2019 Approved DANIEL MC AULIFFE
Interior/Exterior Lathing 6/25/2019 Partial Approval DANIEL MC AULIFFE
Interior/Exterior Lathing 6/28/2019 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 7/31/2019 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 8/2/2019 Approved JAMES POWERS
Masonry Wall/Backfill 10/9/2019 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 10/22/2019 Order to Comply Issued LARRY ARNICK
Masonry Wall/Backfill 10/25/2019 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 10/28/2019 Approved LARRY ARNICK
Masonry Wall/Backfill 11/14/2019 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 11/14/2019 Partial Inspection LARRY ARNICK
Special/Order Compliance 11/27/2019 Partial Inspection LARRY ARNICK
Special/Order Compliance 3/3/2020 Partial Inspection LARRY ARNICK
Final 4/15/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 4/15/2020 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 4/15/2020 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 4/15/2020 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 4/15/2020 Approved LARRY ARNICK
Verify Sprinkler Sign Off 4/15/2020 Approved LARRY ARNICK
Wood Frame 4/15/2020 Approved LARRY ARNICK
Special/Order Compliance 4/24/2020 Partial Inspection LARRY ARNICK
Final 4/30/2020 Corrections Issued LARRY ARNICK
Green Building Final 4/30/2020 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 4/30/2020 SGSOV Approved LARRY ARNICK
Smoke Detectors 4/30/2020 Approved LARRY ARNICK
Final 5/5/2020 Corrections Issued LARRY ARNICK
Green Building Final 5/5/2020 Corrections Issued LARRY ARNICK
Final 5/22/2020 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 5/22/2020 Not Ready for Inspection DAVID BURKHEAD
Final 5/27/2020 Corrections Issued LARRY ARNICK
Green Building Final 5/27/2020 Not Ready for Inspection LARRY ARNICK
Final 6/3/2020 Corrections Issued LARRY ARNICK
Green Building Final 6/3/2020 Conditional Approval LARRY ARNICK
Final 6/11/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 6/11/2020 Not Ready for Inspection LARRY ARNICK
Final 6/22/2020 Conditional Approval LARRY ARNICK
Green Building Final 6/22/2020 Approved LARRY ARNICK