1125 N BEVERLY GLEN BLVD 90077
Certificate Information: 1125 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 16010-30000-05303
- Plan Check / Job No.
- B16WL06098
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story single family dwelling with basement garage
- Permit Issued
- Issued on 5/16/2018
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2016 | MARJAN SHENASI |
| Green Plans Picked Up | 12/30/2016 | APPLICANT |
| Corrections Issued | 1/3/2017 | MARJAN SHENASI |
| Quality Review Completed | 1/4/2017 | STEVEN KIM |
| Building Plans Picked Up | 1/5/2017 | APPLICANT |
| Applicant returned to address corrections | 3/8/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 3/16/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 3/30/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/10/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/19/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/2/2018 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/11/2018 | MARJAN SHENASI |
| Plan Check Approved | 5/16/2018 | MARJAN SHENASI |
| Issued | 5/16/2018 | LADBS |
| CofO in Progress | 10/9/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/13/2017 | TAO YANG |
| BHO/Hillside ordinance | Cleared | 10/13/2017 | TAO YANG |
| BHO/Hillside ordinance | Cleared | 10/13/2017 | TAO YANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2017 | TAO YANG |
| Permit | Cleared | 10/13/2017 | OSCAR GUTIERREZ |
| Hydrant and Access approval | Cleared | 2/1/2018 | PEJMAN NOORI |
| Low Impact Development | Cleared | 2/2/2018 | MITESH PATEL |
| ZI | Cleared | 3/8/2018 | DWAYNE WYATT |
| Excavation more than 5-ft deep | Cleared | 3/16/2018 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 3/16/2018 | MARJAN SHENASI |
| Sewer availability | Cleared | 4/3/2018 | HISASHI KOBAYAKAWA |
| Disturb/Remove Protected Trees | Cleared | 4/26/2018 | ADRIAN SANCHEZ |
| Construction within easement | Cleared | 5/2/2018 | WALTER RAMIREZ |
| Green Code | Cleared | 5/9/2018 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 5/9/2018 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Podegracz, Joseph David; Lic. No.: C78425 | PO BOX 1083 FRAZIER PARK, CA 93225 |
| Engineer | Skyers, Brian; Lic. No.: GE2627 | 20159 HEMMINGWAY STREET WINNETKA, CA 91306 |
| Geologist | Haenschke, Eirik Francis; Lic. No.: EG1597 | 9001 MONOGRAM AVENUE NORTH HILLS, CA 91343 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/16/2018 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/30/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 11/30/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 11/30/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 2/19/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/19/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/8/2021 | Partial Approval | ANTHONY MCDOWALL |
| Reinforced Masonry Frame | 5/7/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Reinforced Masonry Frame | 5/12/2021 | Partial Approval | ANTHONY MCDOWALL |
| Reinforced Masonry Frame | 5/25/2021 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 6/11/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 6/11/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Reinforced Masonry Frame | 6/18/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 10/27/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/18/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 2/18/2022 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 2/18/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 2/18/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 2/18/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 2/18/2022 | Corrections Issued | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 2/18/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/18/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/18/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 4/18/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 4/18/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/18/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 5/10/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 5/19/2022 | Approved | CHRISTOPHER WILSON |
| Final | 6/24/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/24/2022 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 6/24/2022 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/13/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 10/24/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 10/24/2023 | Approved | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 10/24/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Service/Power Release | 10/24/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 10/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 9/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 9/17/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 9/17/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 10/8/2024 | OK to Issue CofO | CHRISTOPHER WILSON |
| Service/Power Release | 10/8/2024 | Approved | CHRISTOPHER WILSON |