1852 S STONER AVE 90025
Certificate Information: 1852 S STONER AVE 90025
- Application / Permit
- 16010-30000-05175
- Plan Check / Job No.
- B16WL05924
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New construction s.f.d. in small subdivision: unit 2 Small lot subdivision pursuant to Preliminary Parcel Map No. AA-2015-3434-PMLA-SL. A certification of occupancy (temporary or final) shall not be issued until after the final map has been recorded. ************** 2 of 3 ******************************
- Permit Issued
- Issued on 3/16/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2016 | RICARDO RAMIREZ |
| Corrections Issued | 12/22/2016 | RICARDO RAMIREZ |
| Quality Review Completed | 12/28/2016 | STEVEN KIM |
| Building Plans Picked Up | 12/29/2016 | APPLICANT |
| Green Plans Picked Up | 12/29/2016 | APPLICANT |
| Applicant returned to address corrections | 2/27/2017 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 5/10/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 2/7/2018 | RICARDO RAMIREZ |
| Issued | 3/16/2018 | LADBS |
| CofO in Progress | 9/21/2021 | KENNETH NAGLE |
| Permit Finaled | 9/21/2021 | KENNETH NAGLE |
| CofO Issued | 9/21/2021 | KENNETH NAGLE |
| Permit Finaled | 9/21/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Watercourse | Cleared | 2/27/2017 | OSCAR GUTIERREZ |
| Address approval | Cleared | 3/3/2017 | HISASHI KOBAYAKAWA |
| CPC | Cleared | 4/20/2017 | JESSE RAMOS |
| Hydrant and Access approval | Cleared | 4/25/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 4/25/2017 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 4/25/2017 | CARLA VALLADARES |
| Green Code | Cleared | 5/3/2017 | BRYAN MEYER |
| Tract Map conditions | Cleared | 5/5/2017 | BRIAN CARR |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2017 | DENNIS BRAGIN |
| Sewer availability | Cleared | 5/10/2017 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 1/23/2018 | TAO YANG |
Contact Information
| Architect | Reiff, Brian A; Lic. No.: C27313 | 11816 LINDBLADE STREET CULVER CITY, CA 90230 |
| Contractor | Ocean Spaulding Inc; Lic. No.: 833486-B | 1061 NORTH SPAULDING AVENUE LOS ANGELES, CA 90046 |
| Engineer | Mina, Joseph Wadie; Lic. No.: C53465 | 7247 DARNOCH WY WEST HILLS, CA 91307 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/1/2018 | Partial Approval | MICHAEL PELHAM |
| Pre-Inspection | 5/1/2018 | Partial Inspection | MICHAEL PELHAM |
| Underground Mechanical | 5/9/2018 | Partial Approval | MICHAEL PELHAM |
| FLOOD-Elevation Certificate | 5/10/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/10/2018 | Partial Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/15/2018 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/11/2018 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/12/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/12/2018 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2018 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2018 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2018 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2018 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 3/20/2019 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2019 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 3/20/2019 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/20/2019 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 3/20/2019 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 3/22/2019 | Approved | ROBERT SHELLY |
| PLUMBING-Rough | 3/27/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 3/29/2019 | Conditional Approval | EVAN COOPER |
| FLOOD-Proofing Certificate | 3/29/2019 | Partial Approval | EVAN COOPER |
| Green Building Rough | 3/29/2019 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/29/2019 | Approved | EVAN COOPER |
| Special/Order Compliance | 3/29/2019 | Partial Inspection | ROBERT SHELLY |
| Verify Sprinkler Sign Off | 3/29/2019 | Partial Approval | EVAN COOPER |
| Shower Pan | 4/2/2019 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/9/2019 | Approved | ROBERT SHELLY |
| FLOOD-Proofing Certificate | 4/9/2019 | Approved | ROBERT SHELLY |
| Green Building Rough | 4/9/2019 | Approved | ROBERT SHELLY |
| Insulation | 4/9/2019 | Approved | ROBERT SHELLY |
| Verify Sprinkler Sign Off | 4/9/2019 | Approved | ROBERT SHELLY |
| Drywall Nailing | 4/19/2019 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/12/2019 | Approved | EVAN COOPER |
| Masonry Wall/Backfill | 1/22/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| Masonry Wall/Backfill | 1/28/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/4/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 6/30/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 7/20/2021 | Conditional Approval | OGANES TARAKHCHYAN |
| Green Building Final | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 7/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Structural Steel Frame | 7/20/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 8/6/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 8/6/2021 | Approved | OGANES TARAKHCHYAN |