601 N PERUGIA WAY 90077
Certificate Information: 601 N PERUGIA WAY 90077
- Application / Permit
- 16010-30000-05116
- Plan Check / Job No.
- B16WL05807
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- New detached rec. room (Pool bath)
- Permit Issued
- Issued on 2/23/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2016 | DIEGO BAUTISTA |
| Corrections Issued | 12/21/2016 | DIEGO BAUTISTA |
| Quality Review Completed | 12/22/2016 | STEVEN KIM |
| Building Plans Picked Up | 12/22/2016 | APPLICANT |
| Applicant returned to address corrections | 1/6/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 1/17/2017 | DIEGO BAUTISTA |
| Green Plans Picked Up | 1/30/2017 | APPLICANT |
| Applicant returned to address corrections | 2/22/2017 | DIEGO BAUTISTA |
| Plan Check Approved | 2/23/2017 | DIEGO BAUTISTA |
| Issued | 2/23/2017 | LADBS |
| CofO in Progress | 1/26/2021 | CHRISTOPHER WILSON |
| CofO Issued | 2/10/2021 | VINCENT COTTON |
| Permit Finaled | 2/10/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2017 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/20/2017 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 2/22/2017 | DIEGO BAUTISTA |
| Low Impact Development | Cleared | 2/22/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 2/22/2017 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Vertoch, Philip Girard; Lic. No.: C21731 | 1419-A CLOVERFIELD BLVD SANTA MONICA, CA 90404 |
| Contractor | Williams Craig R Construction Inc; Lic. No.: 479539-B | 100 N CRESCENT DR STE BEVERLY HILLS, CA 90210 |
| Engineer | Garcia, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Engineer | Naraghi-Arani, Kamran; Lic. No.: C40985 | 30423 CANWOOD STREET SUITE 223 AGOURA HILLS, CA 91301 |
| Engineer | White, William Michael; Lic. No.: C62111 | 17190 BALLINGER ST NORTHRIDGE, CA 91325 |
| Geologist | Clark, Christina Lynn; Lic. No.: EG2586 | 1317 E. PALMER AVE GLENDALE, CA 91205 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2017 | Partial Approval | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2018 | Partial Inspection | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Wood Frame | 6/6/2018 | Corrections Issued | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2018 | Partial Approval | MATT KELLERMAN |
| Wood Frame | 7/13/2018 | Approved | MATT KELLERMAN |
| Deputy Wood Construction | 10/5/2018 | Partial Approval | MATT KELLERMAN |
| Insulation | 11/20/2018 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/20/2018 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/2/2019 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 10/24/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/20/2020 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 11/20/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 12/9/2020 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/9/2020 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 12/9/2020 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 12/9/2020 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 12/9/2020 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 12/9/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/12/2021 | Approved | CHRISTOPHER WILSON |
| Final | 1/12/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 1/12/2021 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 1/12/2021 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 1/12/2021 | Approved | CHRISTOPHER WILSON |
| Final | 1/21/2021 | Conditional Approval | CHRISTOPHER WILSON |