12112 W MARINE ST 90066

Certificate Information: 12112 W MARINE ST 90066

Application / Permit
16010-30000-04756
Plan Check / Job No.
B16WL05373
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 2-story SFD w/ basement and attached garage
Permit Issued
Issued on 3/22/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2016 APPLICANT
Green Plans Picked Up 11/17/2016 APPLICANT
Assigned to Plan Check Engineer 11/23/2016 KAVIAN REFAHI
Corrections Issued 12/6/2016 DIEGO BAUTISTA
Quality Review Completed 12/9/2016 STEVEN KIM
Building Plans Picked Up 12/9/2016 APPLICANT
Applicant returned to address corrections 1/12/2017 DIEGO BAUTISTA
Plan Check Approved 3/22/2017 DIEGO BAUTISTA
Issued 3/22/2017 LADBS
CofO in Progress 1/7/2021 KENNETH NAGLE
Permit Finaled 1/7/2021 KENNETH NAGLE
CofO Issued 1/7/2021 KENNETH NAGLE
Permit Finaled 1/7/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2017 SEVAK ISAKHAYAN
Permit Cleared 2/17/2017 SEVAK ISAKHAYAN
Sewer availability Cleared 2/17/2017 SEVAK ISAKHAYAN
Hydrant and Access approval Cleared 3/6/2017 ROBERT DUFF
Green Code Cleared 3/7/2017 RICHARD GARCIA
Low Impact Development Cleared 3/7/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/7/2017 JAMES MORALEZ

Contact Information

Contractor M P Home Repair & Construction; Lic. No.: 745207-B 12113 MARINE ST      LOS ANGELES, CA 90066
Engineer Padilla, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033
Engineer Tucker, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615
Engineer Uhles, Scott Delane; Lic. No.: C72391 2909 ARIZONA AVE 5      SANTA MONICA, CA 90404

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/5/2017 Partial Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/20/2017 Partial Approval MICHAEL PELHAM
Deputy Reinf. Concrete 4/24/2017 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/8/2017 Partial Approval MICHAEL PELHAM
Deputy Reinf. Concrete 6/12/2017 Conditional Approval MICHAEL PELHAM
Masonry Wall/Backfill 6/21/2017 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/3/2017 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/27/2017 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/10/2017 Partial Approval MICHAEL PELHAM
Masonry Wall/Backfill 8/14/2017 Partial Approval MICHAEL PELHAM
Masonry Wall/Backfill 8/22/2017 Partial Approval MICHAEL PELHAM
Deputy Reinf. Masonry 8/23/2017 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/1/2017 Not Ready for Inspection MICHAEL PELHAM
Footing/Foundation/Slab 11/2/2017 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 12/11/2017 Partial Approval MICHAEL PELHAM
Deputy Reinf. Concrete 12/12/2017 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 1/5/2018 Approved MICHAEL PELHAM
Footing/Foundation/Slab 1/5/2018 Partial Approval MICHAEL PELHAM
Deputy Reinf. Concrete 1/8/2018 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Masonry 1/8/2018 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/2/2018 Partial Approval MICHAEL PELHAM
Masonry Wall/Backfill 2/9/2018 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 2/22/2018 Partial Approval MICHAEL PELHAM
Masonry Wall/Backfill 2/28/2018 Partial Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/23/2018 Partial Inspection ANDREW NAVE
Pre-Inspection 4/23/2018 Partial Inspection MICHAEL PELHAM
Deputy Reinf. Masonry 4/27/2018 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/3/2018 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/7/2018 Conditional Approval ANDREW NAVE
PLUMBING-Rough 6/15/2018 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/25/2018 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 7/13/2018 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 8/10/2018 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 8/23/2018 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 9/11/2018 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 9/18/2018 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/2/2018 Partial Approval ANDREW NAVE
Deputy Steel/Welding 10/17/2018 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 11/9/2018 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 3/19/2019 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 3/19/2019 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 3/19/2019 Conditional Approval KEVIN BEAULIEU
Verify Sprinkler Sign Off 3/19/2019 Not Ready for Inspection KEVIN BEAULIEU
Deputy Wood Construction 4/3/2019 Approved KEVIN BEAULIEU
PLUMBING-Rough 4/9/2019 Partial Approval KEVIN BEAULIEU
Shower Pan 4/24/2019 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 4/29/2019 Partial Approval KEVIN BEAULIEU
Gas Test 4/29/2019 Not Ready for Inspection KEVIN BEAULIEU
Verify Sprinkler Sign Off 4/29/2019 Not Ready for Inspection KEVIN BEAULIEU
ELECTRICAL-Rough 5/3/2019 Approved EVAN COOPER
BUILDING-Rough-Frame 5/13/2019 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 5/13/2019 Approved KEVIN BEAULIEU
Verify Sprinkler Sign Off 5/13/2019 Approved KEVIN BEAULIEU
BUILDING-Rough-Frame 5/15/2019 Approved KEVIN BEAULIEU
Insulation 5/24/2019 Approved KEVIN BEAULIEU
Drywall Nailing 6/5/2019 Approved EVAN COOPER
Interior/Exterior Lathing 6/19/2019 Partial Approval KEVIN BEAULIEU
Special/Order Compliance 9/23/2019 Partial Inspection KEVIN BEAULIEU
Service/Power Release 12/20/2019 Not Ready for Inspection DAVID FEILER
Special/Order Compliance 12/20/2019 Corrections Issued DAVID FEILER
Gas Test 1/28/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/1/2020 Corrections Issued KENNETH NAGLE
PLUMBING-Final 5/1/2020 Approved KENNETH NAGLE
ELECTRICAL-Final 5/15/2020 Approved OGANES TARAKHCHYAN
Final 5/15/2020 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/15/2020 Approved OGANES TARAKHCHYAN
Green Building Final 5/15/2020 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 5/15/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/15/2020 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 5/15/2020 Approved OGANES TARAKHCHYAN
Smoke Detectors 5/15/2020 Approved OGANES TARAKHCHYAN
Structural Steel Frame 5/15/2020 Approved OGANES TARAKHCHYAN
Final 6/5/2020 OK for TCO JUSTIN CURTIS
Green Building Final 6/5/2020 Not Ready for Inspection JUSTIN CURTIS
Final 9/14/2020 Conditional Approval EVAN COOPER
Green Building Final 9/14/2020 Approved EVAN COOPER
Final 9/21/2020 Partial Approval OGANES TARAKHCHYAN