330 S RENNIE AVE 5 90291

Certificate Information: 330 S RENNIE AVE 5 90291

Application / Permit
16010-30000-04600
Plan Check / Job No.
B16WL05213
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story SFD with roof deck, with attached 2-car garage (Lot 5). Small Lot Subdivision
Permit Issued
Issued on 10/25/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2016 APPLICANT
Assigned to Plan Check Engineer 10/20/2016 MARJAN SHENASI
Corrections Issued 10/24/2016 DIEGO BAUTISTA
Green Plans Picked Up 10/24/2016 APPLICANT
Quality Review Completed 10/27/2016 STEVEN KIM
Building Plans Picked Up 10/31/2016 APPLICANT
Applicant returned to address corrections 2/14/2017 DIEGO BAUTISTA
Applicant returned to address corrections 6/7/2017 DIEGO BAUTISTA
Applicant returned to address corrections 8/2/2017 DIEGO BAUTISTA
Applicant returned to address corrections 9/5/2017 DIEGO BAUTISTA
Plan Check Approved 10/23/2017 DIEGO BAUTISTA
Issued 10/25/2017 LADBS
CofO in Progress 6/15/2021 PIERRE VEGA
CofO in Progress 6/15/2021 PIERRE VEGA
Permit Finaled 6/15/2021 VINCENT COTTON
Permit Finaled 6/15/2021 VINCENT COTTON
CofO Issued 6/15/2021 VINCENT COTTON

Permit Application Clearance Information

Specific Plan Cleared 4/7/2017 TAIMOUR TANAVOLI
Hydrant and Access approval Cleared 7/19/2017 ROBERT DUFF
Low Impact Development Cleared 8/7/2017 MICHAEL SCADUTO
Address approval Cleared 8/8/2017 CHEN ZHANG
Eng Process Fee Ord 176,300 Cleared 8/8/2017 CHEN ZHANG
Permit Cleared 8/8/2017 CHEN ZHANG
Roof/Waste drainage to street Cleared 8/8/2017 CHEN ZHANG
Sewer availability Cleared 8/8/2017 CHEN ZHANG
Housing rent stabilization Cleared 8/9/2017 CHARLES GARCIA
Miscellaneous Cleared 8/10/2017 SARAH GOLDMAN
Green Code Cleared 8/30/2017 RICHARD GARCIA
Specific Plan Cleared 9/15/2017 NOAH MCCOY
Tract Map conditions Cleared 9/15/2017 NOAH MCCOY
ZA Case Cleared 9/15/2017 NOAH MCCOY
Coastal Zone Cleared 10/20/2017 NOAH MCCOY
Green Code Cleared 10/23/2017 DIEGO BAUTISTA

Contact Information

Architect Daham, Ramsey Walid; Lic. No.: C34257 109 EUCALYPTUS DRIVE      EL SEGUNDO, CA 90245
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Engineer Obando, Gaspar Eduardo; Lic. No.: C71382 14000 TAHITI WY 303      MARINA DEL REY, CA 90292

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/21/2018 Conditional Approval BOB DUNN
Excavation/Setback/Form/Re-Bar 2/23/2018 Partial Approval RONALD WEBER
Excavation/Setback/Form/Re-Bar 4/5/2018 Corrections Issued BOB DUNN
Excavation/Setback/Form/Re-Bar 4/13/2018 Partial Approval RONALD WEBER
Footing/Foundation/Slab 5/17/2018 Approved RONALD WEBER
Deputy Reinf. Masonry 6/7/2018 Conditional Approval BOB DUNN
Masonry Wall/Backfill 6/7/2018 Corrections Issued BOB DUNN
Deputy Reinf. Masonry 7/13/2018 Conditional Approval BOB DUNN
Deputy Reinf. Masonry 7/16/2018 Conditional Approval BOB DUNN
Masonry Wall/Backfill 7/24/2018 Conditional Approval BOB DUNN
ELECTRICAL-Rough 10/15/2018 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 10/15/2018 Partial Approval CRAIG DAVIS
PLUMBING-Rough 10/15/2018 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/16/2018 Partial Approval CRAIG DAVIS
Drywall Nailing 11/29/2018 Partial Approval CRAIG DAVIS
Green Building Rough 11/29/2018 Not Ready for Inspection CRAIG DAVIS
Deputy Steel/Welding 12/4/2018 Conditional Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/31/2018 Partial Approval RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 2/12/2019 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/18/2019 Partial Approval DAVID HEINE
Masonry Wall/Backfill 7/11/2019 Approved DAVID HEINE
PLUMBING-Rough 7/11/2019 Partial Approval DAVID HEINE
ELECTRICAL-Rough 8/5/2019 Corrections Issued DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Approval DAVID HEINE
Gas Test 8/5/2019 Approved DAVID HEINE
ELECTRICAL-Rough 9/6/2019 Approved DAVID HEINE
PLUMBING-Rough 9/6/2019 Corrections Issued DAVID HEINE
BUILDING-Rough-Frame 9/23/2019 Not Ready for Inspection DAVID HEINE
Green Building Rough 9/23/2019 Not Ready for Inspection DAVID HEINE
HVAC-Rough 9/23/2019 Approved DAVID HEINE
Verify Sprinkler Sign Off 9/23/2019 Not Ready for Inspection DAVID HEINE
Insulation 10/17/2019 Approved DAVID HEINE
Excavation/Setback/Form/Re-Bar 10/23/2019 Approved DAVID HEINE
Deputy Reinf. Concrete 10/25/2019 Partial Approval DAVID HEINE
Drywall Nailing 11/20/2019 Approved DAVID HEINE
Green Building Rough 11/20/2019 Approved DAVID HEINE
Shower Pan 12/13/2019 Approved DAVID HEINE
Interior/Exterior Lathing 1/16/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 2/14/2020 Approved DAVID HEINE
HVAC-Rough 2/14/2020 Approved DAVID HEINE
PLUMBING-Rough 2/14/2020 Approved DAVID HEINE
Interior/Exterior Lathing 5/4/2020 Approved DAVID HEINE
ELECTRICAL-Final 8/14/2020 Approved DAVID HEINE
HVAC-Final 8/14/2020 Approved DAVID HEINE
ELECTRICAL-Final 2/12/2021 Approved JOHNNY MIRANDA
Sewer 2/12/2021 Partial Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 5/3/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 5/3/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 5/3/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 5/3/2021 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 5/3/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 5/20/2021 Approved JOHNNY MIRANDA
Final 5/20/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 5/20/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 5/20/2021 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 5/20/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 5/27/2021 Approved JOHNNY MIRANDA
Final 6/4/2021 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 6/4/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/4/2021 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 6/4/2021 Approved JOHNNY MIRANDA