330 S RENNIE AVE 2 90291
Certificate Information: 330 S RENNIE AVE 2 90291
- Application / Permit
- 16010-30000-04597
- Plan Check / Job No.
- B16WL05213
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD with roof deck attached 2-car garage (Lot 2). Small Lot Subdivision
- Permit Issued
- Issued on 10/25/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2016 | MARJAN SHENASI |
| Corrections Issued | 10/24/2016 | DIEGO BAUTISTA |
| Green Plans Picked Up | 10/24/2016 | APPLICANT |
| Quality Review Completed | 10/27/2016 | STEVEN KIM |
| Building Plans Picked Up | 10/31/2016 | APPLICANT |
| Applicant returned to address corrections | 2/14/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 6/7/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 8/2/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 9/5/2017 | DIEGO BAUTISTA |
| Plan Check Approved | 10/24/2017 | DIEGO BAUTISTA |
| Issued | 10/25/2017 | LADBS |
| CofO in Progress | 6/15/2021 | PIERRE VEGA |
| Permit Finaled | 6/15/2021 | VINCENT COTTON |
| CofO Issued | 6/15/2021 | VINCENT COTTON |
| Permit Finaled | 6/15/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/7/2017 | TAIMOUR TANAVOLI |
| Hydrant and Access approval | Cleared | 7/19/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 8/7/2017 | MICHAEL SCADUTO |
| Address approval | Cleared | 8/8/2017 | CHEN ZHANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2017 | CHEN ZHANG |
| Permit | Cleared | 8/8/2017 | CHEN ZHANG |
| Roof/Waste drainage to street | Cleared | 8/8/2017 | CHEN ZHANG |
| Sewer availability | Cleared | 8/8/2017 | CHEN ZHANG |
| Housing rent stabilization | Cleared | 8/9/2017 | CHARLES GARCIA |
| Miscellaneous | Cleared | 8/10/2017 | SARAH GOLDMAN |
| Green Code | Cleared | 8/30/2017 | RICHARD GARCIA |
| Specific Plan | Cleared | 9/15/2017 | NOAH MCCOY |
| Tract Map conditions | Cleared | 9/15/2017 | NOAH MCCOY |
| ZA Case | Cleared | 9/15/2017 | NOAH MCCOY |
| Coastal Zone | Cleared | 10/20/2017 | NOAH MCCOY |
| Green Code | Cleared | 10/23/2017 | DIEGO BAUTISTA |
Contact Information
| Architect | Daham, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Engineer | Obando, Gaspar Eduardo; Lic. No.: C71382 | 14000 TAHITI WY 303 MARINA DEL REY, CA 90292 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/21/2018 | Corrections Issued | BOB DUNN |
| Excavation/Setback/Form/Re-Bar | 2/23/2018 | Partial Approval | RONALD WEBER |
| Excavation/Setback/Form/Re-Bar | 4/5/2018 | Corrections Issued | BOB DUNN |
| Excavation/Setback/Form/Re-Bar | 4/13/2018 | Partial Approval | RONALD WEBER |
| Footing/Foundation/Slab | 5/17/2018 | Approved | RONALD WEBER |
| Deputy Reinf. Masonry | 6/7/2018 | Conditional Approval | BOB DUNN |
| Masonry Wall/Backfill | 6/7/2018 | Corrections Issued | BOB DUNN |
| Deputy Reinf. Masonry | 7/13/2018 | Conditional Approval | BOB DUNN |
| Deputy Reinf. Masonry | 7/16/2018 | Conditional Approval | BOB DUNN |
| Masonry Wall/Backfill | 7/24/2018 | Partial Approval | BOB DUNN |
| ELECTRICAL-Rough | 10/15/2018 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/15/2018 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 10/15/2018 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2018 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2018 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 11/29/2018 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 11/29/2018 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2018 | Partial Approval | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2019 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2019 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 7/11/2019 | Approved | DAVID HEINE |
| PLUMBING-Rough | 7/11/2019 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 8/2/2019 | Approved | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2019 | Corrections Issued | RONALD WEBER |
| Gas Test | 8/2/2019 | Approved | RONALD WEBER |
| ELECTRICAL-Rough | 9/6/2019 | Approved | DAVID HEINE |
| PLUMBING-Rough | 9/6/2019 | Corrections Issued | DAVID HEINE |
| Deputy Drilled-In Anchors | 10/17/2019 | Not Ready for Inspection | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 10/23/2019 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 10/23/2019 | Approved | DAVID HEINE |
| Wood Frame | 10/23/2019 | Not Ready for Inspection | DAVID HEINE |
| Deputy Reinf. Concrete | 10/25/2019 | Partial Approval | DAVID HEINE |
| Insulation | 10/29/2019 | Approved | DAVID HEINE |
| Drywall Nailing | 12/13/2019 | Approved | DAVID HEINE |
| Green Building Rough | 12/13/2019 | Approved | DAVID HEINE |
| Shower Pan | 12/13/2019 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/16/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 2/14/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 2/14/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 2/14/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 5/4/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 8/14/2020 | Approved | DAVID HEINE |
| HVAC-Final | 8/14/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 5/27/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | JOHNNY MIRANDA |
| Final | 6/4/2021 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Final | 6/4/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 6/4/2021 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 6/4/2021 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 6/4/2021 | Approved | JOHNNY MIRANDA |