2282 N MANDEVILLE CANYON ROAD 90049

Certificate Information: 2282 N MANDEVILLE CANYON ROAD 90049

Application / Permit
16010-30000-04416
Plan Check / Job No.
B16WL05059
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
New ALQ
Permit Issued
Issued on 9/29/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2016 APPLICANT
Assigned to Plan Check Engineer 10/13/2016 MANUEL GARCIA
Corrections Issued 10/18/2016 MANUEL GARCIA
Quality Review Completed 10/18/2016 STEVEN KIM
Green Plans Picked Up 10/18/2016 APPLICANT
Building Plans Picked Up 10/20/2016 APPLICANT
Applicant returned to address corrections 2/2/2017 MANUEL GARCIA
Applicant returned to address corrections 6/22/2017 MANUEL GARCIA
Applicant returned to address corrections 7/19/2017 MANUEL GARCIA
Plan Check Approved 9/28/2017 MANUEL GARCIA
Issued 9/29/2017 LADBS
CofO in Progress 2/25/2021 ANDREW NAVE
CofO Issued 3/24/2021 VINCENT COTTON
Permit Finaled 3/24/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/24/2016 RICHARD SOUTHERLAND
Miscellaneous Cleared 11/7/2016 EDBER MACEDO
Hydrant and Access approval Cleared 4/5/2017 ROBERT DUFF
Low Impact Development Cleared 7/12/2017 MARTIN FRAGOSO
GPI Written Notices Cleared 7/19/2017 MANUEL GARCIA
Grading Pre-Inspection Cleared 7/19/2017 MANUEL GARCIA
Green Code Cleared 7/27/2017 BRYAN MEYER
Miscellaneous Cleared 9/20/2017 MAHELET GEBEYHU
Miscellaneous Cleared 9/20/2017 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 9/20/2017 DENNIS BRAGIN
Sewer availability Cleared 9/20/2017 MAHELET GEBEYHU
Watercourse Cleared 9/20/2017 DENNIS BRAGIN
Excavation more than 5-ft deep Cleared 9/28/2017 CALOSHA APPROVED

Contact Information

Contractor Minardos Construction & Associates; Lic. No.: 728956-B 2800 28TH STREET SUITE 170      SANTA MONICA, CA 90405

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/7/2020 Approved TIM CHRISTENSEN
Drywall Nailing 10/7/2020 Approved TIM CHRISTENSEN
Final 10/7/2020 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 10/7/2020 Approved TIM CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Approved TIM CHRISTENSEN
Smoke Detectors 10/7/2020 Approved TIM CHRISTENSEN
Verify Sprinkler Sign Off 10/7/2020 Approved TIM CHRISTENSEN
Final 2/25/2021 OK to Issue CofO ANDREW NAVE
Special/Order Compliance 3/18/2021 Approved ANDREW NAVE