6140 N RANCHITO AVE 91401
Certificate Information: 6140 N RANCHITO AVE 91401
- Application / Permit
- 16010-30000-04401
- Plan Check / Job No.
- B16WL05050
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Second dwelling unit per Ordinance 184510
- Permit Issued
- Issued on 3/10/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2016 | MANUEL GARCIA |
| Corrections Issued | 10/12/2016 | MANUEL GARCIA |
| Quality Review Completed | 10/13/2016 | STEVEN KIM |
| Building Plans Picked Up | 10/20/2016 | APPLICANT |
| Green Plans Picked Up | 10/20/2016 | APPLICANT |
| Applicant returned to address corrections | 1/4/2017 | MANUEL GARCIA |
| Plan Check Approved | 2/10/2017 | MANUEL GARCIA |
| Issued | 3/10/2017 | LADBS |
| CofO in Progress | 11/25/2025 | RYAN SALAZAR |
| Permit Finaled | 12/17/2025 | RUBEN SALAS |
| CofO Issued | 12/17/2025 | RUBEN SALAS |
| Permit Finaled | 12/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2016 | SEVAK ISAKHAYAN |
| Hydrant and Access approval | Cleared | 12/2/2016 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/8/2016 | AYMAN JABBOURI |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2016 | BRIAN KELLY |
| Roof/Waste drainage to street | Cleared | 12/9/2016 | BRIAN KELLY |
| Sewer availability | Cleared | 12/9/2016 | BRIAN KELLY |
| Green Code | Cleared | 12/12/2016 | BRYAN MEYER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2017 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Grading Pre-Inspection | 9/19/2017 | Not Ready for Inspection | GREG ALLTON |
| PLUMBING-Rough | 9/19/2017 | Not Ready for Inspection | GREG ALLTON |
| Footing/Foundation/Slab | 9/25/2017 | Conditional Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2017 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2017 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2017 | Conditional Approval | GREG ALLTON |
| PLUMBING-Rough | 12/28/2017 | Not Ready for Inspection | GREG ALLTON |
| Rough-Elec/Plmb/HVAC | 12/28/2017 | No Access for Inspection | GREG ALLTON |
| BUILDING-Rough-Frame | 1/26/2018 | Approved | GREG ALLTON |
| Green Building Rough | 1/26/2018 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 1/26/2018 | Partial Approval | GREG ALLTON |
| Rough-Elec/Plmb/HVAC | 1/26/2018 | Partial Approval | GREG ALLTON |
| Verify Sprinkler Sign Off | 1/26/2018 | Approved | GREG ALLTON |
| Insulation | 2/2/2018 | Approved | GREG ALLTON |
| Drywall Nailing | 2/22/2018 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 3/28/2018 | Approved | GREG ALLTON |
| Shower Pan | 3/28/2018 | Approved | GREG ALLTON |
| Final | 6/21/2018 | Not Ready for Inspection | GREG ALLTON |
| Footing/Foundation/Slab | 6/21/2018 | Approved | GREG ALLTON |
| Green Building Final | 6/21/2018 | Approved | GREG ALLTON |
| SGSOV-Seismic Gas S/O Valve | 6/21/2018 | SGSOV Approved | GREG ALLTON |
| Service/Power Release | 6/21/2018 | Not Ready for Inspection | GREG ALLTON |
| Smoke Detectors | 6/21/2018 | Approved | GREG ALLTON |
| Final | 7/6/2018 | Not Ready for Inspection | GREG ALLTON |
| Service/Power Release | 7/6/2018 | Not Ready for Inspection | GREG ALLTON |
| Final | 7/11/2018 | Not Ready for Inspection | GREG ALLTON |
| Service/Power Release | 7/11/2018 | Not Ready for Inspection | GREG ALLTON |
| Service/Power Release | 8/29/2018 | Not Ready for Inspection | ARAM AVEDISIAN |
| Special/Order Compliance | 8/29/2018 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Rec and Parks Fee Memo | 8/29/2018 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 2/24/2024 | Off-Hour Fees Due | |
| Service/Power Release | 2/24/2024 | Off-Hour Fees Due | |
| Final | 2/26/2024 | Off-Hour Fees Due | |
| Service/Power Release | 2/26/2024 | Off-Hour Fees Due | |
| Final | 11/14/2025 | Corrections Issued | RYAN SALAZAR |
| Service/Power Release | 11/14/2025 | Not Required | RYAN SALAZAR |
| Final | 11/24/2025 | OK to Issue CofO | RYAN SALAZAR |