9390 W READCREST DR 90210
Certificate Information: 9390 W READCREST DR 90210
- Application / Permit
- 16010-30000-03854
- Plan Check / Job No.
- B16WL04409
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story single family dwelling with basement and attached garage
- Permit Issued
- Issued on 1/16/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/16/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2016 | DIEGO BAUTISTA |
| Corrections Issued | 9/10/2016 | DIEGO BAUTISTA |
| Quality Review Completed | 9/15/2016 | MARJAN SHENASI |
| Building Plans Picked Up | 10/26/2016 | APPLICANT |
| Applicant returned to address corrections | 11/28/2016 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 12/15/2016 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 1/20/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 8/23/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 8/31/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 9/12/2017 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 9/19/2017 | DIEGO BAUTISTA |
| Green Plans Picked Up | 10/2/2017 | APPLICANT |
| Plan Check Approved | 12/7/2017 | DIEGO BAUTISTA |
| Issued | 1/16/2018 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/19/2017 | ANDREW KO |
| BHO/Hillside ordinance | Cleared | 10/19/2017 | ANDREW SLUSSER |
| BHO/Hillside ordinance | Cleared | 10/19/2017 | ANDREW SLUSSER |
| BHO/Hillside ordinance | Cleared | 10/19/2017 | ANDREW SLUSSER |
| Green Code | Cleared | 10/25/2017 | DIEGO BAUTISTA |
| Low Impact Development | Cleared | 11/3/2017 | RYAN HUDSON |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2017 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 11/15/2017 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/15/2017 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/15/2017 | HISASHI KOBAYAKAWA |
| Work Adjacent to Public Way | Cleared | 11/15/2017 | EDUARDO PEDROZA |
| Excavation more than 5-ft deep | Cleared | 12/7/2017 | CALOSHA APPROVED |
Contact Information
| Contractor | B D R Inc; Lic. No.: 735996-B | P O BOX 410 AGOURA HILLS, CA 91376 |
| Engineer | Doss, Richard E; Lic. No.: C48987 | 30141 AGOURA RD 200 AGOURA HILLS, CA 91301 |
| Engineer | Garcia, Lionel Jesus; Lic. No.: S4653 | 23890 HAWTHORNE BLVD TORRANCE, CA 90505 |
| Engineer | Hollingsworth, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2019 | Corrections Issued | RICHARD STEINBACH |
| Piling/Pier/Caisson | 8/16/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| Special/Order Compliance | 1/20/2022 | No Access for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 1/21/2022 | Partial Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/27/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/6/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/17/2023 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/9/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/27/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/29/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/2/2024 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 3/4/2024 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/22/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/27/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/19/2024 | Partial Approval | RAUL BARAJAS |
| Deck | 9/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/23/2024 | Corrections Issued | CRAIG VAUGHAN |
| Structural Steel Frame | 9/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/26/2025 | Conditional Approval | ROY SPAULDING |