418 W WREN DR 90065
Certificate Information: 418 W WREN DR 90065
- Application / Permit
- 16010-30000-03349
- Plan Check / Job No.
- B16WL03935
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD with attached garage.
- Permit Issued
- Issued on 7/8/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2016 | DIEGO BAUTISTA |
| Corrections Issued | 8/26/2016 | DIEGO BAUTISTA |
| Quality Review Completed | 8/31/2016 | STEVEN KIM |
| Building Plans Picked Up | 9/1/2016 | APPLICANT |
| Green Plans Picked Up | 11/9/2016 | APPLICANT |
| Applicant returned to address corrections | 5/31/2018 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 7/30/2018 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 12/31/2018 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 1/8/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 1/30/2019 | JOSE RODRIGUEZ |
| No Progress | 2/6/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 2/6/2019 | JOSE RODRIGUEZ |
| No Progress | 2/6/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 6/25/2019 | JOSE RODRIGUEZ |
| Issued | 7/8/2019 | LADBS |
| CofO in Progress | 1/26/2022 | OSVALDO PARAMO |
| CofO in Progress | 1/26/2022 | OSVALDO PARAMO |
| CofO Issued | 2/3/2022 | RONALD MYRICK |
| Permit Finaled | 2/3/2022 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/28/2016 | ALFREDO JARA |
| BHO/Hillside ordinance | Cleared | 10/28/2016 | ALFREDO JARA |
| BHO/Hillside ordinance | Cleared | 10/28/2016 | ALFREDO JARA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2016 | ALFREDO JARA |
| Permit | Cleared | 10/28/2016 | ALFREDO JARA |
| Sewer availability | Cleared | 10/28/2016 | ALFREDO JARA |
| Low Impact Development | Cleared | 11/3/2016 | RYAN HUDSON |
| BHO/Hillside ordinance | Cleared | 11/8/2016 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/8/2016 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/29/2018 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/5/2018 | ROBERT DUFF |
| Green Code | Cleared | 7/30/2018 | BRYAN MEYER |
| Miscellaneous | Cleared | 8/28/2018 | LINDA MARGARET |
| Green Code | Cleared | 1/2/2019 | JOSE RODRIGUEZ |
| Green Code | Cleared | 2/21/2019 | SEAN DANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Salehipour, Sassan Abolghasem; Lic. No.: C44172 | 1290 NORTH LAKE AVENUE STE 204 PASADENA, CA 91104 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2019 | Approved | OSVALDO PARAMO |
| Sewer | 9/25/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/22/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Piling/Pier/Caisson | 10/25/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Piling/Pier/Caisson | 11/5/2019 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/22/2019 | Partial Inspection | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 11/26/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/26/2019 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 1/16/2020 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/16/2020 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/21/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 2/11/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/13/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/26/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/2/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 3/23/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/22/2020 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 5/18/2020 | No Access for Inspection | OSVALDO PARAMO |
| Wood Frame | 5/21/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/2/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 6/3/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/3/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 6/3/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/27/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Insulation | 7/27/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 7/27/2020 | Corrections Issued | OSVALDO PARAMO |
| Sewer | 7/27/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 8/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/3/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 8/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 8/5/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 8/5/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 8/5/2020 | Corrections Issued | OSVALDO PARAMO |
| Sewer | 8/5/2020 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 8/10/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/10/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/17/2020 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/19/2020 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 8/19/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/19/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/31/2020 | Partial Inspection | OSVALDO PARAMO |
| Green Building Rough | 8/31/2020 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/31/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/4/2020 | Conditional Approval | OSVALDO PARAMO |
| Insulation | 9/10/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/16/2020 | Conditional Approval | OSVALDO PARAMO |
| Drywall Nailing | 9/16/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/16/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 9/16/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/23/2020 | Conditional Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/23/2020 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/29/2020 | Approved | OSVALDO PARAMO |
| Shower Pan | 9/29/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 9/29/2020 | Approved | OSVALDO PARAMO |
| Shower Pan | 10/2/2020 | Corrections Issued | OSVALDO PARAMO |
| Shower Pan | 10/8/2020 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 10/16/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Shower Pan | 10/27/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/27/2020 | Conditional Approval | OSVALDO PARAMO |
| Special/Order Compliance | 4/16/2021 | Approved | HORACE FULTZ |
| Special/Order Compliance | 4/19/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 4/29/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/8/2021 | Off-Hour Fees Due | |
| Wood Frame | 5/9/2021 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 5/12/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/25/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/8/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 9/1/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 9/2/2021 | Approved | OSVALDO PARAMO |
| HVAC-Final | 9/3/2021 | No Access for Inspection | OSVALDO PARAMO |
| HVAC-Final | 9/8/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/10/2021 | Approved | OSVALDO PARAMO |
| Final | 9/10/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/10/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 9/10/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Reinforced Concrete Frame | 9/10/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/23/2021 | Approved | OSVALDO PARAMO |
| Final | 12/23/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 12/23/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/23/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 12/23/2021 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 12/23/2021 | Approved | OSVALDO PARAMO |
| Final | 1/14/2022 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 1/14/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Approved | OSVALDO PARAMO |
| Final | 1/19/2022 | OK to Issue CofO | OSVALDO PARAMO |