3716 N MULTIVIEW DR 90068
Certificate Information: 3716 N MULTIVIEW DR 90068
- Application / Permit
- 16010-30000-02996
- Plan Check / Job No.
- B16WL03501
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 4-story with 1-level basement SFD w/ attached 3-car garage
- Permit Issued
- Issued on 12/28/2016
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2016 | DIEGO BAUTISTA |
| Green Plans Picked Up | 8/14/2016 | APPLICANT |
| Corrections Issued | 8/17/2016 | DIEGO BAUTISTA |
| Quality Review Completed | 8/18/2016 | STEVEN KIM |
| Building Plans Picked Up | 8/19/2016 | APPLICANT |
| Applicant returned to address corrections | 8/31/2016 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 9/14/2016 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 9/21/2016 | DIEGO BAUTISTA |
| Applicant returned to address corrections | 11/2/2016 | DIEGO BAUTISTA |
| Plan Check Approved | 12/28/2016 | DIEGO BAUTISTA |
| Issued | 12/28/2016 | LADBS |
| CofO in Progress | 2/25/2026 | BRIAN SULLIVAN |
| Permit Finaled | 2/26/2026 | DEROLD HAUFF |
| CofO Issued | 2/26/2026 | DEROLD HAUFF |
| Permit Finaled | 2/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 8/29/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 8/29/2016 | ERIK MUNOZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2016 | ERIK MUNOZ |
| Permit | Cleared | 8/29/2016 | ERIK MUNOZ |
| Sewer availability | Cleared | 8/29/2016 | ERIK MUNOZ |
| Hydrant and Access approval | Cleared | 8/30/2016 | JOHN DALLAS |
| Miscellaneous | Cleared | 8/30/2016 | RICK TORRES |
| Low Impact Development | Cleared | 9/13/2016 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 10/26/2016 | ERIK MUNOZ |
| Green Code | Cleared | 11/2/2016 | RICHARD GARCIA |
| Miscellaneous | Cleared | 11/28/2016 | BRIDGETTE WOOTEN |
| Miscellaneous | Cleared | 11/29/2016 | BRIDGETTE WOOTEN |
| Specific Plan | Cleared | 11/29/2016 | BRIDGETTE WOOTEN |
| Disturb/Remove Protected Trees | Cleared | 12/21/2016 | LUIS TORRES |
| BHO/Hillside ordinance | Cleared | 12/23/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 12/28/2016 | ERIK MUNOZ |
| BHO/Hillside ordinance | Cleared | 12/28/2016 | ERIK MUNOZ |
Contact Information
| Architect | Heeb, Derek M; Lic. No.: C32338 | 3974 SAN RAFAEL AVENUE LOS ANGELES, CA 90065 |
| Contractor | Owner-Builder | , |
| Engineer | Robinson, Rory Anthony; Lic. No.: GE2491 | 963 EAST SANTA CLARA ST VENTURA, CA 93001 |
| Geologist | Robinson, Rory Anthony; Lic. No.: EG1902 | 963 EAST SANTA CLARA STREET VENTURA, CA 93001 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2018 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2018 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/13/2018 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 6/13/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 6/13/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/16/2018 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2018 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2018 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2018 | Partial Approval | BRIAN SULLIVAN |
| Pre-Inspection | 10/25/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/29/2018 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2018 | Partial Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 12/28/2018 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/31/2019 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2019 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2019 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/2/2019 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/2/2019 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2019 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/2/2019 | Partial Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 7/2/2019 | Partial Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/2/2019 | Partial Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/14/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 8/14/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/14/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/12/2019 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 9/12/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 9/12/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/12/2019 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/18/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/20/2019 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 5/15/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 7/24/2020 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 7/24/2020 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 12/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 7/18/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 12/7/2022 | Corrections Issued | BRIAN SULLIVAN |
| Sewer | 2/15/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/7/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 8/7/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 11/4/2025 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 1/26/2026 | Approved | BRIAN SULLIVAN |
| Final | 1/26/2026 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/26/2026 | Approved | BRIAN SULLIVAN |
| Green Building Final | 1/26/2026 | Approved | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 1/26/2026 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 1/26/2026 | Approved | BRIAN SULLIVAN |
| Structural Steel Frame | 1/26/2026 | Approved | BRIAN SULLIVAN |
| Final | 2/24/2026 | OK to Issue CofO | BRIAN SULLIVAN |