1125 N GRACE LANE 90049

Certificate Information: 1125 N GRACE LANE 90049

Application / Permit
16010-30000-02853
Plan Check / Job No.
B16WL03426
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
(n) 56.5' x 48' 2-story Accessory living quarter
Permit Issued
Issued on 12/1/2017
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2016 APPLICANT
Assigned to Plan Check Engineer 7/28/2016 CHON CHIO KUO
Corrections Issued 8/1/2016 CHON CHIO KUO
Quality Review Completed 8/11/2016 FELIX FIGUEROA
Green Plans Picked Up 8/11/2016 APPLICANT
Building Plans Picked Up 8/12/2016 APPLICANT
Applicant returned to address corrections 3/9/2017 CHON CHIO KUO
Applicant returned to address corrections 10/26/2017 CHON CHIO KUO
Plan Check Approved 11/15/2017 CHON CHIO KUO
Issued 12/1/2017 LADBS
CofO in Progress 4/8/2022 CARLOS MATAMOROS
Permit Finaled 4/18/2022 DANIEL ORRANTE
CofO Issued 4/18/2022 DANIEL ORRANTE
Permit Finaled 4/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Tract Map conditions Cleared 10/11/2016 BRIAN CARR
ZA Case Cleared 10/11/2016 BRIAN CARR
BHO/Hillside ordinance Cleared 12/20/2016 ARMENIA AGUILAR
BHO/Hillside ordinance Cleared 12/20/2016 ARMENIA AGUILAR
BHO/Hillside ordinance Cleared 12/20/2016 ARMENIA AGUILAR
BHO/Hillside ordinance Cleared 12/20/2016 ARMENIA AGUILAR
Low Impact Development Cleared 2/10/2017 MARTIN FRAGOSO
ZA Case Cleared 2/17/2017 TOM HENRY
Private street Cleared 2/28/2017 DWAYNE WYATT
Hydrant and Access approval Cleared 3/8/2017 ROBERT DUFF
Miscellaneous Cleared 3/17/2017 OSCAR GUTIERREZ
BHO/Hillside ordinance Cleared 3/28/2017 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 3/28/2017 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 10/17/2017 DENNIS BRAGIN
Sewer availability Cleared 10/17/2017 DENNIS BRAGIN
Green Code Cleared 10/24/2017 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2018 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 8/1/2018 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 3/12/2019 Corrections Issued ANTHONY MCDOWALL
Piling/Pier/Caisson 3/29/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/2/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/3/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 5/21/2019 Partial Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 6/13/2019 Partial Approval ANTHONY MCDOWALL
Piling/Pier/Caisson 6/18/2019 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/1/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 7/24/2019 Partial Inspection ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 8/12/2019 Conditional Approval ANTHONY MCDOWALL
Underground Mechanical 10/8/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 10/18/2019 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 10/21/2019 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/8/2019 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 11/18/2019 Corrections Issued ANTHONY MCDOWALL
Piling/Pier/Caisson 11/18/2019 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Reinf. Concrete 11/21/2019 Approved ANTHONY MCDOWALL
Piling/Pier/Caisson 11/21/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 12/18/2019 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 12/19/2019 Partial Approval ANTHONY MCDOWALL
Wood Frame 1/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 1/27/2020 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 1/30/2020 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 2/10/2020 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 2/11/2020 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 2/25/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Approved CARLOS MATAMOROS
Reinforced Concrete Frame 3/26/2020 Partial Approval CARLOS MATAMOROS
Wood Frame 5/21/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Not Ready for Inspection CARLOS MATAMOROS
Sewer 7/13/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 8/17/2020 Approved CARLOS MATAMOROS
Shower Pan 8/25/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 9/2/2020 Partial Approval CARLOS MATAMOROS
HVAC-Rough 10/14/2020 Partial Approval CARLOS MATAMOROS
Gas Test 11/4/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 12/4/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 12/7/2020 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 12/14/2020 Approved CARLOS MATAMOROS
Special/Order Compliance 12/14/2020 Approved CARLOS MATAMOROS
HVAC-Rough 1/5/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/12/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Approved CARLOS MATAMOROS
Green Building Rough 1/12/2021 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/12/2021 Approved CARLOS MATAMOROS
Insulation 1/15/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 1/15/2021 Approved CARLOS MATAMOROS
Drywall Nailing 1/26/2021 Approved CARLOS MATAMOROS
Final 2/4/2022 Corrections Issued CARLOS MATAMOROS
HVAC-Final 2/4/2022 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 2/4/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 2/7/2022 Corrections Issued CARLOS MATAMOROS
HVAC-Final 2/7/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 2/9/2022 Approved CARLOS MATAMOROS
HVAC-Final 2/11/2022 Approved CARLOS MATAMOROS
Final 4/8/2022 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 4/8/2022 Approved CARLOS MATAMOROS
Green Building Final 4/8/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 4/8/2022 Approved CARLOS MATAMOROS
Smoke Detectors 4/8/2022 Approved CARLOS MATAMOROS