1851 N STANLEY AVE 90046

Certificate Information: 1851 N STANLEY AVE 90046

Application / Permit
16010-30000-02693
Plan Check / Job No.
B16WL03230
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) s.f.d. /gar, 2-story with basement
Permit Issued
Issued on 12/15/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2016 APPLICANT
Green Plans Picked Up 7/11/2016 APPLICANT
Assigned to Plan Check Engineer 7/21/2016 CHON CHIO KUO
Corrections Issued 7/26/2016 CHON CHIO KUO
Building Plans Picked Up 7/26/2016 APPLICANT
Quality Review Completed 8/2/2016 FELIX FIGUEROA
Applicant returned to address corrections 8/30/2016 CHON CHIO KUO
Applicant returned to address corrections 9/12/2016 CHON CHIO KUO
Applicant returned to address corrections 9/20/2016 CHON CHIO KUO
Applicant returned to address corrections 11/4/2016 CHON CHIO KUO
Applicant returned to address corrections 12/16/2016 CHON CHIO KUO
Applicant returned to address corrections 1/4/2017 CHON CHIO KUO
Applicant returned to address corrections 1/30/2017 CHON CHIO KUO
Applicant returned to address corrections 2/13/2017 CHON CHIO KUO
Plan Check Approved 4/7/2017 CHON CHIO KUO
Issued 12/15/2017 LADBS
CofO in Progress 6/12/2023 BRIAN SULLIVAN
CofO Issued 6/25/2023 DEROLD HAUFF
Permit Finaled 6/25/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 8/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 8/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 8/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 8/4/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 8/4/2016 RAVIL MANAPOV
Highway dedication Cleared 8/4/2016 RAVIL MANAPOV
Permit Cleared 8/4/2016 RAVIL MANAPOV
Sewer availability Cleared 8/4/2016 RAVIL MANAPOV
GPI Written Notices Cleared 8/30/2016 CHON CHIO KUO
Grading Pre-Inspection Cleared 8/30/2016 CHON CHIO KUO
CPC Cleared 12/6/2016 JOHN DACEY
Hydrant and Access approval Cleared 12/6/2016 ROBERT DUFF
Low Impact Development Cleared 1/9/2017 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 1/13/2017 JOSEPH RHYU
Excavation more than 5-ft deep Cleared 1/30/2017 CALOSHA APPROVED
Green Code Cleared 4/5/2017 CHON CHIO KUO
Work Adjacent to Public Way Cleared 4/6/2017 RAVIL MANAPOV
Hold Cleared 1/12/2018 TERESA MUI

Contact Information

Contractor Owner-Builder       ,
Engineer Lau, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer Lieurance, Martin Ellis; Lic. No.: C54323 31129 VIA COLINAS 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/12/2018 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 7/18/2018 No Access for Inspection RAUL BARAJAS
Piling/Pier/Caisson 5/17/2019 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/10/2019 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 8/12/2019 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 9/9/2019 Partial Approval BRIAN SULLIVAN
Piling/Pier/Caisson 9/17/2019 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 10/4/2019 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 11/14/2019 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 11/14/2019 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 11/14/2019 Conditional Approval RAUL BARAJAS
Deputy Shotcrete 11/25/2019 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/26/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/19/2019 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 12/20/2019 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/23/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/24/2020 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/28/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/7/2020 Conditional Approval RAUL BARAJAS
Deputy Shotcrete 2/7/2020 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/7/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/11/2020 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/13/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/28/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/6/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/10/2020 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 3/11/2020 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/11/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 4/3/2020 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/14/2020 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 4/16/2020 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/16/2020 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 4/16/2020 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 4/22/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 4/27/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 4/29/2020 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/30/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/30/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/15/2020 Partial Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 6/23/2020 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/23/2020 Partial Approval BRIAN SULLIVAN
Deputy Shotcrete 7/27/2020 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 8/19/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/24/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/24/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 10/5/2020 Partial Inspection BRIAN SULLIVAN
Structural Steel Frame 10/5/2020 Partial Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 10/5/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/15/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/15/2020 Partial Approval BRIAN SULLIVAN
Grounding or Bonding 10/15/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval BRIAN SULLIVAN
Deputy Wood Construction 10/21/2020 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 1/25/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 2/5/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/2/2021 Not Ready for Inspection BRIAN SULLIVAN
Deputy Wood Construction 3/2/2021 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 3/2/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/2/2021 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 3/2/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 4/5/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 4/5/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/12/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 5/24/2021 Approved BRIAN SULLIVAN
HVAC-Rough 5/24/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 6/7/2021 Approved BRIAN SULLIVAN
Green Building Rough 6/7/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/7/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/29/2021 Partial Approval BRIAN SULLIVAN
Drywall Nailing 7/1/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 7/12/2021 Not Ready for Inspection RAUL BARAJAS
Light Gage Steel Frame 7/12/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/15/2021 Partial Approval RAUL BARAJAS
Insulation 7/15/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 7/15/2021 Partial Approval RAUL BARAJAS
HVAC-Rough 7/26/2021 Approved RICHARD STEINBACH
Structural Steel Frame 7/26/2021 Conditional Approval RICHARD STEINBACH
Interior/Exterior Lathing 7/28/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/30/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/6/2021 Approved BRIAN SULLIVAN
Wood Frame 9/1/2021 Approved BRIAN SULLIVAN
Service/Power Release 12/9/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 2/17/2023 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 3/20/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 3/20/2023 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 3/20/2023 Approved BRIAN SULLIVAN
PLUMBING-Final 3/23/2023 Approved BRIAN SULLIVAN
HVAC-Final 3/31/2023 Approved BRIAN SULLIVAN
Final 5/5/2023 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 5/5/2023 Approved STUART CHAPMAN
Green Building Final 5/5/2023 Approved STUART CHAPMAN
Reinforced Concrete Frame 5/5/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 5/5/2023 Approved STUART CHAPMAN
Structural Steel Frame 5/5/2023 Approved STUART CHAPMAN
Final 5/15/2023 Corrections Issued BRIAN SULLIVAN
Final 6/9/2023 OK to Issue CofO BRIAN SULLIVAN