Pre-Inspection
|
6/12/2018
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Pre-Inspection
|
7/18/2018
|
No Access for Inspection
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
5/17/2019
|
Partial Inspection
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2019
|
Partial Inspection
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
8/12/2019
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
9/9/2019
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Piling/Pier/Caisson
|
9/17/2019
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
10/4/2019
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Deputy Reinf. Concrete
|
11/14/2019
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Footing/Foundation/Slab
|
11/14/2019
|
Partial Approval
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
11/14/2019
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
11/25/2019
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
11/26/2019
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
12/19/2019
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
12/20/2019
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/10/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
1/23/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/24/2020
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
1/28/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/7/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
2/7/2020
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
2/7/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
2/11/2020
|
Approved
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
2/13/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
2/28/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
3/6/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/10/2020
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Deputy Reinf. Concrete
|
3/11/2020
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
3/11/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
4/3/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Deputy Reinf. Concrete
|
4/16/2020
|
Approved
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/16/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
4/16/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Underground Mechanical
|
4/22/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
4/27/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
4/29/2020
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/30/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Footing/Foundation/Slab
|
4/30/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/15/2020
|
Partial Inspection
|
BRIAN SULLIVAN
|
|
Deputy Reinf. Concrete
|
6/23/2020
|
Approved
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Deputy Shotcrete
|
7/27/2020
|
No Access for Inspection
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
8/19/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/24/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Footing/Foundation/Slab
|
8/24/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/26/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Green Building Rough
|
10/5/2020
|
Partial Inspection
|
BRIAN SULLIVAN
|
|
Structural Steel Frame
|
10/5/2020
|
Partial Inspection
|
BRIAN SULLIVAN
|
|
Verify Sprinkler Sign Off
|
10/5/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/15/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Footing/Foundation/Slab
|
10/15/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Grounding or Bonding
|
10/15/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/20/2020
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Deputy Wood Construction
|
10/21/2020
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/21/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2020
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
1/25/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
2/5/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
BUILDING-Rough-Frame
|
3/2/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Deputy Wood Construction
|
3/2/2021
|
Conditional Approval
|
BRIAN SULLIVAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/2/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Green Building Rough
|
3/2/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
3/2/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Verify Sprinkler Sign Off
|
3/2/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
HVAC-Rough
|
4/5/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Shower Pan
|
4/5/2021
|
Approved
|
BRIAN SULLIVAN
|
|
PLUMBING-Rough
|
4/12/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/21/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
ELECTRICAL-Rough
|
5/24/2021
|
Approved
|
BRIAN SULLIVAN
|
|
HVAC-Rough
|
5/24/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
BUILDING-Rough-Frame
|
6/7/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Green Building Rough
|
6/7/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Verify Sprinkler Sign Off
|
6/7/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Interior/Exterior Lathing
|
6/29/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Drywall Nailing
|
7/1/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Interior/Exterior Lathing
|
7/12/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Light Gage Steel Frame
|
7/12/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Excavation/Setback/Form/Re-Bar
|
7/15/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
Insulation
|
7/15/2021
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
7/15/2021
|
Partial Approval
|
RAUL BARAJAS
|
|
HVAC-Rough
|
7/26/2021
|
Approved
|
RICHARD STEINBACH
|
|
Structural Steel Frame
|
7/26/2021
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Interior/Exterior Lathing
|
7/28/2021
|
Partial Approval
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/30/2021
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Wood Frame
|
9/1/2021
|
Approved
|
BRIAN SULLIVAN
|
|
Service/Power Release
|
12/9/2022
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Final
|
2/17/2023
|
Corrections Issued
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
3/20/2023
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
PLUMBING-Final
|
3/20/2023
|
Not Ready for Inspection
|
BRIAN SULLIVAN
|
|
Service/Power Release
|
3/20/2023
|
Approved
|
BRIAN SULLIVAN
|
|
PLUMBING-Final
|
3/23/2023
|
Approved
|
BRIAN SULLIVAN
|
|
HVAC-Final
|
3/31/2023
|
Approved
|
BRIAN SULLIVAN
|
|
Final
|
5/5/2023
|
Conditional Approval
|
STUART CHAPMAN
|
|
Footing/Foundation/Slab
|
5/5/2023
|
Approved
|
STUART CHAPMAN
|
|
Green Building Final
|
5/5/2023
|
Approved
|
STUART CHAPMAN
|
|
Reinforced Concrete Frame
|
5/5/2023
|
Approved
|
STUART CHAPMAN
|
|
SGSOV-Seismic Gas S/O Valve
|
5/5/2023
|
SGSOV Approved
|
STUART CHAPMAN
|
|
Smoke Detectors
|
5/5/2023
|
Approved
|
STUART CHAPMAN
|
|
Structural Steel Frame
|
5/5/2023
|
Approved
|
STUART CHAPMAN
|
|
Final
|
5/15/2023
|
Corrections Issued
|
BRIAN SULLIVAN
|
|
Final
|
6/9/2023
|
OK to Issue CofO
|
BRIAN SULLIVAN
|