1432 N TANAGER WAY 90069

Certificate Information: 1432 N TANAGER WAY 90069

Application / Permit
16010-30000-01756
Plan Check / Job No.
B16WL02252
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New SFD with attached garage.
Permit Issued
Issued on 8/4/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2016 APPLICANT
Assigned to Plan Check Engineer 5/26/2016 MANUEL GARCIA
Corrections Issued 6/2/2016 MANUEL GARCIA
Quality Review Completed 6/9/2016 GUANG MIN TUNG
Building Plans Picked Up 6/9/2016 APPLICANT
Green Plans Picked Up 6/10/2016 APPLICANT
Applicant returned to address corrections 6/27/2016 MANUEL GARCIA
Applicant returned to address corrections 7/7/2016 MANUEL GARCIA
Applicant returned to address corrections 7/12/2016 MANUEL GARCIA
Applicant returned to address corrections 8/22/2016 MANUEL GARCIA
Applicant returned to address corrections 9/29/2016 MANUEL GARCIA
Plan Check Approved 3/15/2017 MANUEL GARCIA
Issued 8/4/2017 LADBS
CofO in Progress 5/24/2023 RAUL BARAJAS
Permit Finaled 6/1/2023 DEROLD HAUFF
CofO Issued 6/1/2023 DEROLD HAUFF
Permit Finaled 6/1/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/10/2016 ROBERT SAMONTE
BHO/Hillside ordinance Cleared 6/10/2016 ROBERT SAMONTE
BHO/Hillside ordinance Cleared 6/10/2016 ROBERT SAMONTE
BHO/Hillside ordinance Cleared 6/10/2016 ROBERT SAMONTE
Eng Process Fee Ord 176,300 Cleared 6/10/2016 ROBERT SAMONTE
Permit Cleared 6/10/2016 ROBERT SAMONTE
Sewer availability Cleared 6/10/2016 ROBERT SAMONTE
Hydrant and Access approval Cleared 6/21/2016 ROBERT DUFF
Low Impact Development Cleared 11/3/2016 SAM NAVID
Roof/Waste drainage to street Cleared 11/9/2016 LEE GUILBEAUX
Excavation more than 5-ft deep Cleared 12/13/2016 CALOSHA APPROVED
GPI Written Notices Cleared 12/13/2016 MANUEL GARCIA
Grading Pre-Inspection Cleared 12/13/2016 MANUEL GARCIA
Green Code Cleared 12/15/2016 RICHARD GARCIA

Contact Information

Contractor Oh'S Design & Development; Lic. No.: 989612-B 500 SOUTH SHATTO PLACE #411      LOS ANGELES, CA 90020
Engineer Barajas, Jorge Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Cox, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Peck, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/18/2017 Partial Approval DANIEL GONZALEZ
Deputy Drilled-In Anchors 12/13/2017 Partial Approval DANIEL GONZALEZ
Piling/Pier/Caisson 12/20/2017 Partial Approval DANIEL GONZALEZ
Piling/Pier/Caisson 2/27/2018 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 3/1/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 9/12/2018 Partial Inspection DANIEL GONZALEZ
Piling/Pier/Caisson 9/12/2018 Partial Inspection DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 12/18/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 2/26/2020 Partial Approval RICHARD STEINBACH
Special/Order Compliance 2/26/2020 Corrections Issued RICHARD STEINBACH
Deputy Shotcrete 3/3/2020 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/12/2020 Not Ready for Inspection ROBERT CORNELL
Excavation/Setback/Form/Re-Bar 3/17/2020 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 3/23/2020 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 3/27/2020 Partial Approval ROBERT CORNELL
Footing/Foundation/Slab 4/20/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/22/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/29/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 6/10/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/15/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/18/2020 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/7/2020 Partial Approval RAUL BARAJAS
Deputy Shotcrete 7/8/2020 Partial Approval CHRISTOPHER DELLEFIELD
Pre-Inspection 10/7/2020 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 11/9/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/29/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 1/29/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 2/5/2021 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 2/17/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/14/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/7/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 5/27/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection RAUL BARAJAS
Wood Frame 5/27/2021 Approved RAUL BARAJAS
Pre-Inspection 10/12/2021 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 10/26/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 10/26/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 10/26/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 11/17/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 11/17/2021 Approved RAUL BARAJAS
HVAC-Rough 12/9/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/15/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 12/16/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/22/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 12/22/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 12/22/2021 Not Ready for Inspection RAUL BARAJAS
Wood Frame 12/22/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/14/2022 Approved RAUL BARAJAS
Insulation 1/21/2022 Not Ready for Inspection RAUL BARAJAS
Insulation 1/25/2022 Approved RAUL BARAJAS
Insulation 1/28/2022 Approved RAUL BARAJAS
Drywall Nailing 2/9/2022 Partial Inspection AMY COLIN
Green Building Rough 2/9/2022 Not Ready for Inspection AMY COLIN
Green Building Final 4/8/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/8/2022 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/26/2022 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/26/2022 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/10/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/10/2022 Partial Approval RAUL BARAJAS
Masonry Wall/Backfill 5/18/2022 Approved RAUL BARAJAS
PLUMBING-Rough 5/31/2022 Approved RAUL BARAJAS
Service/Power Release 8/30/2022 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 9/6/2022 Approved RYAN SALAZAR
Gas Test 9/28/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 1/3/2023 Partial Inspection RAUL BARAJAS
ELECTRICAL-Final 1/5/2023 Approved RAUL BARAJAS
PLUMBING-Final 1/5/2023 Corrections Issued RAUL BARAJAS
HVAC-Final 1/19/2023 Partial Approval RAUL BARAJAS
PLUMBING-Final 2/9/2023 Corrections Issued RAUL BARAJAS
HVAC-Final 3/3/2023 Approved RAUL BARAJAS
PLUMBING-Final 3/3/2023 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/27/2023 Approved RAUL BARAJAS
Drywall Nailing 4/27/2023 Approved RAUL BARAJAS
Final 4/27/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/27/2023 Approved RAUL BARAJAS
Green Building Rough 4/27/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved RAUL BARAJAS
Smoke Detectors 4/27/2023 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 4/27/2023 Approved RAUL BARAJAS
Final 5/9/2023 Not Ready for Inspection RAUL BARAJAS
Final 5/24/2023 OK to Issue CofO RAUL BARAJAS