3981 S MOORE ST 90066

Certificate Information: 3981 S MOORE ST 90066

Application / Permit
16010-30000-01714
Plan Check / Job No.
B16WL02170
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 7-unit apartment bldg w/ subterranean garage
Permit Issued
Issued on 8/25/2017
Issuing Office
Valley
Current Status
CofO Issued on 5/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2016 APPLICANT
Assigned to Plan Check Engineer 5/12/2016 MANUEL GARCIA
Disabled Access Plans Picked Up 5/16/2016 APPLICANT
Green Plans Picked Up 5/19/2016 APPLICANT
Corrections Issued 6/2/2016 MANUEL GARCIA
Quality Review Completed 6/8/2016 GUANG MIN TUNG
Building Plans Picked Up 6/9/2016 APPLICANT
Applicant returned to address corrections 7/19/2016 MANUEL GARCIA
Applicant returned to address corrections 7/20/2016 MANUEL GARCIA
Applicant returned to address corrections 8/17/2016 MANUEL GARCIA
Applicant returned to address corrections 9/6/2016 MANUEL GARCIA
Applicant returned to address corrections 9/8/2016 MANUEL GARCIA
Applicant returned to address corrections 9/12/2016 MANUEL GARCIA
Plan Check Approved 9/20/2016 MANUEL GARCIA
Issued 8/25/2017 LADBS
CofO in Progress 2/10/2020 JASON BORUTA
Permit Finaled 5/5/2020 TED RIES
CofO Issued 5/5/2020 TED RIES
Permit Finaled 5/5/2020 TED RIES

Permit Application Clearance Information

Address approval Cleared 6/30/2016 ROBERT SAMONTE
Eng Process Fee Ord 176,300 Cleared 6/30/2016 ROBERT SAMONTE
Prkng lot landscape/Water mgmt Cleared 6/30/2016 HERMINIGILDO AGUSTIN
Sewer availability Cleared 6/30/2016 ROBERT SAMONTE
Work Adjacent to Public Way Cleared 6/30/2016 HUGO RICO
Hydrant and Access approval Cleared 7/6/2016 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 7/12/2016 TOM HENRY
Green Code Cleared 7/15/2016 BRYAN MEYER
Building over 3-story or 36-ft Cleared 7/19/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/19/2016 CALOSHA APPROVED
Specific Plan Cleared 7/19/2016 EDER ROMERO
DAS Clearance Cleared 7/20/2016 FARUK SEZER
Opn space landscape/Water mgmt Cleared 7/21/2016 TOM HENRY
Fire Marshall Fire Life Safety Cleared 7/22/2016 ANDREW KO
Low Impact Development Cleared 9/16/2016 RYAN HUDSON
Highway dedication Cleared 9/19/2016 LUZ RABELO
GPI Written Notices Cleared 9/20/2016 MANUEL GARCIA
Permit Cleared 9/20/2016 BRIAN KELLY
Roof/Waste drainage to street Cleared 9/20/2016 BRIAN KELLY

Contact Information

Architect Walters, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor J R Development Inc; Lic. No.: 561978-B 7525 ETHEL AVENUE UNIT K      NORTH HOLLYWOOD, CA 91605
Engineer Lee, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2017 No Access for Inspection TONY HARTONO
Pre-Inspection 10/2/2017 Approved JONATHAN ALLEN
Piling/Pier/Caisson 10/18/2017 Partial Inspection TONY HARTONO
Deputy Reinf. Concrete 11/28/2017 Approved JOHN DODGE
Footing/Foundation/Slab 12/4/2017 Not Ready for Inspection JASON BORUTA
Piling/Pier/Caisson 12/5/2017 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/1/2018 Partial Approval JOHN DODGE
Footing/Foundation/Slab 2/8/2018 Approved JASON BORUTA
Deputy Shotcrete 2/9/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/9/2018 Approved JASON BORUTA
Deputy Shotcrete 2/12/2018 Approved JASON BORUTA
Deputy Reinf. Concrete 2/13/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/15/2018 Corrections Issued SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 2/20/2018 Corrections Issued JASON BORUTA
Masonry Wall/Backfill 2/20/2018 Partial Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/23/2018 Not Ready for Inspection JASON BORUTA
Deputy Reinf. Concrete 2/26/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/26/2018 Partial Approval JASON BORUTA
Deputy Reinf. Concrete 2/27/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/5/2018 Partial Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/7/2018 Approved JASON BORUTA
Deputy Reinf. Concrete 3/8/2018 Approved JASON BORUTA
Special/Order Compliance 3/9/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/12/2018 Not Ready for Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/16/2018 Approved JASON BORUTA
Deputy Shotcrete 3/20/2018 Approved JASON BORUTA
Pre-Inspection 3/21/2018 Approved JASON BORUTA
Deputy Reinf. Masonry 3/23/2018 Approved JASON BORUTA
Masonry Wall/Backfill 4/2/2018 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 4/11/2018 Conditional Approval JASON BORUTA
Deputy Reinf. Concrete 4/12/2018 Approved JASON BORUTA
Masonry Wall/Backfill 4/27/2018 Conditional Approval JASON BORUTA
Green Building Rough 5/1/2018 Not Ready for Inspection JASON BORUTA
Reinforced Concrete Frame 5/1/2018 Not Ready for Inspection JASON BORUTA
Verify Sprinkler Sign Off 5/1/2018 Not Ready for Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 5/4/2018 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 5/11/2018 Partial Approval JASON BORUTA
Deputy Reinf. Concrete 5/15/2018 Approved JASON BORUTA
Pre-Inspection 5/24/2018 Approved JASON BORUTA
Deputy Steel/Welding 5/31/2018 Corrections Issued JOHN DODGE
Pre-Inspection 6/5/2018 Approved JASON BORUTA
Light Gage Steel Frame 6/6/2018 Not Ready for Inspection JASON BORUTA
Floor/Roof Diaphrgm/Shear Wall 6/8/2018 Partial Approval JASON BORUTA
Pre-Inspection 6/18/2018 Approved JASON BORUTA
Floor/Roof Diaphrgm/Shear Wall 6/25/2018 Approved JASON BORUTA
Floor/Roof Diaphrgm/Shear Wall 7/25/2018 Partial Approval JASON BORUTA
Green Building Rough 7/25/2018 Not Ready for Inspection JASON BORUTA
Verify Sprinkler Sign Off 7/25/2018 Not Ready for Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 8/30/2018 Approved JASON BORUTA
Floor/Roof Diaphrgm/Shear Wall 8/30/2018 Partial Approval JASON BORUTA
Green Building Rough 8/30/2018 Not Ready for Inspection JASON BORUTA
Verify Sprinkler Sign Off 8/30/2018 Not Ready for Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 9/5/2018 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 10/15/2018 Conditional Approval JOHN DODGE
Deputy Drilled-In Anchors 10/16/2018 Approved DERRICK SPENCER
Drywall Nailing 10/16/2018 Not Ready for Inspection DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 10/16/2018 Partial Approval DERRICK SPENCER
Green Building Rough 10/16/2018 Approved DERRICK SPENCER
Pre-Inspection 11/28/2018 Partial Inspection JASON BORUTA
Light Gage Steel Frame 11/30/2018 Partial Approval JASON BORUTA
Wood Frame 12/17/2018 Partial Approval JASON BORUTA
Insulation 12/21/2018 Partial Inspection JASON BORUTA
Pre-Inspection 1/7/2019 No Access for Inspection JASON BORUTA
Pre-Inspection 1/16/2019 Not Ready for Inspection JASON BORUTA
Verify Sprinkler Sign Off 1/25/2019 Approved JASON BORUTA
Wood Frame 1/25/2019 Conditional Approval JASON BORUTA
Insulation 2/1/2019 Partial Approval JASON BORUTA
Insulation 2/4/2019 Approved JASON BORUTA
Light Gage Steel Frame 2/5/2019 Partial Approval JASON BORUTA
Drywall Nailing 2/6/2019 Approved JASON BORUTA
Light Gage Steel Frame 2/6/2019 Partial Approval JASON BORUTA
Drywall Nailing 2/13/2019 Partial Approval JASON BORUTA
Drywall Nailing 2/19/2019 Approved JASON BORUTA
Interior/Exterior Lathing 2/22/2019 Partial Approval JASON BORUTA
Interior/Exterior Lathing 2/28/2019 Approved JASON BORUTA
Wood Frame 4/4/2019 Partial Inspection JASON BORUTA
Interior/Exterior Lathing 5/7/2019 Approved JASON BORUTA
Pre-Inspection 5/13/2019 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 5/24/2019 Approved JASON BORUTA
Footing/Foundation/Slab 6/3/2019 Approved JASON BORUTA
Final 9/4/2019 Partial Inspection JASON BORUTA
Green Building Final 9/4/2019 Partial Approval JASON BORUTA
Reinforced Concrete Frame 9/4/2019 Approved JASON BORUTA
SGSOV-Seismic Gas S/O Valve 9/4/2019 SGSOV Approved JASON BORUTA
Smoke Detectors 9/4/2019 Approved JASON BORUTA
Structural Steel Frame 9/4/2019 Approved JASON BORUTA
Wood Frame 9/4/2019 Approved JASON BORUTA
Final 11/15/2019 Partial Inspection JASON BORUTA
Green Building Final 11/15/2019 Approved JASON BORUTA
Final 1/23/2020 OK to Issue CofO JASON BORUTA
Special/Order Compliance 4/28/2020 Approved SORIN CIRSTOIU