Pre-Inspection
|
10/19/2016
|
Partial Inspection
|
CAMERON CHABAN
|
Footing/Foundation/Slab
|
12/9/2016
|
Partial Inspection
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
12/29/2016
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
12/29/2016
|
Partial Approval
|
JOHN KITCKO
|
Special/Order Compliance
|
1/9/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
1/17/2017
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
1/17/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
1/31/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/2/2017
|
Approved
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
2/22/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Shotcrete
|
2/23/2017
|
Approved
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
2/23/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
2/28/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/3/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/3/2017
|
Partial Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/3/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/6/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/7/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/8/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/9/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/10/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/10/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/10/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wall Anchors
|
3/10/2017
|
Partial Approval
|
JOHN KITCKO
|
Wall Anchors
|
3/11/2017
|
Off-Hour Fees Due
|
|
Wall Anchors
|
3/12/2017
|
Off-Hour Fees Due
|
|
Deputy Shotcrete
|
3/13/2017
|
Approved
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
3/13/2017
|
Partial Approval
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
3/13/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/14/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
3/14/2017
|
Not Ready for Inspection
|
ROLLIN GETTLE III
|
Interior/Exterior Lathing
|
3/14/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/14/2017
|
Partial Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/14/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
3/15/2017
|
Off-Hour Fees Due
|
|
Green Building Rough
|
3/17/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
3/17/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Structural Steel Frame
|
3/17/2017
|
Partial Approval
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/17/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
3/21/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
3/21/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
3/22/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/28/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
3/28/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
3/28/2017
|
Partial Approval
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/28/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/30/2017
|
Partial Approval
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
3/30/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Shotcrete
|
3/31/2017
|
Approved
|
JOHN KITCKO
|
Deputy Shotcrete
|
4/3/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
4/5/2017
|
Approved
|
JOHN KITCKO
|
Pre-Inspection
|
4/20/2017
|
Partial Inspection
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
4/27/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
4/28/2017
|
Approved
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
4/28/2017
|
Partial Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
4/28/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Structural Steel Frame
|
4/28/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Verify Sprinkler Sign Off
|
4/28/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
5/1/2017
|
Partial Approval
|
JOHN KITCKO
|
Structural Steel Frame
|
5/1/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/2/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/10/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
5/10/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
5/10/2017
|
Not Ready for Inspection
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/11/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
5/12/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
5/12/2017
|
Partial Inspection
|
JOHN KITCKO
|
Deputy Drilled-In Anchors
|
5/16/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
5/16/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/17/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/18/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
5/30/2017
|
No Access for Inspection
|
CAMERON CHABAN
|
Green Building Rough
|
5/30/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Deputy Reinf. Concrete
|
6/1/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
6/1/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Masonry Frame
|
6/1/2017
|
Partial Inspection
|
JOHN KITCKO
|
Green Building Rough
|
6/5/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
6/5/2017
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
Reinforced Masonry Frame
|
6/6/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
6/7/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
6/20/2017
|
Approved
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
6/20/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
7/13/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
7/20/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
7/21/2017
|
Approved
|
JOHN KITCKO
|
Green Building Rough
|
7/21/2017
|
Not Ready for Inspection
|
MICKEY YAMASHITA
|
Reinforced Concrete Frame
|
7/21/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
7/24/2017
|
Approved
|
JOHN KITCKO
|
Deputy Reinf. Concrete
|
7/26/2017
|
Conditional Approval
|
ROBERT COLE
|
Deputy Reinf. Concrete
|
7/27/2017
|
Approved
|
JEFFREY DURAN
|
Floor/Roof Diaphrgm/Shear Wall
|
8/21/2017
|
Conditional Approval
|
CAMERON CHABAN
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2017
|
Partial Approval
|
CAMERON CHABAN
|
Deputy Wood Construction
|
8/31/2017
|
Approved
|
JOHN KITCKO
|
Floor/Roof Diaphrgm/Shear Wall
|
9/1/2017
|
Partial Approval
|
DANNY RODRIGUEZ
|
Wood Frame
|
9/18/2017
|
Partial Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
11/7/2017
|
Conditional Approval
|
JOHN KITCKO
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2017
|
Partial Approval
|
CAMERON CHABAN
|
Floor/Roof Diaphrgm/Shear Wall
|
11/17/2017
|
Partial Approval
|
CAMERON CHABAN
|
Wood Frame
|
11/22/2017
|
Conditional Approval
|
JOHN KITCKO
|
Wood Frame
|
11/28/2017
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
12/1/2017
|
No Access for Inspection
|
JOHN KITCKO
|
Wood Frame
|
12/4/2017
|
Conditional Approval
|
JOHN KITCKO
|
Deputy Wood Construction
|
12/5/2017
|
Approved
|
JOHN KITCKO
|
Wood Frame
|
12/6/2017
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
12/20/2017
|
Partial Approval
|
JOHN KITCKO
|
Green Building Rough
|
1/25/2018
|
Approved
|
ROBERT DAVIS
|
Drywall Nailing
|
1/31/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
2/6/2018
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
2/6/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
2/9/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
2/14/2018
|
No Access for Inspection
|
JOHN KITCKO
|
Insulation
|
2/15/2018
|
Corrections Issued
|
JOHN KITCKO
|
Insulation
|
2/22/2018
|
Corrections Issued
|
JOHN KITCKO
|
Wood Frame
|
2/26/2018
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
2/27/2018
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
3/1/2018
|
Partial Inspection
|
JOHN KITCKO
|
Wood Frame
|
3/2/2018
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
3/6/2018
|
Partial Inspection
|
JOHN KITCKO
|
Wood Frame
|
3/9/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
3/15/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
Floor/Roof Diaphrgm/Shear Wall
|
3/16/2018
|
Partial Approval
|
CAMERON CHABAN
|
Deputy Drilled-In Anchors
|
3/19/2018
|
Conditional Approval
|
CAMERON CHABAN
|
Wood Frame
|
3/19/2018
|
Partial Approval
|
CAMERON CHABAN
|
Floor/Roof Diaphrgm/Shear Wall
|
3/23/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
3/23/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Floor/Roof Diaphrgm/Shear Wall
|
3/27/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
3/27/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
4/5/2018
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/6/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Wood Frame
|
4/6/2018
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/9/2018
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
4/9/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Insulation
|
4/11/2018
|
Partial Approval
|
JOHN KITCKO
|
Wood Frame
|
4/11/2018
|
Partial Approval
|
JOHN KITCKO
|
Insulation
|
4/18/2018
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
4/23/2018
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
4/24/2018
|
Conditional Approval
|
CAMERON CHABAN
|
Drywall Nailing
|
4/25/2018
|
Corrections Issued
|
JOHN KITCKO
|
Drywall Nailing
|
4/27/2018
|
Partial Approval
|
CAMERON CHABAN
|
Green Building Final
|
5/9/2018
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
5/10/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
5/11/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
5/11/2018
|
Partial Approval
|
JOHN KITCKO
|
Drywall Nailing
|
5/15/2018
|
Partial Approval
|
ROBERT DAVIS
|
Drywall Nailing
|
5/16/2018
|
Partial Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
5/17/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
5/18/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
5/23/2018
|
Partial Approval
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
5/29/2018
|
Partial Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
7/3/2018
|
Conditional Approval
|
CAMERON CHABAN
|
Footing/Foundation/Slab
|
7/5/2018
|
Conditional Approval
|
CAMERON CHABAN
|
Drywall Nailing
|
7/24/2018
|
Partial Approval
|
JOHN KITCKO
|
Interior/Exterior Lathing
|
8/31/2018
|
Not Ready for Inspection
|
CAMERON CHABAN
|
Interior/Exterior Lathing
|
9/6/2018
|
Conditional Approval
|
CAMERON CHABAN
|
Final
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Final
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
SGSOV-Seismic Gas S/O Valve
|
11/29/2018
|
SGSOV Not Ready
|
JOHN KITCKO
|
Smoke Detectors
|
11/29/2018
|
Not Ready for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
1/4/2019
|
Partial Approval
|
ROBERT DAVIS
|
Excavation/Setback/Form/Re-Bar
|
1/10/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
Excavation/Setback/Form/Re-Bar
|
1/11/2019
|
Partial Approval
|
JOHN KITCKO
|
Special/Order Compliance
|
1/28/2019
|
Partial Inspection
|
JOHN KITCKO
|
Drywall Nailing
|
2/26/2019
|
Partial Approval
|
JOHN KITCKO
|
Final
|
3/6/2019
|
Partial Inspection
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
3/6/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
Green Building Final
|
3/6/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
Reinforced Concrete Frame
|
3/6/2019
|
Approved
|
JOHN KITCKO
|
Reinforced Masonry Frame
|
3/6/2019
|
Approved
|
JOHN KITCKO
|
SGSOV-Seismic Gas S/O Valve
|
3/6/2019
|
SGSOV Not Ready
|
JOHN KITCKO
|
Smoke Detectors
|
3/6/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
Final
|
5/10/2019
|
Corrections Issued
|
JOHN KITCKO
|
Footing/Foundation/Slab
|
5/10/2019
|
Approved
|
JOHN KITCKO
|
Green Building Final
|
5/10/2019
|
Approved
|
JOHN KITCKO
|
SGSOV-Seismic Gas S/O Valve
|
5/10/2019
|
SGSOV Approved
|
JOHN KITCKO
|
Smoke Detectors
|
5/10/2019
|
Approved
|
JOHN KITCKO
|
Final
|
5/15/2019
|
Partial Inspection
|
JOHN KITCKO
|
Final
|
6/6/2019
|
OK to Issue CofO
|
JOHN KITCKO
|