12117 W VALLEYHEART DR 1-23 91604

Certificate Information: 12117 W VALLEYHEART DR 1-23 91604

Application / Permit
16010-30000-00818
Plan Check / Job No.
B16WL00996
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 23 UNIT APARTMENT BUILDING, 5 STORY W/ROOF DECK OVER 1 LEVEL SUBTERRANEAN GARAGE.
Permit Issued
Issued on 10/17/2016
Issuing Office
Metro
Current Status
CofO Issued on 6/19/2019
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2016 APPLICANT
Disabled Access Plans Picked Up 3/17/2016 APPLICANT
Assigned to Plan Check Engineer 3/24/2016 ARMEN JIVALAGIAN
Corrections Issued 4/1/2016 ARMEN JIVALAGIAN
Quality Review Completed 4/11/2016 BILL STUTSMAN
Applicant returned to address corrections 7/12/2016 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/27/2016 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/9/2016 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/10/2016 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/15/2016 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/23/2016 ARMEN JIVALAGIAN
Plan Check Approved 10/17/2016 ARMEN JIVALAGIAN
Issued 10/17/2016 LADBS
CofO in Progress 6/6/2019 JOHN KITCKO
Permit Finaled 6/19/2019 RICKEY JACKSON
CofO Issued 6/19/2019 RICKEY JACKSON
Permit Finaled 6/19/2019 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 4/7/2016 ARMEN DERMENJIAN
Eng Process Fee Ord 176,300 Cleared 4/7/2016 ARMEN DERMENJIAN
Permit Cleared 5/24/2016 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 5/24/2016 LEE GUILBEAUX
Highway dedication Cleared 6/1/2016 RICHARD SOUTHERLAND
Sewer availability Cleared 6/1/2016 RICHARD SOUTHERLAND
DAS Clearance Cleared 7/12/2016 SHINE LIN
Driveway location Cleared 7/14/2016 TAIMOUR TANAVOLI
Hydrant and Access approval Cleared 7/14/2016 ROBERT DUFF
Internal circulation Cleared 7/14/2016 TAIMOUR TANAVOLI
Fire Marshall Fire Life Safety Cleared 7/22/2016 PEJMAN NOORI
Bicycle Parking Cleared 8/4/2016 JACOB BIGLER
Frnt yard landscape/Water mgmt Cleared 8/4/2016 GRACIELA ACOSTA
ZI Cleared 8/4/2016 GRACIELA ACOSTA
Construction near power lines Cleared 8/9/2016 LUCIO FERRER
Green Code Cleared 8/30/2016 ARMEN JIVALAGIAN
Building over 3-story or 36-ft Cleared 9/8/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/8/2016 CALOSHA APPROVED
Opn space landscape/Water mgmt Cleared 9/21/2016 RICK TORRES
Low Impact Development Cleared 10/11/2016 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 10/17/2016 RAVIL MANAPOV

Contact Information

Architect Albert, Stephen M; Lic. No.: C9412 2032 STONER AVE      LOS ANGELES, CA 90025
Contractor Hy-Max Building Corp; Lic. No.: 702339-B 28376 CONSTELLATION ROAD      VALENCIA, CA 91355
Engineer Aoanan, Virgilio Cendana; Lic. No.: C36079 3951 MEDFORD ST      LOS ANGELES, CA 90063
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

JOHN KITCKO, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2016 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 12/9/2016 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 12/29/2016 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/29/2016 Partial Approval JOHN KITCKO
Special/Order Compliance 1/9/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/17/2017 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/17/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/31/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 2/2/2017 Approved JOHN KITCKO
Footing/Foundation/Slab 2/22/2017 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 2/23/2017 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/23/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/28/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/3/2017 Approved JOHN KITCKO
Reinforced Concrete Frame 3/3/2017 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 3/3/2017 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 3/6/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/7/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/8/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/9/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/10/2017 Approved JOHN KITCKO
Reinforced Concrete Frame 3/10/2017 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 3/10/2017 Not Ready for Inspection JOHN KITCKO
Wall Anchors 3/10/2017 Partial Approval JOHN KITCKO
Wall Anchors 3/11/2017 Off-Hour Fees Due
Wall Anchors 3/12/2017 Off-Hour Fees Due
Deputy Shotcrete 3/13/2017 Approved JOHN KITCKO
Footing/Foundation/Slab 3/13/2017 Partial Approval JOHN KITCKO
Reinforced Masonry Frame 3/13/2017 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 3/14/2017 Approved JOHN KITCKO
Green Building Rough 3/14/2017 Not Ready for Inspection ROLLIN GETTLE III
Interior/Exterior Lathing 3/14/2017 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 3/14/2017 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 3/14/2017 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 3/15/2017 Off-Hour Fees Due
Green Building Rough 3/17/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 3/17/2017 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 3/17/2017 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 3/17/2017 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 3/21/2017 Approved JOHN KITCKO
Reinforced Masonry Frame 3/21/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/22/2017 Approved JOHN KITCKO
Deputy Shotcrete 3/28/2017 Approved JOHN KITCKO
Green Building Rough 3/28/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 3/28/2017 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 3/28/2017 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 3/30/2017 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 3/30/2017 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 3/31/2017 Approved JOHN KITCKO
Deputy Shotcrete 4/3/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/5/2017 Approved JOHN KITCKO
Pre-Inspection 4/20/2017 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 4/27/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/28/2017 Approved JOHN KITCKO
Footing/Foundation/Slab 4/28/2017 Partial Inspection JOHN KITCKO
Reinforced Concrete Frame 4/28/2017 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 4/28/2017 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 4/28/2017 Approved JOHN KITCKO
Reinforced Masonry Frame 5/1/2017 Partial Approval JOHN KITCKO
Structural Steel Frame 5/1/2017 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 5/2/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/10/2017 Approved JOHN KITCKO
Green Building Rough 5/10/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 5/10/2017 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 5/11/2017 Approved JOHN KITCKO
Green Building Rough 5/12/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 5/12/2017 Partial Inspection JOHN KITCKO
Deputy Drilled-In Anchors 5/16/2017 Approved JOHN KITCKO
Reinforced Masonry Frame 5/16/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/17/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/18/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/30/2017 No Access for Inspection CAMERON CHABAN
Green Building Rough 5/30/2017 Not Ready for Inspection MICKEY YAMASHITA
Deputy Reinf. Concrete 6/1/2017 Approved JOHN KITCKO
Green Building Rough 6/1/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Masonry Frame 6/1/2017 Partial Inspection JOHN KITCKO
Green Building Rough 6/5/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 6/5/2017 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/6/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/7/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 6/20/2017 Approved JOHN KITCKO
Reinforced Concrete Frame 6/20/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/13/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/20/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/21/2017 Approved JOHN KITCKO
Green Building Rough 7/21/2017 Not Ready for Inspection MICKEY YAMASHITA
Reinforced Concrete Frame 7/21/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/24/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 7/26/2017 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 7/27/2017 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2017 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2017 Partial Approval CAMERON CHABAN
Deputy Wood Construction 8/31/2017 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/1/2017 Partial Approval DANNY RODRIGUEZ
Wood Frame 9/18/2017 Partial Approval JOHN KITCKO
Deputy Wood Construction 11/7/2017 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/8/2017 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2017 Partial Approval CAMERON CHABAN
Wood Frame 11/22/2017 Conditional Approval JOHN KITCKO
Wood Frame 11/28/2017 Partial Approval JOHN KITCKO
Wood Frame 12/1/2017 No Access for Inspection JOHN KITCKO
Wood Frame 12/4/2017 Conditional Approval JOHN KITCKO
Deputy Wood Construction 12/5/2017 Approved JOHN KITCKO
Wood Frame 12/6/2017 Partial Approval JOHN KITCKO
Insulation 12/20/2017 Partial Approval JOHN KITCKO
Green Building Rough 1/25/2018 Approved ROBERT DAVIS
Drywall Nailing 1/31/2018 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 2/6/2018 Partial Approval JOHN KITCKO
Insulation 2/6/2018 Not Ready for Inspection JOHN KITCKO
Insulation 2/9/2018 Not Ready for Inspection JOHN KITCKO
Insulation 2/14/2018 No Access for Inspection JOHN KITCKO
Insulation 2/15/2018 Corrections Issued JOHN KITCKO
Insulation 2/22/2018 Corrections Issued JOHN KITCKO
Wood Frame 2/26/2018 Partial Approval JOHN KITCKO
Wood Frame 2/27/2018 Partial Approval JOHN KITCKO
Wood Frame 3/1/2018 Partial Inspection JOHN KITCKO
Wood Frame 3/2/2018 Partial Approval JOHN KITCKO
Wood Frame 3/6/2018 Partial Inspection JOHN KITCKO
Wood Frame 3/9/2018 Not Ready for Inspection JOHN KITCKO
Wood Frame 3/15/2018 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/16/2018 Partial Approval CAMERON CHABAN
Deputy Drilled-In Anchors 3/19/2018 Conditional Approval CAMERON CHABAN
Wood Frame 3/19/2018 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2018 Not Ready for Inspection JOHN KITCKO
Wood Frame 3/23/2018 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/27/2018 Not Ready for Inspection JOHN KITCKO
Wood Frame 3/27/2018 Not Ready for Inspection JOHN KITCKO
Wood Frame 4/5/2018 Partial Approval JOHN KITCKO
Insulation 4/6/2018 Not Ready for Inspection JOHN KITCKO
Wood Frame 4/6/2018 Partial Approval JOHN KITCKO
Insulation 4/9/2018 Partial Approval JOHN KITCKO
Wood Frame 4/9/2018 Not Ready for Inspection JOHN KITCKO
Insulation 4/11/2018 Partial Approval JOHN KITCKO
Wood Frame 4/11/2018 Partial Approval JOHN KITCKO
Insulation 4/18/2018 Partial Approval JOHN KITCKO
Drywall Nailing 4/23/2018 Partial Approval JOHN KITCKO
Drywall Nailing 4/24/2018 Conditional Approval CAMERON CHABAN
Drywall Nailing 4/25/2018 Corrections Issued JOHN KITCKO
Drywall Nailing 4/27/2018 Partial Approval CAMERON CHABAN
Green Building Final 5/9/2018 Partial Approval JOHN KITCKO
Drywall Nailing 5/10/2018 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 5/11/2018 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 5/11/2018 Partial Approval JOHN KITCKO
Drywall Nailing 5/15/2018 Partial Approval ROBERT DAVIS
Drywall Nailing 5/16/2018 Partial Inspection JOHN KITCKO
Drywall Nailing 5/17/2018 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 5/18/2018 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 5/23/2018 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 5/29/2018 Partial Inspection JOHN KITCKO
Drywall Nailing 7/3/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 7/5/2018 Conditional Approval CAMERON CHABAN
Drywall Nailing 7/24/2018 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 8/31/2018 Not Ready for Inspection CAMERON CHABAN
Interior/Exterior Lathing 9/6/2018 Conditional Approval CAMERON CHABAN
Final 11/29/2018 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 11/29/2018 Not Ready for Inspection JOHN KITCKO
Green Building Final 11/29/2018 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 11/29/2018 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 11/29/2018 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 11/29/2018 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 11/29/2018 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/4/2019 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/10/2019 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/11/2019 Partial Approval JOHN KITCKO
Special/Order Compliance 1/28/2019 Partial Inspection JOHN KITCKO
Drywall Nailing 2/26/2019 Partial Approval JOHN KITCKO
Final 3/6/2019 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 3/6/2019 Not Ready for Inspection JOHN KITCKO
Green Building Final 3/6/2019 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 3/6/2019 Approved JOHN KITCKO
Reinforced Masonry Frame 3/6/2019 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 3/6/2019 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 3/6/2019 Not Ready for Inspection JOHN KITCKO
Final 5/10/2019 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 5/10/2019 Approved JOHN KITCKO
Green Building Final 5/10/2019 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 5/10/2019 SGSOV Approved JOHN KITCKO
Smoke Detectors 5/10/2019 Approved JOHN KITCKO
Final 5/15/2019 Partial Inspection JOHN KITCKO
Final 6/6/2019 OK to Issue CofO JOHN KITCKO