Excavation/Setback/Form/Re-Bar
|
9/12/2016
|
Corrections Issued
|
ANTHONY ANDERSON
|
Piling/Pier/Caisson
|
11/7/2016
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
Deputy Reinf. Concrete
|
11/9/2016
|
Conditional Approval
|
ANTHONY ANDERSON
|
Footing/Foundation/Slab
|
1/17/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Deputy Reinf. Concrete
|
1/19/2017
|
Approved
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
2/14/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
2/22/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
3/6/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Footing/Foundation/Slab
|
3/8/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
3/9/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Excavation/Setback/Form/Re-Bar
|
3/14/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
3/30/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
3/31/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
4/3/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
4/7/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
4/27/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Floor/Roof Diaphrgm/Shear Wall
|
5/8/2017
|
Partial Approval
|
KENNETH NAGLE
|
Deputy Steel/Welding
|
5/9/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
5/10/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
5/15/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
5/16/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
5/19/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
5/23/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Floor/Roof Diaphrgm/Shear Wall
|
5/24/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Sewer
|
6/8/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Pre-Inspection
|
7/19/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Underground Mechanical
|
7/19/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Floor/Roof Diaphrgm/Shear Wall
|
7/31/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Green Building Rough
|
7/31/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
Verify Sprinkler Sign Off
|
7/31/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
Special/Order Compliance
|
8/5/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Green Building Rough
|
8/17/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
8/17/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Sewer
|
8/17/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Structural Steel Frame
|
8/17/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Verify Sprinkler Sign Off
|
8/17/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
Wood Frame
|
8/17/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
9/18/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
9/20/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
ELECTRICAL-Rough
|
9/28/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Pre-Inspection
|
9/28/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Floor/Roof Diaphrgm/Shear Wall
|
10/10/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Green Building Rough
|
10/10/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
Structural Steel Frame
|
10/10/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Verify Sprinkler Sign Off
|
10/10/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
HVAC-Rough
|
10/17/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
10/17/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
10/30/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
11/9/2017
|
Corrections Issued
|
ANTHONY ANDERSON
|
ELECTRICAL-Rough
|
11/15/2017
|
Approved
|
ANTHONY ANDERSON
|
HVAC-Rough
|
11/28/2017
|
Approved
|
ANTHONY ANDERSON
|
BUILDING-Rough-Frame
|
12/11/2017
|
Corrections Issued
|
ANTHONY ANDERSON
|
Green Building Rough
|
12/11/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
Verify Sprinkler Sign Off
|
12/11/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
Underground Mechanical
|
12/19/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
12/28/2017
|
Approved
|
ANTHONY ANDERSON
|
Deputy Steel/Welding
|
12/29/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
Underground Mechanical
|
1/5/2018
|
Partial Approval
|
MATT KELLERMAN
|
Deputy Steel/Welding
|
1/11/2018
|
Conditional Approval
|
ANTHONY ANDERSON
|
Footing/Foundation/Slab
|
1/16/2018
|
Partial Approval
|
THOMAS FINNILA
|
Green Building Rough
|
2/1/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
Structural Steel Frame
|
2/1/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
Verify Sprinkler Sign Off
|
2/1/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
Sewer
|
2/15/2018
|
Partial Approval
|
ANTHONY ANDERSON
|
ELECTRICAL-Rough
|
2/22/2018
|
Approved
|
JOEL LAUNCHBAUGH
|
Deputy Drilled-In Anchors
|
2/23/2018
|
Conditional Approval
|
ANTHONY ANDERSON
|
PLUMBING-Rough
|
3/13/2018
|
Approved
|
ANTHONY ANDERSON
|
BUILDING-Rough-Frame
|
3/14/2018
|
Approved
|
ANTHONY ANDERSON
|
Green Building Rough
|
3/14/2018
|
Approved
|
ANTHONY ANDERSON
|
Interior/Exterior Lathing
|
3/14/2018
|
Corrections Issued
|
ANTHONY ANDERSON
|
Verify Sprinkler Sign Off
|
3/14/2018
|
Approved
|
ANTHONY ANDERSON
|
Drywall Nailing
|
3/28/2018
|
Approved
|
ANTHONY ANDERSON
|
Insulation
|
3/28/2018
|
Approved
|
ANTHONY ANDERSON
|
Shower Pan
|
4/3/2018
|
Approved
|
ANTHONY ANDERSON
|
Interior/Exterior Lathing
|
4/9/2018
|
Partial Approval
|
THOMAS FINNILA
|
Interior/Exterior Lathing
|
4/16/2018
|
Corrections Issued
|
JONATHAN HOM
|
Interior/Exterior Lathing
|
4/24/2018
|
Partial Approval
|
ANTHONY ANDERSON
|
Interior/Exterior Lathing
|
5/8/2018
|
Approved
|
JONATHAN HOM
|
Shower Pan
|
5/21/2018
|
Partial Approval
|
MATT KELLERMAN
|
Interior/Exterior Lathing
|
6/5/2018
|
Approved
|
JONATHAN HOM
|
Gas Test
|
6/22/2018
|
Approved
|
JOEL LAUNCHBAUGH
|
PLUMBING-Rough
|
6/22/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
Underground Mechanical
|
6/22/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
Underground Mechanical
|
6/29/2018
|
Approved
|
JOEL LAUNCHBAUGH
|
Pre-Inspection
|
9/17/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
ELECTRICAL-Rough
|
10/24/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Underground Mechanical
|
10/24/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
ELECTRICAL-Final
|
11/29/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
PLUMBING-Final
|
11/29/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
ELECTRICAL-Rough
|
12/4/2018
|
Corrections Issued
|
JOEL LAUNCHBAUGH
|
PLUMBING-Rough
|
12/4/2018
|
Conditional Approval
|
JOEL LAUNCHBAUGH
|
ELECTRICAL-Rough
|
12/19/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
Underground Mechanical
|
12/19/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
ELECTRICAL-Final
|
1/16/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
Pre-Inspection
|
1/16/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
ELECTRICAL-Rough
|
2/11/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
Underground Mechanical
|
2/11/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Footing/Foundation/Slab
|
2/21/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
Underground Mechanical
|
2/21/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
Service/Power Release
|
3/27/2019
|
Approved
|
CHRISTOPHER WILSON
|
Final
|
4/5/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Footing/Foundation/Slab
|
4/5/2019
|
Approved
|
CHRISTOPHER WILSON
|
Green Building Final
|
4/5/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Pre-Inspection
|
4/5/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
SGSOV-Seismic Gas S/O Valve
|
4/5/2019
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
Smoke Detectors
|
4/5/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
Structural Steel Frame
|
4/5/2019
|
Approved
|
CHRISTOPHER WILSON
|
PLUMBING-Final
|
7/8/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
Green Building Final
|
10/7/2019
|
Not Ready for Inspection
|
MATT KELLERMAN
|
HVAC-Final
|
10/7/2019
|
Not Ready for Inspection
|
MATT KELLERMAN
|
Grading Pre-Inspection
|
10/28/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
Green Building Final
|
10/28/2019
|
Approved
|
ANTHONY MCDOWALL
|
HVAC-Final
|
10/28/2019
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
ELECTRICAL-Final
|
10/31/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
PLUMBING-Final
|
10/31/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
ELECTRICAL-Final
|
11/4/2019
|
Corrections Issued
|
ANTHONY MCDOWALL
|
HVAC-Final
|
11/4/2019
|
Approved
|
ANTHONY MCDOWALL
|
ELECTRICAL-Final
|
11/8/2019
|
Approved
|
CHRISTOPHER WILSON
|
Final
|
11/8/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
SGSOV-Seismic Gas S/O Valve
|
11/8/2019
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
Smoke Detectors
|
11/8/2019
|
Approved
|
CHRISTOPHER WILSON
|
Final
|
12/5/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
Final
|
12/6/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|