2311 N VASANTA WAY 90068

Certificate Information: 2311 N VASANTA WAY 90068

Application / Permit
16010-20004-03877
Plan Check / Job No.
B21VN14430
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT FOR 16010-20000-03877 TO EXTEND (E) FRONT ENTRY/STAIRS ON 1ST & 2ND FLRS (2'-9" X 20'-6"), 2ND FLR LIVING ROOM (8'-3" X 37'-1") & 3RD FLR MASTER BEDROOM (8'-1" X 33'-1") TO (E) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT); REVISE FLOOR PLANS
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
Permit Finaled on 8/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 NILOOFAR MEHRAIN
Corrections Issued 11/9/2021 NILOOFAR MEHRAIN
Quality Review Completed 11/9/2021 STEVEN KIM
Building Plans Picked Up 11/10/2021 APPLICANT
Applicant returned to address corrections 2/16/2022 NILOOFAR MEHRAIN
Plan Check Approved 3/2/2022 NILOOFAR MEHRAIN
Issued 3/9/2022 APPLICANT
Permit Finaled 8/15/2022 BRIAN SULLIVAN

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/17/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 11/17/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 11/17/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 11/17/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 11/17/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/20/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 2/8/2022 CELINA MORENO
Hydrant and Access approval Cleared 2/11/2022 KURT CORRAL

Contact Information

Contractor Martinez Jose Luis; Lic. No.: 602195-B 2426 ASPEN DRIVE      LOS ANGELES, CA 90068
Engineer Watry, Stephen Matthew; Lic. No.: GE2238 820 IDYLBERRY RD      SAN RAFAEL, CA 94903
Engineer Yaghi, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866
Geologist Watry, Stephen Matthew; Lic. No.: EG1260 820 IDYLBERRY ROAD      SAN RAFAEL, CA 94903

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/30/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 4/5/2022 Approved BRIAN SULLIVAN
Green Building Rough 4/5/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 6/29/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 6/29/2022 Approved STUART CHAPMAN
PLUMBING-Final 6/29/2022 Approved STUART CHAPMAN
Reinforced Concrete Frame 6/29/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 7/1/2022 Corrections Issued RAUL BARAJAS
Service/Power Release 7/7/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/8/2022 Partial Inspection SCOTT FINNILA
Final 8/8/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 8/8/2022 Conditional Approval SCOTT FINNILA
Green Building Final 8/8/2022 Approved SCOTT FINNILA
Smoke Detectors 8/8/2022 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 8/8/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/15/2022 Approved BRIAN SULLIVAN
Final 8/15/2022 Permit Finaled BRIAN SULLIVAN
Footing/Foundation/Slab 8/15/2022 Approved BRIAN SULLIVAN
Gas Test 8/15/2022 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 8/15/2022 Approved BRIAN SULLIVAN